FA5240-16-T-0001_RFI_Responses_23Jan2016.pdf

PDF 29 KB Posted

Attached to
Concrete IDIQ Federal contract opportunity
Solicitation number
FA5240-16-T-0001
Issued by
Department of the Air Force Pacific Air Forces

About this file

RFI Responses 23 Jan 2016

View the file

Other files for this federal contract opportunity

Other files attached to Concrete IDIQ, newest first.
File Type Posted
FA5240-16-T-0001-0002.pdf PDF
FA5240-16-T-0001-0001_Attachment_1_-_Statement_of_Work.pdf PDF
FA5240-16-T-0001-0001_Comformed_Copy.pdf PDF
FA5240-16-T-0001-0001.pdf PDF
FA5240-16-T-0001_EXHIBITS_-_Pricing_Schedule.xlsx XLSX spreadsheet
FA5240-16-T-0001_Attachment_1_-_Statement_of_Work.pdf PDF
FA5240-16-T-0001.pdf PDF
FA5240-16-T-0001_EXHIBITS_A_B_and_C_-_Pricing_Schedule.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5240-16-T-0001 CONCRETE IDIQ

REQUESTS FOR INFORMATION

23 JANUARY 2016

QUESTION 1: The RFQ indicates a submission date of January 31, 2016, which falls on a Sunday. Could you please confirm if this is the correct submission date?

RESPONSE 1: Yes, quotes are due NLT 31 Jan 2016.

QUESTION 2: Is there a bid bond or bonding capability letter requirement for this solicitation?

RESPONSE 2: No bid bond or bonding capability is required for this solicitation.

QUESTION 3: Statement of work says that “contractor shall provide quality control test results of all materials in accordance with the specifications for each mixtures…” please provide the indicated specification.

RESPONSE 3: The specifiactions are included in the ELIN descriptions. This refers to the PSI specifcations on each line.

QUESTION 4: Pump truck fee will vary depending on length of boom like 28 meter, 36 meter, and 47 meter which are all commonlyavailable in the market. However ‘Pricing Schedule’ did not indicate the size of equipment. Please provide the guideline how to price the ‘Pump Truck Fee’ in pricing schedule.

RESPONSE 4: If it is necessary to deviate from the pricing schedule posted with the solicitation (Exhibits A, B and C), please provide a quote for the smaller boom on the Exhibit document, and provide a separate document with pricing for additional booms with a narrative explaining why the deviation is necessary.