IMPORTANT NOTICE 2.doc
DOC document 23 KB Posted
- Solicitation number
- FA524009R0018
About this file
This is a response to an inquiry as well as an important notice regarding the outstanding water line drawings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA5240-09-R-0018 Amendment 3.doc | DOC document | |
| FA5240-09-R-0018 Amendment 2.doc | DOC document | |
| Water Tank Repair Clarification.doc | DOC document | |
| IMPORTANT NOTICE.doc | DOC document | |
| RFI Responses.doc | DOC document | |
| FA5240-09-R-0018 Amendment 1.doc | DOC document | |
| Pricing Schedule.xls | XLS spreadsheet | |
| Pre-proposal Mins.doc | DOC document | |
| FA5240-09-R-0018 - Specifications.zip | ZIP file | |
| FA5240-09-R-0018.pdf | ||
| FA5240-09-R-0018 - Drawings.zip | ZIP file | |
| FA5240-09-R-0018 - Pricing Schedule.zip | ZIP file | |
| Attachment J-1 - Statement of Work- AJJW 07-1144-47 Rpr Water System | — | |
| Attachment J-7 - Guam Labor Rates Effective 7-2008.pdf | ||
| Attachment 5 - Questionnaire Cover Ltr.pdf | ||
| Attachment J-6 - 2007 Annual Precipitation Report.pdf | ||
| Attachment J-7 - Guam Labor Rates Effective 7-2008.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IMPORTANT NOTICE
We request clarification regarding the Performance period for the four Recovery projects. Are these projects will be issued NTPs simultaneously? If so, then the maximum contract time will be 300 days, right? If this is the case are we required to assign four teams for the site supervision, safety and QC for each location or just 1 team for the whole contract? Please advise as this will be a price factor in the proposal.
Response: Maximum period of performance for all four projects combined will be 300 calendar days, therefore, all 4 projects will be worked on simultaneously. Note: The contractor will have to complete the by-pass before work is iniated on the Santa Rosa water tank. Only 1 team for site supervision, safety, and QC will be required for this contract.
ATTENTION:
CD's with as-built drawings of existing water line from Wells 5-9 to Booster Pump Station No. 3 and from Booster Pump Station No. 3 to Santa Rosa Water Tank are now available. Please stop by the 36th Contracting Squadron, Unit 14040, APO-AP 96543-4040 to get a copy (limit 1 per contractor). Your POC for this request will be A1C Jason C. Kimpel @ 366-1709.