Attachment 7 SMP Form.docx

DOCX document 14 KB Posted

Attached to
Oil Water Separator Maintenance Federal contract opportunity
Solicitation number
FA5000-12-R-0002OWS_JBER
Issued by
Department of the Air Force Pacific Air Forces

About this file

Special Maintenance Project Form Attachment 7

View the file

Other files for this federal contract opportunity

Other files attached to Oil Water Separator Maintenance, newest first.
File Type Posted
FA5000-12-R-0002-0003.pdf PDF
FA5000-12-R-0002 Amendment 0002.pdf PDF
FA5000-12-R-0002 Amendment 0001.pdf PDF
FY12 OWS Inventory 10-25-11.xlsx XLSX spreadsheet
FY12 PWS dated 25 Oct 11.docx DOCX document
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE FINAL.doc DOC document
FA5000-12-R-0002.pdf PDF
WD 05-2017 REV 15 06-13-11.pdf PDF
25-JULY-2011-FINAL-SIGNED-sans-copyrighted-charts.pdf PDF
PP Information FINAL.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5000-12-R-002

Attachment 7, SMP Form Request/Authorization for NTE CLIN Special Maintenance Project

SECTION A.

773d CES/CEOSS

JBER, AK

Contract Number:

Project POC:

Phone:

Project Address:

Date Work Site Available

Required Completion Date

Project Control Number:

Contract CLIN:

Minor Alterations: ___YES __ NO

Project Description:

SECTION B. (To be completed by 673 CONS/LGCB)

This proposal is within the scope of the contract. Request you prepare a proposal and submit it to this Office by __________

Contracting Officer Date

SECTION C. (To be completed by Contractor)

Point of contact:

Phone:

Contractor’s Fully Burdened Bid:

REMARKS:

Signature of Project Manager/ DATE

SECTION D. Project Approval

Projects less than $3,000 are approved by Functional Director. / COR.

Projects over $3,000 require the signature of the Functional Director/COR and Contracting Officer.

Approved/Disapproved

Chief, CEOSS/ COR. Date Approved/Disapproved

Contracting Officer Date

SECTION E. Notification of completion by Contractor

PROJECT IS COMPLETE: DATE: SIGNATURE:

SECTION F. Project Accepted by COR

PROJECT ACCEPTED: YES NO DATE: SIGNATURE: