v1 Sept 25 QandA.docx

DOCX document 14 KB Posted

Attached to
374 CONS Sharepoint Application
Solicitation number
FA520920QNJ01
Issued by

View the file

Other files

File Type Posted
v2 Sept 25 QandA.docx DOCX document
STATEMENT OF WORK for SharePoint Application V1.docx DOCX document
Combined Synopsis Sharepoint Application V1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5209-20-Q-NJ01 374 CONTRACTING SQUADRON (374 CONS) SHAREPOINT APPLICATION

Questions and Answers – v1 09/25/2020 (Japan)

CS = Contract Specialist CO = Contract Officer V = Vendor

1. What type of contract/purchase are you anticipating awarding (Cost reimbursable, T&M, FFP)?

a. CS: FFP, Firm Fixed Price

2. Are you able to grant a one-day extension

a. CS: Are you asking for one business day extension or a calendar day extension.

b. V: 1 calendar day

c. CS: Yes, we will amend the announcement and extend the deadline to Sept 26, 1700 (Japan Time)

3. What is the level of effort to be performed at each location (Japan & Hawaii)

a. CS: The system is actually located here in Japan, our headquarters is in Hawaii. We cannot assess how much effort it takes one company to finish the changes to SharePoint as opposed to the next. Right now we use excel sheets and would like to have that data added to SharePoint with a top level dashboard or easy measures. This was not specifically stated because we mainly want to purchase a solution but do not want to dictate how we get there as long as it is in compliance. This is why one of the lines of effort is to establish a baseline of our existing data (several excel sheets). CONS will leverage the tedious parts such as data entry from existing technical team.