Attachment 3a SOW Seed Project 20201208.pdf

PDF 693 KB Posted

Attached to
JBER Mini-MACC Federal contract opportunity
Solicitation number
FA500021R0001
Issued by
Department of the Air Force Pacific Air Forces

About this file

This statement of work and related federal contract opportunity outline requirements for repair and renovation work on Building 5327 at Joint Base Elmendorf-Richardson in Alaska. The statement of work provides detailed specifications for repairs and replacement of exterior siding, doors, windows, and associated systems. Work includes removal and disposal of hazardous materials, installation of new metal siding and trim, replacement of doors and windows, and electrical and HVAC upgrades. The related solicitation is for the Mini-MACC contract to provide multiple general construction disciplines for on-base facilities at JBER. The contract will supplement a larger MACC design-build contract and include projects requiring minimal design from 35-95% completion. The Department of the Air Force Pacific Air Forces is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to JBER Mini-MACC, newest first.
File Type Posted
Attachment 1a Mini-MACC SOW - JBER Richardson IFS_20201208.pdf PDF
Attachment 1f Mini-MACC SOW - Contractors Fire Safety Guide 20201208.pdf PDF
Attachment 1g1 Mini-MACC SOW - Dig Permit Custom Map Elmo 20201208.pdf PDF
Attachment 3c Drawings Seed project 20201208.pdf PDF
Attachment 1c Mini-MACC SOW - JBER Hazardous Waste Management Plan - 20201208.pdf PDF
Attachment 1g Mini-MACC SOW - 673ABW Form 3 Dig Permit (20 Version) 20201208.pdf PDF
Attachment 3 FOPR-Seed Project 20210430.pdf PDF
Attachment 3b SPECs Seed project 20201208.pdf PDF
Solicitation - FA500021R0001 20210430.pdf PDF
Attachment 1 Mini-MACC SOW 17 July 2020201221.pdf PDF
Attachment 1h Mini-MACC SOW - DD1354 _ FILLABLE Template _ AUG2013 20201208.pdf PDF
Attachment 3e DD1354-fillable seed project 20201208.pdf PDF
Attachment 3f DBA WD AK20210409.pdf PDF
Attachment 5 Financial Data Form 20201208.pdf PDF
Attachment 1b Mini-MACC SOW - JBER_Elmendorf_IFS_20201208.pdf PDF
Attachment 1d Mini-MACC SOW - ENV_PRECON Checklist 20201208.pdf PDF
Attachment 1e Mini-MACC SOW - CAD GIS RECORD DRAWING DESIGN AND AS BUILT STANDARD 20201208.pdf PDF
Attachment 1g2 Mini-MACC SOW - Dig Permit Custom Map Rich 20201208.pdf PDF
Attachment 1i TIA-568 Telecomm Cabling Standard.pdf PDF
Attachment 2 NAFI General Provisions-Clauses 20210322.pdf PDF
Attachment 3d AF 66 Seed Project 20201208.pdf PDF
Attachment 4 Price Schedule 20210204.pdf PDF
Attachment 6 PPCL 20210430.pdf PDF
Attachment 7 PPQ 20210419.pdf PDF
Attachment 8 Past Performance Supplement Worksheet 20210416.xlsx XLSX spreadsheet
Attachment 9 Teaming consent 20201208.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

673d Civil Engineer Squadron Joint Base Elmendorf-Richardson, AK

FXSB 17-1110 – Repair Bldg. 5327 Exterior Page 1 of 6

03 JUN 2020

STATEMENT OF WORK

REPAIR BLDG. 5327 EXTERIOR

FXSB 17-1110

SECTION 1: PROJECT INFORMATION

1.1 PROJECT LOCATION: MINI-MACC project FXSB 17-1110 shall be completed as a routine requirement at or near building 5327 Kenney Ave., on Joint Base Elmendorf-Richardson, AK.

Project hours are standard work hours.

1.2 UNIQUE REQUIREMENTS: Building shall be occupied during construction, Contractor shall coordinate and schedule work with 673 CES/CEN, 673 CONS, and End Users prior to starting any operation.

1.3 PROJECT DESCRIPTION: This is a 35% conceptual design-build project to include replacement of portions of sill plate/stud framing, all man doors, all overhead sectional doors, and most windows along with installation of a vapor barrier, rigid insulation board, furring strips, and ribbed steel siding to include associated flashings and trim. Lead Based Paint (LBP) is present on the existing wood siding and trim, therefore precautions and treatment of hazardous materials during cutting and drilling operations shall be followed. Asbestos Contained Material (ACM) exists in the drywall mud and drywall surrounding most windows and doors. Required precautions and removal techniques for ACM shall be followed. Where conflict exists between this document and the contract drawings the requirements in this document shall govern.

SECTION 2: GENERAL REQUIREMENTS

2.1 WORKMANSHIP: All work shall be accomplished in accordance with all applicable building and fire codes. Contractor shall field verify all measurements, quantities, or values stated by the Government. Liquidated damages shall be assessed for work that is not finished within the scheduled performance period.

2.2 WORKSITE: The contractor shall limit the work to the areas indicated by the government. The contractor shall make every effort not to disturb or obstruct portions of the facilities still occupied by the government. The contractor shall coordinate and schedule work with the 673 CES/CEN office prior to the start of any operation. The contractor shall dispose of all construction debris off base at an approved disposal facility.

2.3 SITE SECURITY AND PROTECTION: The contractor shall make every effort to secure the work site, allowing only authorized personnel to enter the work site. The contractor shall protect the site from damage from weather, vandalism, and/or theft.

2.4 DAMAGE TO EXISTING SITE CONDITIONS: The contractor shall be responsible for repairing all damage incurred to existing Real Property/Grounds due to poor workmanship at no cost to the government. Contractor shall not park or drive on sidewalk or grassy/snowy areas. Damage incurred shall be repaired at no cost to the government.

FA500021R0001

Mini_MACC

FXSB 17-1110 – Repair Bldg. 5327 Exterior Page 2 of 6

2.5 HEALTH/SAFETY: The contractor shall be responsible for compliance with OSHA and Alaska Department of Labor (AKOSH) standards. The contractor shall maintain a clean and debris free site at all times. The contractor shall keep driveways and entrances into and around the work site clear at all times. The contractor shall not use driveways or entrances as employee parking or storage of materials unless otherwise stated.

2.6 GREEN PROCUREMENT: Contractor must incorporate “green procurement” principles into the design of their projects. Specifically, consult the EPA’s web site at www.epa.gov/greenerproducts for a listing of the products that have been mandated as green procurement requirements for purchases.

SECTION 3: DESCRIPTION OF WORK AND SPECIAL INSTRUCTIONS

3.1 General Requirements (Div 1)

3.1.1. Provide complete design and construction services and drawings as noted in this document and on the Schedule of Material Submittals. Drawings shall be provided in AutoCAD and Adobe (pdf) format and shall include the color table file, font files, and any other supporting files required to print the drawings correctly. Record As-Built drawings shall comply with the attached REVISED JBER CAD RECORD DRAWING DESIGN AND AS- BUILT STANDARD Dec 2019.

3.1.2. Provide project management and quality control in accordance with base contract requirements.

3.1.3. Provide on-site portable toilet facilities for the duration of the project.

3.2 Existing Conditions (Div 2)

3.2.1. Pressure wash exterior of building to aid in removal of loose and peeling paint, taking all required steps to collect the fallen loose/peeling paint as LBP hazardous waste.

3.2.2. When cutting and/or drilling the siding and trim, all required precautions, and approved methods when LBP is present shall be followed.

3.2.3. During the process of removing doors/door frames and windows, all requirements of removing ACM drywall and drywall mud shall be followed.

3.2.4. Remove all man doors and frames with associated hardware.

3.2.5. Remove all overhead sectional doors with associated hardware.

3.2.6. Remove all windows and associated hardware.

3.2.7. Remove sections of deteriorated siding, sill plate, and lower portions of stud framing as required leaving solid material onto which can be spliced new sill plate and lower stud portions.

3.2.8. Remove wooden canopies at doors #01, #02, #03, #04, #18, and #19. Reference contract drawings for locations.

3.2.9. Remove wooden canopy and walls from door #17. Reference contract drawings for location.

FA500021R0001

http://www.epa.gov/greenerproducts

FXSB 17-1110 – Repair Bldg. 5327 Exterior Page 3 of 6

3.2.10. Remove existing shelter for flammable cabinets south of door #17. Reference contract drawings for location.

3.2.11. Remove existing exhaust fan south of door #17, to be replaced with new of similar style/type. Reference contract drawings for location.

3.2.12. Remove wood framed in-fill at overhead door #4, right side as viewed from outside.

Reference contract drawings for location.

3.2.13. Remove and reinstall steel framed canopies at doors #09 and #10. Reference contract drawings for locations.

3.2.14. Remove all existing wall mounted light fixtures, to be replaced with new LED fixtures of similar style/type. Reference contract drawings for locations.

3.2.15. Remove existing light fixture over door #14, to be replace with new LED fixture of similar style/type. Reference contract drawings for location.

3.2.16. Remove existing conduits, wiring, junction boxes, and receptacles, all to be replaced with new and wired to same circuits as they are currently on. New conduits, wiring, junction boxes, and receptacles shall be mounted on the surface of the new siding.

3.2.17. Remove gable vents from west side, to be replaced with new metal vents and associated trim. Reference contract drawings for locations.

3.2.18. Remove existing sliding door track and associated hardware and reinstall once new siding has been installed. Reference contract drawings for locations.

3.2.19. Remove and reinstall exhaust fan cover west of door #19. Reference contract drawings for location.

3.2.20. Remove exhaust fan louver within window frame east of door #18, to be replaced with new of similar style/type. Reference contract drawings for location.

3.2.21. Remove all smaller vents and vent hoods as required and reinstall once new siding has been installed.

3.2.22. Remove all loudspeakers and reinstall once new siding has been installed.

3.2.23. Remove and re-install all antennas.

3.3 Metals (Div 5)

3.3.1. Provide and install new steel framed gable style canopies for doors #01, #02, #03, #04, #05, #06, #07, #08, #11, #17, #18 and #19. Shop drawings shall be submitted for Government approval prior to fabrication and installation. Reference contract drawings for locations.

3.3.2. Remove and reinstall steel framed canopies at doors #09 and #10. Reference contract drawings for locations.

3.4 Wood, Plastics, and Composites (Div 6)

3.4.1. Provide and install new pressure treated dimensional lumber sill plate splices/replacements where required.

FXSB 17-1110 – Repair Bldg. 5327 Exterior Page 4 of 6

3.4.2. Provide and install new pressure treated dimensional lumber and plywood as sheathing where sill plate and stud framing repairs are done.

3.4.3. Provide and install new dimensional lumber framing to in-fill where replacement windows are downsized from existing windows. Reference contract drawings for locations.

3.4.4. Provide and install new pressure treated dimensional lumber and plywood sheathing, on the exterior side, where in-fill framing for new windows has been installed.

3.4.5. Provide and install new 2” thick furring strips, 24” O.C., over existing wood siding.

3.4.6. Provide and install new flammables shelter/shed south of door #17. Reference contract drawings for location.

3.5 Thermal & Moisture Protection (Div 7)

3.5.1. Provide and install new 6” thick batt insulation where in-fill framing is installed for new replacement windows. Reference contract drawings for location.

3.5.2. Provide and install new Gypsum Wall Board (GWB), on the interior side, where in-fill framing has been installed. Reference contract drawings for location.

3.5.3. Provide and install new vapor barrier over the existing wood siding.

3.5.4. Provide and install new rigid insulation (EPS), 2” thickness, in between new furring strips.

3.5.5. Provide and install new 24 gauge ribbed and smooth steel siding along with all associated trim, flashings, and sealants per siding manufacturer’s recommendation, providing a weather tight exterior cladding system. Style/pattern of ribbed siding TBD. Color of steel siding TBD based upon siding manufacturer’s color options.

3.5.6. Provide and install new eave and rake trim. Color to match roofing.

3.6 Openings (Div 8)

3.6.1. Provide and install new thermally broken hollow metal door frames. Reference contract drawings for locations and further details.

3.6.2. Provide and install new insulated hollow metal doors. Reference contract drawings for locations and further details.

3.6.3. Provide and install new insulated blast resistant glazing for select doors. Reference contract drawings for further details.

3.6.4. Provide and install new door hardware. Reference contract drawings for further details.

3.6.5. Provide and install new insulated overhead sectional doors and associated hardware.

Reference contract drawings for locations and further details.

3.6.6. Provide and install new insulated blast resistant glazing, thermally broken aluminum framed windows. Reference contract drawings for locations and further details.

3.7 Finishes (Div 9)

3.7.1. Provide and install new one (1) coat primer on wall in-fill at newly installed window locations.

FXSB 17-1110 – Repair Bldg. 5327 Exterior Page 5 of 6

3.7.2. Provide and install new two (2) coats finish color on wall in-fill at newly installed window locations. Match existing color a close as possible.

3.7.3. Clean and repaint exhaust fan cover west of door #19. Reference contract drawings for location.

3.8 Heating Ventilation Air Conditioning (HVAC) (Div 23)

3.8.1. Provide and install new exhaust fan louver east of door #18. Reference contract drawings for location.

3.8.2. Provide and install new exhaust fan south of door #17. Reference contract drawings for location.

3.8.3. Provide and install new metal louver vents on western gable ends. Reference contract drawings for locations.

3.8.4. Remove and re-install exhaust fan cover west of door #19. Reference contract drawings for location.

3.8.5. Remove and re-install all smaller vents and vent hoods, as required, once new siding has been installed. Locations vary.

3.9 Electrical (Div 26)

3.9.1. Provide and install new conduit, wiring, junction boxes, and GFCI duplex receptacles in same locations as existing, to be installed on the surface of the new siding.

3.9.2. Provide and install new LED light fixtures similar to existing, same locations as existing unless otherwise specified. Reference contract drawings for locations.

SECTION 4: ATTACHMENTS & REFERENCES

4.1 REFERENCES

4.1.1. Refer to Specifications METAL WALL PANELS attached, SECTION 07 42 13.

4.1.2. Refer to Specifications STEEL DOORS AND FRAMES attached, SECTION 08 11 13.

4.1.3. Refer to Specifications SECTIONAL OVERHEAD DOORS attached, SECTION 08 36 13.

4.1.4. Refer to Specifications ALUMINUM WINDOWS attached, SECTION 08 51 13.

4.1.5. Refer to Specifications BLAST RESISTANT TEMPERED GLASS WINDOWS attached, SECTION

08 56 53.

4.1.6. Refer to Specifications DOOR HARDWARE attached, SECTION 08 71 00.

4.1.7. Refer to Specifications JBER ENVIRONMENTAL HAZARD_v4 APR 2019 attached, 01120.

4.1.8. Refer to Specifications JBER DISP. OF HAZ WASTE_v2 JAN 2019 attached, 01121.

4.1.9. Refer to UFC 3-530-01 INTERIOR AND EXTERIOR LIGHTING SYSTEMS AND CONTROLS C4:

not attached.

4.1.10. Contractor to provide record drawings as required including all information shown in the contract drawings and all deviations, modifications, or changes on the contract drawings which were incorporated in the work.

FXSB 17-1110 – Repair Bldg. 5327 Exterior Page 6 of 6

4.1.11. Refer to Ability One PL Notice of Addition Ltr 20160209.

4.1.12. Reference attached drawings.

SECTION 5: PROJECT MANAGER - INSPECTOR

5.1 Geoffrey Farley, Arch-PM

geoffrey.farley.1@us.af.mil Phone: 384-1914

5.2 Robert McElroy, Inspector

robert.mcelroy@us.af.mil Phone: 384-3081

FA500021R0001