Attachment No.2 to Solicitation No. FA520919QA033
July 16
STAEMENT OF WORK
BALL TRANSFER UNITS
374 LRS COMBAT MOBILITY FLIGHT (LGRA)
1. GENRAL OVERVIEW – This Statement of Work provides the guidelines for the execution of installation of ball transfer units for 374th LRS Combat Mobility Flight (LGRA). It will highlight the responsibilities of the contractor(s), general repair requirements for each floors, and the conditions of acceptance of the finished products.
2. GOVERNMENT REPRESENTATIVE (GR): The authorized primary Government Representatives (GR) for this contract are Primary: tsGT Ryan Aubert, DSN: 225-4149, E-mail: ryan.aubert@us.af.mil, Alternate: TSgt Jason Golden, DSN: 225-4149, E-mail: jason.golden.2@us.af.mil. They will work as quality assurance inspectors as well as the point of contact for the Contractor.
3. CONTRACTOR RESPONSIBILITIES – This section will outline the responsibilities of the contractor(s) during the execution of this contract.
3.1. The materials and methods used in the execution of this contract will be of the commercially accepted types and applications used for work of this type.
3.2. The contractor(s) will be responsible for producing a finalized product that is acceptable to Combat Mobility Flight (CMF). The CMF will not be responsible for additional costs above and beyond the initial estimated cost that are incurred due to the re-accomplishment of any work that is not deemed acceptable during the acceptance inspection.
3.3. The contractor shall perform the service Monday through Friday and the building will be available 24 hours excluding U.S. and Japanese legal holidays.
Performance period is 60 calendar days.
3.4. The contractor(s) shall be held responsible for any damage that may occur to any government or private property that is damaged in the process of the contractor(s) work. All government owned or private property will be removed from the rooms prior to the contractor staring work.
3.5. The contractor(s) shall at no time leave materials or waste, which is required to be regulated by Japanese Laws and/or JEGS, unattended on Yokota Air Base.
4. REQUIREMENTS FOR BALL TRANSFER UNITS – This section will outline the types of repairs requested for the Ball Transfer Units designated in this contract. Unless specified otherwise, all provided software, drawings, manuals, instructions, reports, mailto:ryan.aubert@us.af.mil and other documents and code shall be provided in the English language. Dual-language with Japanese as the second language shall be acceptable provided everything defaults to English.
4.1. BALL TRANSFER UNITS
4.1.1. Remove existing roller system and frames from the eastern section on the flight line side of warehouse floor.
4.1.2. Install new ball transfer units on the east end of the current roller system.
The ball transfer units will be utilized to move airdrop platforms, 463L pallets and other cargo equipment between the two different roller systems currently installed
4.1.2.1. East end of current rollerized system must fit the dimensions of two sections measured at 9.8 ft/118 inches wide by 13 ft/151 inches long that will have the capability to move independently vertically with in-ground scales built-in underneath. Between both of these independent units will be a third unit inserted measured at 3.3 ft/40 inches wide by 13ft/151 inches long to allow the transfer of airdrop platforms, 463L pallets and other cargo between rollerized lanes and scales. Ball transfer units must be 4.25 inches off the ground to meet the height of the current rollerized system installed.
4.1.2.2. Each unit will have forklift tine troughs built into the units to support military 10K Standard and 10K All-Terrain forklift tine measurements.
4.1.2.3. Each ball transfer unit shall have a removable bottom for cleaning of the small ball bearings by maintenance personnel. The removable bottom shall be securely retained in place but shall be removable. Each type of ball transfer unit used shall be approved by the GR prior to ordering. The ball transfer unit manufacturer shall have been manufacturing ball transfer units for a minimum of 5 continuous years.
4.1.2.4. Each ball transfer unit shall have a minimum load capacity of 500 pounds.
4.1.2.5. Ball transfer units shall consist of a machined metal housing containing a minimum 30-millimeter diameter main load ball with a stainless steel Grade 200 or better. The main ball and all smaller balls shall be manufactured of the same material and shall have the same hardness. Components of the ball transfer units shall not corrode, rust, or deteriorate due to condensation.
4.1.2.6. Each ball transfer unit shall have debris holes on the bottom with a minimum area of 15 square millimeters.
4.1.2.7. Each ball transfer unit shall be marked with the manufacturer’s name and model number in a location that is visible from above when installed in the ball transfer tread plate.
4.1.2.8. Ball transfer units shall be installed on maximum 6-inch centers. Ball transfers and the spacing used shall not damage airdrop platforms, 463L pallets, or other cargo stored or transferred on the surface. Ball transfer unit surface shall be level with the currently installed rollerized system for ease of transfer of items between the two systems.
4.1.2.9. The Contractor shall certify the load capacity of the ball transfer units, that the housing is machined, and the material and hardness of the mail ball and smaller balls.
4.1.2.10. The ball transfer frame shall be constructed of structural steel and shall support all loads without permanent deformation. The frame may be combined with the tread plate the tread plate into a single unit if the design is approved by the GR prior to manufacturing. A metal tread plate shall be provided around all ball transfers. All tread plates shall for a single, integral walking area that provides a safe walking surface for personnel who manually transfer platforms, pallets and cargo. Tread plates shall be a minimum of 0.12-inch thick steel. Tread plates shall provide a non-slick surface with high traction even when wet. Holes for the ball transfers shall not create a gap larger than 0.03 inch between the ball transfer and the tread plate. Tread plates shall be designed, installed, and seized to be easily removable by one person. Tread plates shall not be welded in place. If separate from the frame, tread plates shall be fastened in place with recessed-head bolts that are not a tripping or snagging hazard. Tread plates may be retained in place without fasteners if the design is approved by the GR. Platforms and pallets being transferred on the ball transfer unit shall not make any contact with the tread plates.
4.1.2.11. A steel skirt shall extend from the tread plate surface to within 0.25 inch of the floor on all exposed sides of the ball transfer unit. The ball transfer frame may also serve as the frame skirt.
4.1.3. Removable pallet stops shall be configured to fit plates that measure 0.5 inches thick by 9.5 inches wide.
4.1.4. Ball transfer guide rails shall be installed in conjunction with the current rollerized guide rails and shall function as a continuous fixed stop. They shall span the entire length of the roller ball sections and meet performance requirements for pallet stops.
4.1.5. Forklift tine deflectors shall be installed at each outer most end of the roller ball units to deflect tines from an approaching forklift upwards so the impact is not felt by or transferred to the frame. The deflector and the surface it is mounted to shall not exhibit damage, deformation, or decreased performance from forklift tine impacts. The forklift tine deflector shall be a minimum of 0.37-inch thick steel installed at an angle to deflect approaching tines upwards.
The forklift tine deflectors shall be installed within the forklift tine troughs built into the frame of the ball transfer unit.
4.1.6. All ball transfer units shall be designed to withstand, operate, and be safe to use in rain, heat, direct sunlight, wind, moisture, fog, humidity, snow, sleet, ice, and all other environmental conditions at Yokota AB.
4.1.7. The system shall be designed, fabricated, and installed to facilitate maintainability and ensure a minimum service life of 10 years. The design shall provide for modular assembly of components and subassemblies where feasible to permit repair or replacement of parts in a minimum of time.
4.1.8. Standard, commercial components which have been for sale and available for purchase to the general public or government agencies for at least one year shall be used to the maximum extent possible. If requested by the GR, the Contractor shall furnish evidence that equipment of approximately the same design as the proposed to be installed has been tested and successfully operated. Where two or more units of the same type of equipment are required, these units shall be products of the same manufacturer.
4.1.9. Use of special tools shall be minimized and, where required for operational adjustments, shall be securely mounted within the equipment in a readily accessible location. Standard tools, fittings, lubricants and fluids shall be used the maximum practicable extent.
4.1.10. All metal system component surfaces with exception to the tread plates shall be protected from corrosion by painting, plating, or a galvanized protective coating. Surface preparation and color shall be as specified prior to approval.
3. ACCEPTANCE CONDITIONS – This section will outline the method of inspection for acceptance of the finalized product and some of the main points that will be checked during the acceptance inspections. This list is not, however, all-inclusive.
3.3. The acceptance inspections will be conducted at Building 202, Combat Mobility Flight Warehouse.
3.4. Types of occurrences that will not be accepted on the final product:
3.4.1. Inoperable ball transfer units.
3.4.2. Inability to transfer airdrop platforms, pallets or cargo from ball transfer units to currently installed rollerized rail system.
3.4.3. Any other mistakes or aesthetic inconsistencies the take away or otherwise reduce the overall appearance of the floors and walls.