This document is a Questions and Answers file for a WiFi and Internet Services solicitation (FA489725QC053) for Mountain Home Air Force Base. The key details include a requirement for a Dedicated Internet Access (DIA) circuit delivering two (2) Gigabytes per second via fiber optic transport to Building 610. Current providers on the base are Lumen and Zito, though the specific incumbent cannot be disclosed for fair competition reasons. The Government will provide existing WiFi infrastructure including routers, access points, cables, and network switches, and will be responsible for their installation and maintenance. The contractor is expected to provide the fiber connection and internet service, with the public demarcation point located at 355 Liberator, Mountain Home AFB, Idaho. The solicitation covers a base year with four additional option years for WiFi and internet services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
366 OG WiFi
FA489725QC053
Question 1: We see Lumen and Zito as current providers on the base. Is this correct and do you currently have service from both? We would like to utilize known vendors for our response. If there are others, please advise.
Answer 1: Lumen and Zito are the current providers on base and both provide service.
Questions 2: We would appreciate clarification on” deliver and install a minimum of two
(2) Gigabyte per second (GBPS) of Commercial internet access via fiber optic transport”
-Does this mean 2 separate circuits?
-Would you require 2 diverse carriers?
Answer 2: This is only for one (1) circuit as well as one (1) diverse carrier.
Questions 3: Is there a Publicly resolvable address for “Building 610”? Maybe there is a public demarc at 366 Gunfighter or 355 Liberator?
Answer 3: 355 Liberator Mountain Home AFB, Idaho 83648
Question 4: Is this a requirement for a DIA (Dedicated Internet Access) circuit, or business-class internet service?
Answer 4: This requirement is for a DIA (Dedicated Internet Access) circuit.
Question 5: Based on the PWS, is only internet service required, or is Wi-Fi service also included?
Answer 5: The internet service will be connected to a router and the router will connect to a switch, which will have the access point connected to the switch to provide WiFi.
Question 6: Will the contractor be responsible for maintaining any Wi-Fi infrastructure, such as access points, switches, or cabling etc.? If so, could you please provide detailed information regarding the quantity and types of equipment that need to be maintained?
Answer 6: No, the Government currently has the access points, switches etc… in place and will be responsible for maintaining them.
Question 7: Will the contractor also be responsible for the installation of any access points, switches, cabling, or related commercial wifi components?
Answer 7: The Government will be responsible for the installation of any access points
Question 8: Is there an incumbent currently providing this service? If so, please share any available details.
Answer 8: Yes, however due to fair competition the vendors name cannot be released.
Question 9: Would this be a Wi-Fi set-up in the bldg with access points, network switches, etc? The way it reads to me it look like just a fiber line delivering 2Gbps to the bldg. where someone else would plug their own Wi-Fi router into the line.
Answer 9: Yes, this is for WiFi set-up in the building but the Government has routers, access points cables, and network switches in place.
Question 10: Could we get access to base fiber from building 2318 to bldg. 610? There’s unused fiber in 2318 that if not already going to 610 can likely be cross-connected.
Answer 10: No, building 2318 is not part of this requirement and the contractor will need to provide fiber. The vendor who has fiber in 2318 would need to bid this contract and win, for them to use the existing fiber.