Attachment 3d AF 66 Seed Project 20201208.pdf
PDF 628 KB Posted
- Attached to
- JBER Mini-MACC Federal contract opportunity
- Solicitation number
- FA500021R0001
About this file
This document contains a schedule of material submittals for the Mini-MACC contract FA500021R0001 to repair exterior facilities at Joint Base Elmendorf-Richardson in Alaska. The schedule requires the contractor to submit items such as construction schedules, health and safety plans, lead paint abatement plans, 65% and 95% design drawings, shop drawings, demolition plans, specifications for metal siding, doors, windows, roofing, lighting and other architectural and mechanical elements. Submittals are due at various dates after notice to proceed with 100% design drawings due 90 days after NTP. The schedule also includes requirements for closeout documents such as operations and maintenance manuals, as-built drawings and warranty information.
The related federal contract opportunity notice provides additional context, describing the Mini-MACC as complementing the larger MACC design-build contract for JBER. The Mini-MACC is for smaller general construction projects requiring some but not all design services. It aims to maintain a pool of contractors for continued small project work. The Department of the Air Force Pacific Air Forces is the contracting agency.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF FORM 66, OCT 99 Previous Edition Will Be Used
LI
N
E N
U M
B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.
C
ER
TI
F.
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
TU
R
U R
'S R
EC
O
M M
EN
D
AT
IO
C
AT
AL
O
G D
AT
A
O &M
R
EC
O M
M
EN
D
AT
IO
N
S
C
AL
C U
LA
TI
O N
S
W
AR
R
AN
TY
D R
AW
IN
G S
R
EP
O R
T
SA
FE
TY
D
AT
A
SH
EE
TS
O
TH
ER
TE
ST
R
ES
U
LT
S
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E
TO
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
AP
PR
O
VE
D
D
IS
AP
PR
O
VE
D
C O
N
TR
AC
TO
R S
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
NOTES
GENERAL
1 Project Specific Form 66 X NTP + 15 2 Construction Schedule X NTP + 15 3 Contractor's Health, Safety, and Environment Plan X NTP + 15 4 Contractor's QA/QC Plan X NTP + 15 5 Material Safety Data Sheet (MSDS) X NTP + 15
6 Lead Based Paint Abatement Plan X See Notes LBP Abatement Plan must be submitted and approved by Government prior to start of abatement.
DESIGN
All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) and 100% Design Drawings to include:
X NTP + 90
(100%) All required disciplines
8 Plans, Elevations, Sections, Schedules, and Details -- 65% Design X NTP + 45 All required disciplines
9 Plans, Elevations, Sections, Schedules, and Details -- 95% Design X NTP + 75 All required disciplines
10 Plans, Elevations, Sections, Schedules, and Details -- 100% Design X NTP + 90 All required disciplines
11 Plans, Elevations, Sections, Details -- Shop Drawings X NTP + 120
DEMOLITION
12 Demolition Plan X X X NTP + 45
ARCHITECTURAL
13 Metal Panel Siding - Ribbed & Smooth X X X X X X NTP + 120 14 Doors and Frames X X X X X NTP + 120 15 Door Hardware X NTP + 120 16 Windows (Glazing, Frames, & Mullions) X X X X X NTP + 120 17 Blast Resistant Materials X X X X NTP + 120 18 Exterior Wall Insulation X NTP + 120 19 Canopies (Roofing, Structural Steel) X X NTP + 120
ELECTRICAL
20 Receptacles X NTP + 120 21 Cables (Electrical) X NTP + 120 22 Conduits (Electrical) X NTP + 120 23 LED Light Fixtures X NTP + 120
SOLICITATION /CONTRACT NUMBERPROJECT NAME
REPAIR B5327 EXTERIOR SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
PROJECT NUMBER
FXSB 17-1110
FA500021R0001
Mini-MACC
AF FORM 66, OCT 99 Previous Edition Will Be Used
LI
N
E N
U M
B ER Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.
C
ER
TI
F.
O F
C O
M
PL
IA
N
C E
SH
O
P D
R
AW
IN
G
S
C O
LO
R
S
EL
EC
TI
O N
M
AN
U
FA
TU
R
U R
'S R
EC
O
M M
EN
D
AT
IO
C
AT
AL
O
G D
AT
A
O &M
R
EC
O M
M
EN
D
AT
IO
N
S
C
AL
C U
LA
TI
O N
S
W
AR
R
AN
TY
D R
AW
IN
G S
R
EP
O R
T
SA
FE
TY
D
AT
A
SH
EE
TS
O
TH
ER
TE
ST
R
ES
U
LT
S
R
EQ
U
IR
ED
S
U
BM
IS
SI
O N
D
AT
E
D
AT
E
TO
C O
N
TR
AC
TI
N G
D
AT
E
TO
C
IV
IL
E
N G
IN
EE
R
IN
G
R
ET
U R
N S
U
SP
EN
SE
D
AT
E
SU
BM
IT
TA
L N
U M
BE
R
S
AP
PR
O
VE
D
D
IS
AP
PR
O
VE
D
C O
N
TR
AC
TO
R S
U
BM
IT
TA
L
FI
N
AL
A
PP
R
O
VA
L
NOTES
SOLICITATION /CONTRACT NUMBERPROJECT NAME
REPAIR B5327 EXTERIOR SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
PROJECT NUMBER
FXSB 17-1110
MECHANICAL
24 Exhaust Fan X
HAZMAT
25 JBER HAZMAT Usage Tracking Form X See Notes NLT 10 working days prior to material being brought onto installation
26 JBER HAZMAT Usage Tracking Form X See Notes NLT 7 working days after final acceptance
CLOSEOUT
27 O&M maintenance data and maintenance manuals & Manufacturer's Warranty for All Equipment Installed X X X Install + 5
28 Completion of DD 1354 X Final + 7
29 As Builts (electronic in AutoCAD and hard copies on Mylar) X Final + 7