6. iFortress Construction Prelimanry Schedule.pdf
PDF 187 KB Posted
- Attached to
- Misawa Construction Surveillance Technician (CST) Service Federal contract opportunity
- Solicitation number
- FA520525Q0010
About this file
This is a project timeline Gantt chart for an iFortress project at Misawa, spanning 172 days from September 3, 2025, to April 30, 2026. The project involves multiple construction and installation phases, including long lead item procurement for HVAC, electrical systems, and doors, followed by systematic assembly and installation processes. Key project stages include team mobilization, iFortress structure assembly (with 8-10 workers), MEPS (Mechanical, Electrical, Plumbing, and Structural) installations, and various technical infrastructure work such as OSP fiber pulling and passive IT implementation. The timeline is carefully sequenced, with specific durations for each task, including 10 weeks for HVAC installation, 11 weeks for electrical installation, and concluding with RF testing, owner manual handover, and project completion milestones.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA520525Q00100002 SF 30.pdf | ||
| 1. Misawa Construction Surveillance Technician PWS-Aug 2025_Updated 28 Aug.pdf | ||
| Misawa CST Services - RFQ FA520525Q0010_Questions _ Answers.xlsx | XLSX spreadsheet | |
| Solicitation Amendment FA520525Q00100001 SF 30.pdf | ||
| 5. Pricing Sheet.xlsx | XLSX spreadsheet | |
| 2. DD 254 Contract Security Classification Specification_Misawa CST.pdf | ||
| 3. DD 254 Instructions.pdf | ||
| 4. DCSA_Field_Office_Locations.pdf | ||
| Solicitation - FA520525Q0010.pdf | ||
| 1. Misawa Construction Surveillance Technician PWS-Aug 2025.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 Misawa 172 days Wed 9/3/25 Thu 4/30/26
2 PO RECEIVED 0 days Wed 9/3/25 Wed 9/3/25
3 LONG LEAD ITEMS 105 days Wed 9/3/25 Tue 1/27/26 2
4 HVAC LONG LEAD ITEMS 65 days Wed 9/3/25 Tue 12/2/25
5 PROCUREMENT OF ITEMS 8 wks Wed 9/3/25 Tue 10/28/25
6 HVAC LONG LEAD SHIPPING 5 wks Wed 10/29/25 Tue 12/2/25 5
7 ELECTRICAL LONG LEAD ITEMS 105 days Wed 9/3/25 Tue 1/27/26
8 PROCUREMENT OF ITEMS 16 wks Wed 9/3/25 Tue 12/23/25
9 ELECTRICAL LONG LEAD SHIPPING 5 wks Wed 12/24/25 Tue 1/27/26 8
10 DOOR LONG LEAD ITEMS 50 days Wed 9/3/25 Tue 11/11/25
11 STC 50 DOORS 10 wks Wed 9/3/25 Tue 11/11/25
12 HOLLOW MEDAL DOORS 8 wks Wed 9/3/25 Tue 10/28/25
13 MCF iMove Series iFortress Shipping 25 days Mon 9/15/25 Fri 10/17/25 2
14 MCF iMove iFortress Shipping From Inventory 5 wks Mon 9/15/25 Fri 10/17/25
15 iFortress Assembly (Structure) (8-10 workers) 49 days Thu 10/16/25 Tue 12/23/25
16 TEAM MOBILIZATION 1 day Thu 10/16/25 Thu 10/16/25 14FS-2 days
17 RECEIVE DELIVERY 1 day Fri 10/17/25 Fri 10/17/25 14FS-1 day
18 ASSEMBLY (STRUCTURE) 6 wks Mon 10/20/25 Fri 11/28/25 17
19 ASSEMBLY (ROOF) (Starts @ wk 5 of structure) 2 wks Mon 11/24/25 Fri 12/5/25 18SS+5 wks
20 FLOORING INSTALL 5 days Mon 12/1/25 Fri 12/5/25 18
21 INSTALL FLOORING 1 wk Mon 12/1/25 Fri 12/5/25
22 Door Installation 30 days Wed 11/12/25 Tue 12/23/25 10
23 Ship Doors 5 wks Wed 11/12/25 Tue 12/16/25 10
24 Install Doors 1 wk Wed 12/17/25 Tue 12/23/25 23
25 For lines 13-22, there will be approx. 8-10 workers on site.
26 iFortress MEPS 96 days Tue 12/2/25 Tue 4/14/26
27 HVAC (6-8 workers) 51 days Tue 12/2/25 Tue 2/10/26
28 RECEIVE DELIVERY 1 day Tue 12/2/25 Tue 12/2/25 6FS-1 day
29 HVAC INSTALLATION 10 wks Wed 12/3/25 Tue 2/10/26 28
30 ELECTRICAL (6-8 workers) 56 days Tue 1/27/26 Tue 4/14/26
31 RECEIVE DELIVERY 1 day Tue 1/27/26 Tue 1/27/26 9FS-1 day
32 ELECTRICAL INSTALLATION 11 wks Wed 1/28/26 Tue 4/14/26 31
33 FIRE SUPPRESSION (2-4 workers) 20 days Wed 1/28/26 Tue 2/24/26 32SS
34 FS INSTALLATION 4 wks Wed 1/28/26 Tue 2/24/26
35 Starting Passive IT and OSP fiber pull (2-3 workers) 32 days Wed 12/17/25 Fri 1/30/26
36 OSP fiber pull into comms room, termination, and testing2 days Mon 1/12/26 Wed 1/14/26
37 Passive IT and all associated work 30 days Wed 12/17/25 Wed 1/28/26
38 Final walkthrough and signoff 1 day Thu 1/29/26 Fri 1/30/26
9/3
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026
ID Task
Mode
Task Name Duration Start Finish Predecessors
39 ASSEMBLY COMPLETE 1 day Wed 4/15/26 Wed 4/15/26 26
40 RF TESTING 1 day Thu 4/16/26 Thu 4/16/26 39
41 OWNER MANUAL HAND OVER 2 wks Fri 4/17/26 Thu 4/30/26 40
42 Misawa COMPLETE 0 days Thu 4/30/26 Thu 4/30/26 41 4/30
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026