DEPARTMENT OF THE AIR FORCE
PACIFIC AIR FORCES
14 Jun 16
MEMORANDUM FOR PROSPECTIVE PROPOSER
FROM: 374 CONS/LGCZ
Unit 5228, Yokota AB Fussa-shi, Tokyo, 197-0001 Japan
SUBJECT: RFQ FA5209-16-T-0073, Questions and Answers (#4, Last)
We have received the last question regarding subject RFQ from a prospective vendor by the question submission due/time specified in the subject RFQ, and the following is our answer.
Q29: If a contractor needs to make a hole on concrete wall for re-wiring cable, should a contractor provide the construction work?
A29: Yes, a contractor needs to make a hole on concrete wall.
For any questions, please contact POCs: Kaori Kanematsu, Contract Specialist, Commercial Phone No. +81-(0)42- 553-8549, DSN 225-2634, Email: kaori.kanematsu.jp@us.af.mil, and the undersigned at Commercial Phone No.
+81-(0)42-553-8549, DSN 225-7628, Email: izumi.sugimoto.jp@us.af.mil.
IZUMI SUGIMOTO
Contracting Officer
CC: 374CS and DoDEA, Yokota AB