This is a Performance Work Statement (PWS) for HVAC VAV and Thermostat Replacement services at Joint Base Pearl Harbor-Hickam. The contract involves the removal of 26 broken Variable Air Volume (VAV) controllers and 26 thermostats from Building 4069 (Moffett Street, Hickam Field) and installation of 26 new customer-provided VAV controllers and 26 new thermostats. The contractor is responsible for all associated work including ceiling tile removal, wiring replacement and repair, site restoration, and ensuring all new components function properly. The project will be awarded on a competitive basis using total project cost. A site visit may be requested to validate actual site conditions and programming needs.

The contractor must provide certified professionals for removal and installation work, with an authorized representative maintaining physical presence throughout the project unless otherwise agreed by the Contracting Officer Representative (COR). Key requirements include compliance with federal, state, and local laws; provision of a contract manager within 10 business days of award; employment of licensed electricians paid per Davis-Bacon wage determination HI20250001; submission of personnel lists complying with REAL ID Act requirements; and customer service availability during standard duty hours (0730-1630, Monday-Friday, excluding federal holidays). The contractor bears liability for damage to government property and must complete a post-installation walkthrough with the COR to address any punch list items. Base access requires navigation of security procedures at the Kuntz Commercial Gate with current vehicle registration, proof of insurance, and valid driver's licenses. Three primary deliverables are defined: removal (CDRL A001), installation (CDRL A002), and electrician/electrical work if required (CDRL A003). Performance objectives require no more than one customer complaint per removal and installation with 24-hour resolution, and zero unresolved punch list items prior to project completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

CUI

735 AMS Performance Work Statement (PWS)

HVAC VAV and Thermostat Replacement

Version 1.0

Joint Base Pearl Harbor-Hickam, USA

08 June 2026

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

Table of Contents

1.0 Background cover sheet or appendix

2.0 Scope

3.0 Description of Work

3.1 General Services

3.2 Assembly, Installation and Removal Work

3.3 Inspection/Acceptance Checklist

4.0 Government Furnished Support

5.0 Site Conditions

6.0 Voluntary Protection Program (VPP)/Safety

7.0 Base/Installation Specifics

8.0 Deliverables (CDRLs)

9.0 Performance Objective Summary

Revision History

Author Name Date Reason For Changes Version

Garron 04/08/2026 Initial Draft 1.0

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

1.0 Background

This Performance Work Statement (PWS) facilitates the removal of 26 broken Variable Air Volume (VAV) controllers, 26 thermostats, and any necessary associated hardware and replacing them with 26 new VAVs and 26 new thermostats that are provided by the customer.

The contractor shall remove the 26 failed VAV controllers in building 4069 and replace them with 26 new VAV controllers. The contractor will also remove and replace the 26 associated thermostats. The contractor will perform associated work related to these tasks and ensure all new components are in proper working order.

2.0 Scope

This project is to provide the removal and installation of customer provided VAV controllers and thermostats and will be awarded on a competitive basis using total project cost. This will include all associated work as required, such as removing ceiling tiles to access work area, replacing wiring, repairing wiring, returning site to original conditions, and so on.

A site visit may be requested if needed.

For this project we require the following items to be removed and installed:

Building 4069Moffet Street Hickam Field Remove 26 damaged/broken VAV controllers Install 26 new VAV controllers and provide any associated wiring as needed Remove the 26 associated thermostats Install 26 new thermostats and provide any associated wiring as needed

It is the responsibility of the contractor to validate the actual site conditions as well as any specific programming needs of the customer. Assistance will be provided from the customer that meets the customer requirements and accommodates the physical environment for consideration as part of proposal. The customer may assist with equipment if they have it available.

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

3.0 Description of Work

3.1 General Services

Coordination and management of all product, equipment and people required to remove and install the aforementioned VAV controllers and thermostats within an Air Force location.

3.1.1 The contractor shall be responsible for all personnel, equipment, tools, materials, supervision, storage, incidentals and all other items and services necessary to remove and install the VAV controllers and thermostats.

3.1.2 The contractor shall be knowledgeable of and shall comply with all applicable federal, state, and local laws, codes, permits, DoD, AF, and base requirements and instructions required for the performance of the duties in this Performance Work Statement (PWS).

3.1.3 The contractor shall ensure policies and procedures are established that protect the safety and welfare of customers, employees, and the community to minimize or eliminate safety or environmental risks. These policies shall be in compliance with Federal and Installation policies and procedures.

3.1.4 The contractor shall provide a contract manager or team leader who shall be responsible for the performance of the work. The name of this person and an alternate or alternates who shall act for the contractor when the manager is absent shall be designated in writing to the Contracting Officer (CO) and the Contracting Officer Representative (COR) within 10 business days after contract award. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to the daily operations of this contract on the installation.

3.1.5 The contractor shall provide a Project Manager with experience assembling and installing the company's product, responsible for project site management, scheduling, coordination and technical assistance to the Air Force representative as required throughout the project. Resumes and letters of intent shall be provided upon request.

3.1.6 Any electrician provided by the contractor shall be a licensed electrical contractor. The electrician will be paid in accordance with Davis-Bacon wage determination HI20250001.

3.1.7 The contractor shall submit a complete list of personnel in accordance with installation policy, including deliverymen, who will be expected to work on the installation. This list will contain Privacy Act information as required as well as the expectation that each individual will be able to present a current and valid state/federal identification complying with the REAL ID Act, to meet local Air Force security requirements. (Please note that many installations require this information be coordinated days in advance).

3.1.8 The contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees.

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

3.1.9 The contractor shall manage removal and installation of the 26 provided VAV controllers and thermostats to final acceptance by the COR.

3.1.10 The contractor shall provide customer service during normal duty hours, 0730-1630 hours, Monday through Friday; except for federal holidays.

3.1.11 Recognized US Federal Holidays are as follows: New Year’s Day, Birthday of Martin Luther King Jr., Washington’s Birthday, Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day. If the holiday falls on a Saturday, it is observed on Friday. If the holiday falls on Sunday, it is observed on Monday.

3.1.12 When the contractor desires to work other than standard times, a written request shall be submitted to the COR for approval. Written approval and/or a contract modification from the CO must be received before proceeding with the work. The request shall be submitted at least five (5) workdays prior to the proposed performance of work, and it shall indicate the day/days, time/amount of work, and reason why performance is necessary during nonstandard hours.

3.1.13 The contractor shall provide alternate work locations for employees or allow employees to take vacation during designated Government non-workdays or other periods where government offices are closed.

3.1.14 All Air Force inquiries shall be responded to by a contractor representative within two business days.

3.1.15 Meetings may periodically be held between base personnel and contractor management to discuss contract status. The COR will notify the contractor in writing in advance of the place and time of required meetings and notify and include the CO as needed.

3.1.16 The contractor shall be responsible for coordination of an escort through any controlled areas through the local COR.

3.1.17 Lost vehicle and entry passes shall be reported immediately to the Security Police as well as the COR in accordance with the local security forces policy.

3.1.18 The contractor shall be responsible for any storage of all equipment, parts and assemblies prior to and during removal and installation in accordance with the agreed upon schedule.

3.1.19 The contractor shall maintain continuity between the support operations at the 735 AMS, Bldg 4069, 2048 Moffett Street, JBPHH, HI, 96853 and all other assigned performance locations and the contractor’s corporate offices. The contractor shall provide the necessary resources to manage and administer the contract. The contractor shall, as a minimum, maintain a single point of contact for this effort to be available in person to the 735 AMS, during the same business day.

3.1.20 The contractor shall provide for the management and support of personnel, to include: making necessary arrangements for employees required to travel; supporting personnel co-located on 735 AMS, Bldg 4069, 2048 Moffett Street, JBPHH, HI, 96853 and other locations specified with additional resources, expertise, advice; necessary infrastructure to support work to be accomplished off-base; conducting personnel meetings;

providing administrative support for employees in a timely fashion; and providing facility and staff security requirements.

3.1.21 All personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government officials. They must also ensure

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

3.2 Assembly, Installation and Removal Work

Certified professionals to remove and install Carrier compatible VAV controllers and thermostats.

3.2.1 The contractor shall appoint an authorized representative who will be the company's senior representation on site for all customer communication and enforce compliance of all requirements for the project. This representative shall have a physical presence throughout removal and installation unless agreed to by the COR.

3.2.2 The contractor representative shall meet with COR to review the installation plans prior to installation.

3.2.3 The contractor shall remove and install fuel pit lids in accordance with each requirement statement and basic plan provided by the customer.

3.2.4 Contractor shall be liable for any damage to government property caused by the contractor or their representatives.

3.2.5 During removal and installation, the contractor shall protect the work site from further damage. The government may make repairs and back charge the installation contractor.

3.2.6 Services shall include product transportation of existing inventory as required.

3.2.7 Services shall include installation of product to conform to final CO and/or COR approval.

3.2.8 Services shall include removal of any packing materials used during transport or installation.

3.2.9 All trash removed from the worksite shall be disposed of in accordance with state laws, and packaging and other recyclable materials shall be recycled wherever possible.

3.2.10 The contractor shall maintain environmental controls when working in any government facility, to include but not limited to keeping doors shut and lights off when not in use and turning off vehicle engines when parked.

3.2.11 The contractor shall provide all components, completely assembled, installed, and operational.

3.2.12 The contractor shall inspect to ensure the VAV controllers and thermostats are free of surface dirt and defects, the installation is complete, and the items are ready for use.

3.3 Inspection/Acceptance Checklist

Validation between the contractor and the COR that all products have been installed according to manufacturer guidelines and/or customer specifications.

3.3.1 A post-installation walkthrough shall be coordinated with the contractor’s authorized representative and COR.

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

3.3.2 All areas requiring correction shall be documented in a punch list by the contractor and provided to the COR upon completion of a joint walk through by the contractor and the COR. No payment will be authorized while punch list items remain open.

3.3.3 A final walk through will be performed with the contractor and the COR and the CO to ensure all punch list items have been addressed to the satisfaction of the government.

4.0 Government Furnished Support

4.1 Base support includes Government-controlled working space and utilities.

5.0 Site Conditions

5.1 Standard site conditions shall be considered those that include:

5.1.1 Free and clear hard surface access to the receiving and installation location during regular working hours

5.1.2 Threat condition level of the base is Bravo. This requires company personnel to get base access in order to complete the product installation.

5.1.3 A staging area adequate to sort, stage and uncrate products along with a waste receptacle suitable for disposal of materials.

5.2 Contractor shall notify the CO of any deviations from the above standards, as well as any requests for equitable adjustment to the contract price based on a condition not available at site visit.

6.0 Voluntary Protection Program (VPP)/Safety

6.1 Voluntary Protection Program: The Air Force is part of the AOSHA VPP. All contractors are required to familiarize themselves with the requirements of the VPP. Information on VPP can be accessed at https://www.osha.gov/vpp

7.0 Base/Installation Specifics

7.1 All commercial trucks must enter through the Kuntz (Commercial) Gate on the

Hickam side, which is located at the end of Elliot Street off of Nimitz Hwy for inspection. In accordance with the Installation 647 SFS, base entry procedures must adhere to delivery vehicle process requirements mandated IAW JBPH-H INST 5530.2B. Once at Kuntz Gate, the driver must have a current DBIDS pass issued by JBPHH Pass & ID located at Bldg 3455, South Drive for entry through the Kuntz Gate. Approval for DBIDS will be completed through the 735 AMS with all workers have previously completed the SECNAV 5512-1 and the JB2 Form 0-180 for base access. Vehicles will be ready for inspection prior to entry and may be asked to provide proof of:

• A current Vehicle Registration

• A current Proof of Insurance

• A valid and current Driver's License for the driver https://www.osha.gov/vpp

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

• A valid and current Driver's License or other State Identification for any passenger(s) in the vehicle.

7.2 Gate Procedures:

• Once at Kuntz Gate, be prepared to exit the vehicle and allow for vehicle inspection. At this time you may ask for directions to your final destination.

• If the final destination requires the driver to leave the Kuntz Gate and re-enter the base through an alternate gate, the pass received will be sufficient documentation for entry into both gates, within a pre-established time directed by the Security Forces representative.

• Arrival at the appropriate gate after the designated allotted time will result in non-admittance to the installation.

• This procedure will occur each time a commercial truck requests access to the base.

7.3 Current Bill of Lading (BOL) to get delivery driver and the vehicle on base. BOL must include the AF installation name, date of anticipated delivery, and specific destination (including building number, street address, and point of contact information).

7.4 Personnel should the following items when entering an installation:

• Current Registration for all vehicles

• Current Proof of Insurance for all vehicles

• Valid driver’s license for each driver

• Valid driver’s license or other state identification for each passenger

• Depending on the current Force Protection Condition, a government representative may be required to sponsor those people in person at Pass & ID, Bldg 3455, South Drive.

• The sponsor must state the guest's purpose and destination. It is the responsibility of the contractor to validate this need with their government POC prior to their arrival so as to coordinate the arrival time accordingly.

Sponsors may request that a pass be applicable for multiple days if needed.

7.5 To sponsor 10 or more people, a typed list of those people must be submitted by the COR in Word or Excel format, stating LAST NAME then FIRST NAME of each person. The sponsor must submit that list to Pass & ID Bldg 3455, South Drive, no fewer than three days prior to the anticipated arrival. Names listed must be complete names, (no nicknames), and correspond to the names on the state ID for each person.

7.6 Mission Essential Services: Contractors are not considered mission essential.

7.7 Prohibitions: Firearms may not be brought on base under any circumstances.

Individuals with criminal records are not allowed on base. Contractor personnel are prohibited from sponsoring guests onto the installation.

8.0 Deliverables (CDRLs)

8.1 (CDRL A001) Removal

8.2 (CDRL A002) Installation

8.3 (CDRL A003) Electrician/Electrical Work (if required)

8.4 The Government has full ownership of all formal deliverables and required supporting documentation with regard to use, distribution and reproduction.

PWS HVAC VAV and Thermostat Replacement Contract No. xxxxxxxxxxxxx

9.0 Performance Objective Summary

Performance Objective PWS

Paragraph Performance Threshold

1) General –Oversight and accountability for all people and equipment used and product provided for a project

3.1 No more than 1 customer complaint per removal and

installation and resolution of all issues identified and validated by the COR within 24 hours.

2) Installation/Removal

– product was removed and installed per customer’s approved plan within the allotted time frame

3.5 No more than one customer complaint. Complaints

must be successfully resolved within 48 hours.

6) Acceptance – All punch list items have been remedied, and the fuel pit lid for 22B is in proper working condition.

3.6 Zero punch list items remain unresolved prior to

project completion.

1.0 Background
2.0 Scope
3.0 Description of Work
3.1 General Services
3.2 Assembly, Installation and Removal Work
3.3 Inspection/Acceptance Checklist
4.0 Government Furnished Support
5.0 Site Conditions
6.0 Voluntary Protection Program (VPP)/Safety
7.0 Base/Installation Specifics
8.0 Deliverables (CDRLs)
9.0 Performance Objective Summary

File details come from the government source that posted it. Updated .