RFI Log Zipline Demo.pdf

PDF 125 KB Posted

Attached to
Playground Zipline Demolition
Solicitation number
FA521526Q0023
Issued by

About this file

This is a Requests for Information (RFIs) document for a zipline demolition project at a federal facility. Sixteen RFIs were submitted between July 1 and July 10, 2026, with responses provided by July 13, 2026.

The project involves the complete demolition and removal of an existing zipline structure from a playground area, including removal of embedded concrete support post footings and repair of the artificial turf surface. Key requirements include: obtaining a base dig permit if concrete footings are completely removed; cutting support posts below the turf line and repairing the surface to a safe, even condition free of hazards; providing replacement surfacing material that matches existing color and texture where possible but must meet safety standards; maintaining access to the main playground during demolition; restricting staging and dumpsters to an adjacent parking lot; and limiting work to daytime and weekend hours only to avoid neighborhood disturbance. Contractor personnel must obtain government access passes, complete access request forms, provide Real ID copies, and pass background checks free of felonies. Subcontracting is permitted. The government will not provide replacement materials; this cost must be included in the contractor's proposal. Inspection criteria focus solely on achieving a smooth, safe surface free of hazards rather than matching original specifications.

View the file

Other files

File Type Posted
RFQ COMBO.pdf PDF
RFI Log Zipline Demo.pdf PDF
Zipline Images.pdf PDF
Zip Line image.png PNG image
RFQ COMBO.pdf PDF
Provisions and clauses.pdf PDF
Field of Dreams Zip Line Removal - SOW.pdf PDF
Capability Statement Zip Line Demolition.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI # Date Recv'd Date Sent to PM RFI Response

Date Answered

1 1-Jul-26 1-Jul-26 Do you have any pictures of the site? Photos Attached 3-Jul-26

2 1-Jul-26 1-Jul-26 Can you confirm that the zipline is on turf? If so is there a particular spec or type that you would want us to use?

Turf appears to be artificial grass over impact absorbing materials. Picture provided. Want a relatively smooth surface that children can run on and possibly fall without major injury.

3-Jul-26

3 1-Jul-26 1-Jul-26

What on post requirements are necessary prior to entering post?

Contractor access passes will be provided for the term of the contract. All personnel requiring access will need to complete access request forms, provide copies of Real IDs, and pass a basic background check free of felonies.

3-Jul-26

4 1-Jul-26 1-Jul-26 Are there any permitting requirements prior to beginning the demo?

If the proposal is to completely remove the concrete footings a base dig permit is required. If there is no digging into dirt, there should be no permit requirement.

3-Jul-26

5 1-Jul-26 1-Jul-26 Are there any equipment access or staging restrictions within the playground area that we should account for when preparing our quote?

We would like the main playgrounds to remain accessible during the demolition project. Staging should be within proximity to the zipline.

3-Jul-26

6 1-Jul-26 1-Jul-26 Is subcontracting allowed? Yes 3-Jul-26

7 1-Jul-26 1-Jul-26 Can you confirm whether the support posts are surface-mounted or embedded in concrete footings, and whether the intended removal method is to cut the posts above the footings or remove the anchor bolts?

Support posts are embedded in concrete footings. It is acceptable to cut them below the turf and repair the turf to a safe condition

3-Jul-26

8 1-Jul-26 1-Jul-26 Can you provide any available drawings, specifications, manufacturer information, or approximate dimensions of the zipline (overall length, pole height, and pole size)?

Photos Attached 3-Jul-26

9 10-Jul-26 10-Jul-26 What is the manufacturer of the existing turf and safety padding?

I don’t have any details on the existing turf and safety padding

13-Jul-26

10 10-Jul-26 10-Jul-26 Is matching the existing color and texture required?

Matching is preferred but an even surface that is safe is required.

13-Jul-26

11 10-Jul-26 10-Jul-26 Is there an acceptable patch size or repair specification?

No, as long as the patch provides an even surface free of safety hazards

13-Jul-26

12 10-Jul-26 10-Jul-26 Will the Government provide replacement surfacing material if matching material is unavailable?

No, this should be included in the contract.

13-Jul-26

13 10-Jul-26 10-Jul-26 What inspection criteria will be used to determine acceptable surfacing repairs?

Inspection criteria will be a smooth surface free of safety hazards. 13-Jul-26

14 10-Jul-26 10-Jul-26 Are weekend or after-hours work permitted?

Weekend hours can be coordinated, but not after-hours so as to limit disturbance to residents in the adjacent neighborhood

13-Jul-26

15 10-Jul-26 10-Jul-26 Will the playground remain open during construction?

The zipline portion of the playground can be closed. The playground within the fence should remain open.

13-Jul-26

16 10-Jul-26 10-Jul-26 Are there restrictions on dumpsters or equipment staging?

It is preferrable to have dumpsters and staging within the adjacent parking lot.

13-Jul-26

Requests For Information (RFIs) - Zipline Demolition

Sheet1