SOW - Storm Drain System Redesign - Bldg 1788_16 JAN 2025.pdf

PDF 257 KB Posted

Attached to
Bldg 1788 Storm Drain Repair Federal contract opportunity
Solicitation number
FA489725B0005
Issued by
Department of the Air Force Air Combat Command

About this file

This Statement of Work (SOW) details a construction project for storm drain system redesign at Building 1788 on Mountain Home Air Force Base in Idaho. The project scope includes adding gutters over courtyard access doorways, demolishing interior courtyard concrete and storm infrastructure, installing new concrete and trench drain, replacing 6-inch storm drain pipe, and repairing joint and masonry sealants. The work was necessitated by significant flooding during a precipitation event in August 2023 that exposed drainage system deficiencies.

The contract requires a 150-calendar day performance period from the Notice to Proceed, with specific technical requirements including protecting indoor spaces, installing a new floor trench drain, replacing concrete surfaces, adding gutter sections, and applying masonry sealants. The project involves careful coordination with base operations, adherence to safety protocols, and compliance with Department of Defense Unified Facility Criteria. Contractors will need to submit detailed schedules, follow strict security access procedures, and complete comprehensive site restoration, with a one-year warranty on all work performed.

View the file

Other files for this federal contract opportunity

Other files attached to Bldg 1788 Storm Drain Repair, newest first.
File Type Posted
Presolicitation - Sources Sought Bldg 1788.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR CONSTRUCTION

INVITATION FOR BIDS

QYZH230009

Storm Drain System Redesign for Building 1788

24 February 2025

1.0 INTRODUCTION

The United States Government (USG) has a requirement for Construction Services for Mountain Home Air Force Base (MHAFB), Mountain Home, ID. Work for the site generally consists of the addition of gutters over the access doorways to the courtyard at Building 1788, demolition of the interior courtyard concrete, tree wells, and storm inlet, grading and installation of new concrete and trench drain in the courtyard, replacement of 6-inch storm drain pipe, and repair failed and/or missing joint sealant and masonry sealant in courtyard.

The complete design package with drawings and specifications is provided herein. All work shall be in accordance with current Department of Defense Unified Facility Criteria (UFC) and Unified Facilities Guide Specifications (UFGS).

2.0 BACKGROUND INFORMATION

Due to an unusually high level of precipitation that occurred on August 3rd of 2023, the storm drain system for Building 1788 was unable to provide enough drainage, resulting in significant flooding and damage to the facility. The exterior walls of the facility consist of concrete masonry units where mortar joints appear to be split or separated at some locations. The main entry doors and windows consist of aluminum storefront framing where joint sealants are missing or failing at several locations, specifically around the window frames and at door thresholds. Pitched roofs are provided around the perimeter of the courtyard, the roofs consist of standing seam metal panels where no gutters or downspouts are installed, resulting in storm water from the roof draining directly to the ground in front of the door openings.

3.0 PERIOD OF PERFORMANCE

3.1 The period of performance for the following Statement of Work (SOW) shall be 150 calendar days from the Notice to Proceed (NTP).

3.2 The contractor must keep the Government appraised of the work schedule by providing a Baseline Schedule per the Submittal Schedule and a 3-Week Look Ahead Schedule of upcoming work to be performed. If the Contractor foresees a delay in Project completion beyond the requested completion date, the Contractor shall notify the USG Contracting Officer (KO) and USG Project Manager, in writing, of the reasons for the delay and provide a Get-Well-Plan to get back on schedule.

4.0 DESCRIPTION OF WORK: The Contractor shall provide all plant, labor, materials, equipment, supervision, and services to execute and satisfy the requirements in the Design, Drawings, Specifications, and this Statement of Work. See design sheets and plans for more information.

General description of work to be performed as follows:

4.1 Removal and replacement of door frames to allow construction access to courtyard.

The removal of existing door, door frames, and door access control systems will be required for contractor access. All parts shall be salvaged for reuse and reinstall.

4.2 Protection of indoor spaces necessary for construction access to the courtyard.

Contractor to relocate all existing furniture within area of work, construct temporary flooring to protect existing flooring, provide a temporary access door in the exterior opening, install heavy duty plastic sheeting over existing ceiling, and construct temporary framed partitions over temporary flooring.

4.3 Demolish the existing interior courtyard concrete, tree wells, and storm inlet. Remove 1,507 SF (Contractor to field verify quantity) of concrete in courtyard. Sawcut at existing joints on perimeter. Retain and protect existing concrete between joint and wall. Retain and protect 6” storm drain in courtyard. Remove all material from site and dispose of in accordance with Local, State, and Federal requirements.

4.4 Demolish approximately 50 SF of concrete sidewalk necessary to remove 35 LF of 6” storm drain outside of the courtyard. NOTE: Retain and protect existing 6” storm drain cleanout. Salvage gravel for restoration.

4.5 Install a new 6-foot outdoor floor trench drain in the courtyard. Connect trench drain outlet to existing 6” cast iron pipe invert. Finish concrete shall be 1/8” higher than top of channel frame with a stainless-steel grate provided over the trench drain system.

4.6 Replacement of reinforced concrete over crushed aggregate to provide positive drainage in courtyard to the new area drain. Perimeter to match existing concrete grade.

Cut contraction joints at least 1” deep. Expansion joints at the junctions with the existing concrete to remain in the courtyard with the specified joint filler, bar and sealant. Produce a scored surface by brooming with a fiber bristle brush.

4.7 Replace 35 LF of 6” storm drain from cleanout to the outlet location with straight grade from cleanout to outlet curb cut. NOTE: Restore landscape gravel to original location.

4.8 Replace two panels, approximately 50 SF concrete sidewalk. Sidewalk slab to be constructed in place of demolished sidewalk. Match adjacent grades, slopes and finish.

4.9 Installation of 10-foot gutter sections located above the two doorway access locations to the courtyard. The existing roof does not include gutters and downspouts. To direct stormwater away from the door openings, two 10-foot sections of gutters, centered in the doorways, are proposed. Each downspout to include associated elbows and straps.

4.10 Replace failed and/or missing joint sealant. The courtyard main entry doors and windows consist of aluminum storefront framing. Joint sealants are missing or failing at several locations, specifically around the window frames and at the door thresholds. The contractor shall remove and scrape existing sealant around all door and window frames.

Replacement backer rod and sealant shall be provided as necessary.

4.11 Repair failed and/or missing masonry sealant in courtyard. The exterior walls consist of concrete masonry units with vertical expansion joints at regular intervals. Mortar joints appear to be split or separated at some locations. Cracked and split mortar joints shall be repaired with a silicon-based sealant with sand mix to match the appearance of existing mortar joints.

4.12 The masonry shall be cleaned, and a masonry sealer shall be applied over all masonry surfaces facing the courtyard. The existing masonry veneer consists of split-face colored concrete block, which is porous and prone to absorbing moisture due to both the nature or the concrete and the manufacturing process of the split-face blocks. To resist water penetration into the wall cavity from wind driven rain, it should be maintained every 5 to 10 years with a water-repellent sealer. The contractor shall be responsible for cleaning the blocks and applying the sealer across the full length of the masonry walls facing the courtyard.

4.13 At the completion of courtyard work, return building and interior corridor to the original condition. Demolish temporary framed partitions, remove plastic sheeting from existing ceiling, remove temporary flooring, and replace furniture in its original location.

All existing finishes shall be patched and repaired as necessary to match existing undamaged finishes, including but not limited to existing walls, ceilings, flooring, doors, etc. Reinstall door frames with proper backer rod and sealant at exterior doors. Verify doors function properly. Connect door access control system and verify the door security controls function properly.

5.0 GENERAL REQUIREMENTS

5.1 The proposal shall include a price breakdown by specification division with sufficient detail of all costs, including material, labor, equipment, subcontracts, and overhead and profit.

5.2 Work shall include furnishing all labor, materials, services, oversight and direction to complete the construction of the requirements identified in this Statement of Work (SOW), the project Design and Specifications.

5.3 Provide adequate professional supervision, quality control, and safety to ensure the accuracy, quality, timeliness, delivery, and completeness of the work during the execution of the construction.

5.4 Provide construction, materials, equipment, testing, and submittals as required by the attached Design Drawings, Specifications, and Submittal Schedule included in this contract.

5.5 Preconstruction Conference: Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference. The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site.

5.6 Red-Line Construction Drawings: During the progress of work, the Contractor shall keep a careful record of all changes and corrections from the original design layouts shown on the drawings. These red-line drawings will be maintained at the job site, available for inspection by the Government. Upon completion of the project the red-line drawings shall be submitted to the government Contracting Officer and Project Manager, electronically in PDF format, to be used to develop the As-Built Drawings.

5.7 The work is located on Mountain Home AFB main base in Building 1788. The site is secured by a fence. Upon award, the Contractor and all construction personnel will be verified through the Idaho Public Safety and Security Information System (ILETS) and shall be authorized for unescorted entry for access during normal working hours only, through an Entry Authority List (EAL). See Section 12.0 Security Considerations and Base Access for more information.

5.8 Working Hours: Regular working hours will consist of a 9-hour period between 7:30 am and 4:30 pm, Monday through Friday excluding Government holidays, allowed for the Contractor to implement this project at the Mountain Home AFB, Building 1788. Work outside regular working hours requires Contracting Officer approval.

5.9 The Contractor shall provide timelines and critical path items showing an understanding of the project requirements and capability in achieving the desired period of performance provided in this SOW.

5.10 Work Schedule: The Contractor shall submit for approval a Baseline Construction Schedule in the form of a Bar Chart Schedule to the Contracting Officer prior to start of work.

During project execution, the contractor is required to update the Construction Schedule at monthly intervals or when the schedule has been revised. A monthly Narrative Report shall be submitted, along with copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer. A 3-Week Look Ahead schedule shall be prepared and issued no later than 8 am each Monday to be reviewed during the weekly CQC Coordination or Production Meeting. All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) and Test Reports must reference Schedule Activities that are being addressed.

5.11 Payment will be made for costs associated with Wide Area Workflow (WAWF) upon approval of the AF-3065 Contract Progress Report.

5.12 If the Contractor chooses to have storage or facilities at the work site, pending availability, the Contracting Officer will designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. The Contractor shall maintain the area in a clean and orderly fashion and secure if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government. The Contractor shall restore the land to its original or better condition upon completion of work, including removing gravel used to traverse grassed areas.

5.13 Temporary Utilities: The Contractor shall provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.

5.14 Excavation Requirements:

5.14.1 Work Clearance Request: Before commencing work on an individual contract, the

Contractor shall prepare and coordinate an AF Form 103, Work Clearance Request, with drawings indicating where the existing subsurface improvements are in the area and specific excavation and trenching locations widths and depths. The Government will provide information on which offices on MHAFB must coordinate on the AF Form 103. The Contractor, in coordination with the Contracting Officer Representative (COR), shall hand carry the AF Form 103 to the coordinating offices and get their approval signatures.

5.14.2 Form 103 shall be provided to the Government prior to the Contractor requesting utility locates. A copy of the completed AF Form 103 shall be on the contract site for the duration of the contract.

5.14.3 Utility Locates: The Contractor must submit the AF Form 103 request at least fifteen

(15) working days prior to initiating excavation and trenching to arrange appointments to get utility spots at the site. The Contractor is responsible for protection of any underground utilities and structures identified on the AF Form 103 or by utility locate within five (5) feet of the identified location. The Contractor is responsible to maintain the utility locates until the Contractor no longer requires them to complete the execution of the TO. Should the Contractor damage any underground utilities or structures, they shall immediately notify the Base Civil Engineer Service Desk and the COR. If the damaged item was identified on the AF Form 103 or by the utility locate, the Contractor shall repair the damage immediately and return the item to its original working condition at their own expense. If the damaged item was not identified on the AF Form 103 or by the utility locate, the Government will repair it at their expense.

5.15 Inspections, Tests and Reports:

5.15.1 Any required inspections, tests, and reports made by the Contractor, subcontractors, specifically trained technicians, equipment manufacturers, and others as required by a contract shall be furnished upon request to the Government in accordance with the terms of the contract.

5.15.2 The Contractor shall obtain on-site inspection review and permission from the COR/Inspector before back filling any trenches, pouring of concrete or utility tie-ins.

The Contractor warrants that authorized Government Representatives shall have unimpeded access to examine the work site(s), staging area(s) and all other areas utilized by the Contractor in the performance of a contract for the purposes of assessing the Contractor's performance and for any other purpose deemed necessary by the KO or authorized Government Representative.

5.16 Protection of Water Resources: Protection of Water Resources: The Contractor shall not discharge stormwater from construction sites nor discharge excavation ground water to the sanitary sewer, storm drains, or to surface waters. If the water is noted or suspected of being contaminated, it may only be released to the storm drain system if the discharge is specifically permitted. Obtain authorization in advance from the KO and Environmental for any release of contaminated water. Discharge of hazardous substances will not be permitted under any circumstances. The National Pollutant Discharge Elimination System (NPDES) stormwater program requires operators of construction sites of greater than 1 acre to obtain authorization to discharge stormwater under an EPA NPDES Construction General Permit (CGP). The Contractor shall refer to Idaho DEQ's Catalog of Stormwater Best Management Practices (BMPs) for Cities and Counties (http://www.deq.idaho.gov/media/622263-Stormwater.pdf) and utilize the necessary/appropriate BMPs for controlling/preventing stormwater runoff.

5.17 Disposal of Waste:

5.17.1 All construction debris will be taken off base to a state-approved landfill.

5.17.2 All trucks containing loose debris shall ensure that upon leaving the site, the debris is loaded in such a manner that shall prevent dropping of materials on streets and conform to local ordinances/laws. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The Contractor shall be responsible for cleaning up any materials that fall from trucks and be held liable for any resulting damages. NOTE: Idaho Waste Systems (IWS) will no longer accept ANY liquid wastes from Mountain Home AFB.

5.17.3 The Contractor shall submit all trip tickets from the landfill facility to show all debris is being disposed of in an approved landfill and in accordance with all Federal and State requirements.

5.17.4 To the extent practicable, all scrap metal, cardboard, wood pallets and #1-2 plastic must be sent for reuse or recycling and will not be disposed of in a landfill.

Recyclable materials may be dropped off at the base Recycling Center or when coordinated in advance, the Recycling Center may assist with material pick-up.

5.18 Submittals: Submittal Register is provided within the Design Specifications. The Contractor shall submit to the Contracting Officer for review and approval the following information: Preconstruction Submittals, Shop Drawings, Product Data, Samples, Design Data, Test Reports, Certificates, Manufacturer’s Instructions, Operation and Maintenance Data, and Closeout Submittals. All material Submittals shall be original vendor information (not copies).

5.19 The Contractor shall secure all supplies and equipment stored on the project site to discourage theft or damage. Contractor shall maintain the project site in a clean, safe and orderly manner. Protection and security for materials and equipment on site is the sole responsibility of the Contractor.

5.20 Material salvage and recycling: All non-hazardous material should be recycled as much as possible. MHAFB has a recycling program, and the Point of contact is Michael Wussow, Solid Waste Program Manager, 208.828.6667.

5.21 Hazardous Materials to include, but not limited to, Asbestos Containing Materials (ACM), lead based paint (LBP), mold, and mercury. The Contractor’s proposal shall include removal and dispose of any known hazardous materials in accordance with State and Federal rules and regulations and survey to determine if any additional ACM, LBP, mold, mercury or other hazardous material are contained in the contract work area. If additional hazardous materials requiring remediation are identified during the survey, or during construction, the Contractor will address them under a modification to the contract.

5.22 The Contractor shall thoroughly review the project request for constructability and advise the Government of possible problem areas prior to submitting a proposal.

5.23 Progress of Work: Once awarded a contract, the Contractor shall submit for approval all work schedules to the Government before start of work, unless otherwise specified. The reports contemplated by FAR Clause 52.236-15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. This requirement is applicable to a contract with a minimum performance period of greater than 60 calendar days unless otherwise specified by the KO.

5.24 The Contractor shall hold weekly progress meetings to discuss current status, future scheduled work and any coordination requirements.

5.25 Pre-Final and Final Inspection:

5.25.1 Contractor shall request from the KO a final acceptance meeting. The request shall be in writing (email is sufficient) at least three (3) working days prior to the meeting.

5.25.2 Meeting will be chaired be the KO and attended by appropriate Government and

Contractor personnel. It is mandatory the contract superintendent be in attendance.

5.25.3 If any Contractor personnel are still working on the contract or it becomes obvious to the KO that the work is not ready for final acceptance, the KO will immediately cancel the final acceptance meeting and direct the Contractor to reschedule when the work is complete.

5.25.4 The Government will generate a punch list of deficiencies that the Contractor must complete prior to the Government taking beneficial occupancy of the facility. During the final acceptance meeting, the KO will ask the Contractor how much time he/she requires to correct the deficiencies and both parties will come to an agreement on the number of days to correct the deficiencies. The Government will schedule a meeting to verify the deficiencies are corrected.

5.26 Minimize interference with, disturbance to, and damage to fish and wildlife, and plants including their habitat to protect threatened, endangered, species of concern, migratory birds, or otherwise protected animal and plant species, including their habitat in accordance with the MHAFB Integrated Natural Resources Management Plan (INRMP), federal, state, regional, and local laws and regulations. Protection of migratory birds, particularly burrowing owls, is of concern on MHAFB. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor’s responsibility.

5.27 A burrowing owl and ground nesting bird survey is required prior to the start of construction. Do not disturb ground nesting birds; burrowing owls are protected under the Migratory Bird Treaty Act. Call 366 CES/CEIE, Natural Resources Program Manager at

(208) 828-1784 or (208) 828-6351, who will conduct the survey and assist with wildlife/bird conflict issues.

5.28 The Government Project Manager and Construction Inspector will inspect all work, materials or equipment used on site at any time during execution of the work.

5.29 Concealed Work: All items of work to be concealed shall be inspected by the Government prior to concealment. All Government inspection shall be within the work hours specified in paragraph 3.7 “Work Times.”

6.0 COORDINATION and AUTHORITY

6.1 All work shall be conducted under the general direction of the KO. References to “Contracting Officer” in the scope of work, specifications, drawings, etc. may be interchangeable with Contracting Officer’s Representative (COR), Contracting Officer’s Technical Representative (COTR), Project Manager (PM), Inspector, Subject Matter Expert (SME), “shop”-specific personnel, or other Government representative(s) that are assisting the KO with technical monitoring or administration of contract requirements, identified, appointed, or delegated certain responsibilities by the KO.

6.2 Under no circumstances shall anyone other than the Contracting Officer (KO) have authority to make any commitments or changes on behalf of the Government with the contractor that affect price, quality, quantity, delivery, or any other terms and conditions of the contract, nor shall any other Government representative in any way direct the contractor or its subcontractors to operate in conflict with the contract terms and conditions.

6.3 Upon award, the Contractor shall proceed with securing payment and performance surety bonds. No other efforts shall commence until the KO issues a Notice to Proceed (NTP) except for attendance of a preconstruction conference. The conference will be held with the KO prior to the start of construction at the work site. Upon receipt of an NTP, the Contractor shall proceed with all other efforts required by the contract. All preconstruction submittals shall be approved prior to commencement of any construction at the work site, unless otherwise authorized by the KO.

7.0 WORK PROGRESS and SCHEDULE

7.1 The scheduling and reporting of percentage of completion contemplated by FAR Clause

52.232-5 Payments under Fixed-Price Construction Contracts and 52.236-15, Schedules for Construction Contracts, shall be accomplished on or equivalent to an Air Force Form (AF) 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report.

7.2 The project schedule shall incorporate, as applicable, milestone events specified in the contract, including, notice to proceed, substantial completion, milestones related to specified work phases and site restrictions, Contractor-defined milestones to identify target dates for critical events based upon the Contractor’s chosen sequence of work, and depict all major activities necessary to complete the work.

7.3 The Contractor shall also prepare and submit for approval a cost breakdown of the Contract price, to be referred to as the “schedule of values”, assigning values to each major activity necessary to complete the work. Values must include all direct and indirect costs, although a separate value for bond costs may be established.

7.4 The schedule of values must contain sufficient detail to enable the Contracting Officer to evaluate applications for payment. If the percentage completed for the monthly reported period is less than the approved scheduled percentage the contractor shall provide the KO with an explanation for falling behind. If progress will not be regained within the next monthly reported period, the contractor shall provide the KO a supplementary schedule for approval demonstrating how progress will be regained.

7.5 Progress payments may be made up to substantial completion (95%) and after a pre-final inspection has occurred with the KO. The final progress payment of 5% (Final Invoice) will only be made following completion of any remaining punch-list items and final inspection, submission of the final progress report (100%), any remaining submittals, records, drawings, payrolls, Standard Form 1413s, release of claims, and other closeout documents, and turnover of Government property (materials, equipment, keys, etc.).

7.6 MHAFB Building 1788 will be occupied during performance of work under this Contract during the hours of 0700 - 1700. Occupancy notifications will be posted in a prominent location in the work area. Work that would impact Building operations; including but not limited to disturbance of existing utilities serving facilities occupied and used by the Government, including water, sewer, electrical, and steam services; may not be done during this timeframe. Before work is started, arrange with the Contracting Officer times for work and a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways if applicable.

7.7 Before, during and after the demolition work continuously evaluate the condition of the site-specific features being demolished and take immediate action to protect all personnel working in and around the project site.

7.8 Provide regulatory notification requirements in accordance with federal, state, and local regulations. Submit copies of regulatory notifications to the Contracting Officer at least 14 days prior to commencement or work activities. Typically, regulatory notifications must be provided for the following (this listing is not all-inclusive): demolition, renovation, NPDES defined site work, construction, removal or use of a permitted air emissions source, and remediation of controlled substances (asbestos, hazardous waste, lead paint).

7.9 Weekends, Federal holidays, and any associated ‘AF Family Day’ are non-workdays and decrease the availability of Government personnel for coordination. Federal holidays are:

New Year’s Day; Birthday of Martin Luther King Jr; Inauguration Day; Washington’s Birthday/President’s Day; Memorial Day (associated Family Day); Juneteenth National Independence Day (associated Family Day); Independence Day (associated Family Day);

Labor Day (associated Family Day); Columbus Day; Veterans Day; Thanksgiving Day (associated Family Day); and Christmas Day (associated Family Day).

7.10 Further decreased availability of Government personnel shall be anticipated during the workweeks of the Thanksgiving, Christmas and New Year’s holidays. It is the responsibility of the Contractor to adequately plan for and schedule all coordination necessary (i.e. base/site access, submittals, construction) in advance of known non-workdays.

7.11 Coordinate work during weekends and holidays with the Project Manager and/or Project Inspector at least one week in advance.

7.12 Transfer and Acceptance of Military Real Property (DD 1354): At completion of project, the Contractor shall fill out and submit a “Transfer and Acceptance of Military Real Property" (DD 1354). The DD 1354 form can be obtained from http://www.dtic.mil/whs/directives/forms/eforms/dd1354.pdf

8.0 CODES AND STANDARDS

8.1 Work shall meet the requirements of the plans and specifications and shall not be less than the minimum requirements of applicable sections of the latest adopted Codes and Standards of following organizations (Not All Inclusive – See Each Specification Division)

AASHTO – American Association of State Highway and Transportation Officials ABA – Architectural Barriers Act ACI – American Concrete Institute AFCFS – Air Force Corporate Facilities Standards AFI – Air Force Instructions ASTM – American Society for Testing and Materials ISPWC – Idaho Standards for Public Works Construction MHAFB Temporary Environmental Controls Specifications MUTCD – Manual on Uniform Traffic Control Devices NCMA – National Concrete Masonry Association OSHA – Occupational Safety and Health Administration UFC – Unified Facilities Criteria UFCG – Unified Facilities Guide Specifications

9.0 SAFETY

9.1 In order to provide safety controls for protection to the life and health of employees and other persons, for prevention of damage to property, materials, supplies, and equipment, and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with all pertinent provisions of the Corps of Engineers Manual, EM 385-1-1, entitled “Safety and Health Requirements Manual,” as most recently amended at time of contract notice to proceed (NTP). The Contractor shall also take or cause to be taken such additional measures as the KO, or his/her designated representative may determine to be reasonably necessary for the purpose.

9.2 The Contractor shall comply with OSHA General Industry Safety and Health Standards (29 CFR 1910), Publication V2206 and OSHA Construction Industry Standards (29 CFR 1926).

9.3 The Contractor shall submit with the Quality Control Plan, the name of the designated on-site safety persons responsible for ensuring that all safety and accident prevention provisions of this Statement of Work are implemented and enforced. The Contractor shall ensure his personnel receive safety training and briefings and that all safety inspections, practices, and procedures are within compliance. The name of the designated on-site safety persons, safety training, briefings, inspections, practices and procedures shall be included in the Quality Control Plan.

9.4 The Contractor will maintain an accurate record of, and will report to the KO, or his/her designated representative, in the manner and on the forms prescribed by the KO or his/her designated representative. The Contractor will report exposure data and all accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies, and equipment incident to work performed under this contract.

9.5 The KO or his/her designated representative will notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the site of the work, shall be deemed sufficient for this purpose. If the Contractor fails or refuses to comply promptly, the KO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of a claim for extension of time or for excess costs or damages by the Contractor.

9.6 The Contractor will be responsible for the safety and health compliance of all subcontractors.

9.7 The Contractor shall indoctrinate each employee to ensure clear understanding of the following subject areas, but not limited to:

9.7.1 The purpose of the accident prevention program (i.e., to minimize hazards and prevent injuries).

9.7.2 A review of the hazards inherent in the work environment and the precautions to be taken.

9.7.3 Location of first aid and other emergency facilities

9.7.4 A detailed description of what to do in case of injury, fire, or identification of a safety hazard.

9.7.5 Review of cleanup procedures

9.7.6 Required safety equipment including earplugs, googles, face guards, respirators, protective clothing, hard-hats, etc. (when and how to use).

9.7.7 Location of company safety rules (posting or handout)

9.7.8 Identification of the Contractor employees responsible for safety/accident prevention.

9.8 In addition to normal safety practices, the Contractor shall comply with the following requirements:

9.8.1 The safety of Contractor personnel on-site is the Contractor's responsibility.

9.8.2 All personnel shall receive an initial Air Force safety briefing, prior to site entry, and will comply with all requirements set forth in that briefing. All personnel shall comply with Air Force on-site safety procedures and the US Army Corps of Engineers Safety Manual EM-385-1-1 as directed by the Contracting Officer.

9.8.3 The Contractor shall ensure that safety barriers/portable ladders, ladder extensions, or environmental covers are properly installed at access hatches and excavations.

9.8.4 Equipment shall be placed so as not to impede normal traffic in and out of the work area, nor to interfere with emergency exit from work area and off-site.

9.8.5 Extreme caution must be exercised to preclude personal contact with energized electrical circuits. Contractor shall comply with NFPA 70 and 72E for electrical safety.

9.8.6 Hard-hats shall be worn in accordance with EM-385-1-1 requirements and hard-toed safety shoes shall be worn by all personnel at all times on the work site. Other safety items such as ear protection, respirators and safety glasses, which are required by EM-385-1-1 and/or the manufacturer of products for specific hazards, shall be available and used as necessary.

9.8.7 All heavy equipment shall be equipped with backup alarm in accordance with EM- 385-1-1 regulations.

9.8.8 All vehicles shall be in safe operating condition. Vehicles and equipment not in compliance with EM-385-1-1 requirements shall not be allowed on site.

9.9 Several hazards inherent to the work environment must be recognized. They include, but are not limited to:

9.9.1 Electrical circuits and devices pose serious and generally continuing hazards.

Contractor shall comply with NFPA 70 and 72E for electrical safety. The Contractor shall take every precaution to prevent personnel injury. Ground Fault Interrupters (GFI's) shall be in-line appliances on all temporary electrical circuits installed near the supply.

9.9.2 Mechanical devices can pose serious hazards when operated. Appropriate precautions shall be taken.

9.10 First aid and medical requirements are as follows:

9.10.1 The Contractor shall comply with accident response requirements. These requirements are provided in a safety briefing by base personnel at the pre-construction conference. The Contractor shall keep these requirements on file at the working site for inspection by Air Force personnel and the Contracting Officer Representative (COR).

9.10.2 The Contractor shall maintain an emergency first aid kit at the work site.

9.10.3 All accidents (employee injuries and vehicle, building, or equipment property damage, etc.), regardless of severity, shall be reported promptly to the Contracting Officer.

10.0 SUBMITTALS

10.1 Submittal Register is provided within the Design Specifications. The Contractor shall submit to the Contracting Officer for review and approval the following information:

Manufacturer's product brochures and catalog data for all equipment, components and materials to be installed. All material Submittals shall be original vendor information (not copies).

10.2 All submittals will be coordinated through the Contracting Office using an AF Form 3000.

The KO may request submittals in addition to those specified when deemed necessary to adequately describe work covered.

10.3 Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. If the submittal is incomplete or otherwise does not provide the Government with sufficient detail, the KO may request additional information to determine compliance; such requests shall not be construed as Government delay or entitle the contractor to any equitable adjustment.

10.4 The Government shall be allotted 14 calendar days after the date the Government receives the submittal to complete reviews. Upon transmission of the submittal to the Government the contractor shall confirm its receipt.

10.5 Approval of a submittal shall not be construed as a complete check and indicates only that the Government does not otherwise object to the submittal.

10.6 Approval shall not relieve the contractor of the responsibility to meet contract requirements or for any error.

11.0 REFERENCES

11.1 Design Analysis (provided)

11.2 Design Drawings (provided)

11.3 Design Specifications (provided)

12.0 SECURITY CONSIDERATIONS and BASE / SITE ACCESS

The security requirements set forth in this section represent the minimum acceptable security standards for this project. The security requirements set forth in this section are intended to supplement the contract, other specifications and other security standards applicable to the Contractor. Nothing in this section is intended to supersede the contract, other specifications or other security standards applicable to the Contractor. Any questions concerning the purpose and scope of this section or any perceived conflicts between this section and other contract documents and security standards should be immediately brought to the attention of the USG Contracting Officer (KO) and USG Project Manager.

12.1 All workers shall be subject to the base rules of entry and exit and subject to search at any time.

12.2 The Contractor shall cooperate fully in all security matters, which may arise relating to this contract and/or base activities.

12.3 It is prohibited to carry/use weapons on the site without prior USG approval. If approval is granted, personnel will abide by Base policies for authorized use.

12.4 Cellphones are authorized on the site. Only “hands free” use is allowed while operating a motor vehicle.

12.5 Base Access to the MHAFB must be obtained by completing an SF Form 30 for all individuals who need access to the project site. The SF Form 30 will be provided to the Contractor after contract award. Individuals will be vetted for security by the USG before given access to the project site with an approved SF30.

12.6 The Contractor shall submit all project SFS Form 30s to the KO (Sponsor) for processing to the VCC prior to the two-week lead time. No consideration shall be given to the Contractor for delays or cost increases experienced due to failing to request base access in a timely manner, nor due to the denial of base access to a contractor or subcontractor employee following the Government-performed background check.

12.7 Base access under this contract shall adhere to the most current entry protocols found at https://www.mountainhome.af.mil/Base-Resources-Helping-Agencies/Visitors-Control- Center/

12.8 The project site is a controlled area. All workers must be included on an Entry Authority List (EAL) to gain authorization for unescorted access to the worksite. Movement within the site will be confined to a designated free zone as specified by the Facilities Manager and Contracting Officer. The following information for all personnel requesting access to the project site must be submitted to the PM before being added to the EAL.

Last Name First Name Middle Name Date of Birth State DL# Company

12.9 The Contractor will be working in an existing building which is occupied. The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

12.10 Delays in entering and leaving work area: If the work site is located in a controlled area, the Contractor may experience delays due to compliance with entrance / exit requirements of the restricted/controlled areas. The Contractor shall not be compensated for reasonable delays in accessing these restricted / controlled areas. The contractor may also be requested to leave a restricted or controlled area at any time. The Contractor shall not be compensated for reasonable delays due to these security measures. The KO may extend the contract period of performance when there is a change in security designations that limit or diminish Contractor access to a work site after commencement of contract performance.

The KO may also extend the period of performance of a contract to offset undue delays, singular or cumulative, due to Contractor's compliance with security restrictions.

12.11 All the aforementioned security procedures are strictly enforced. Inappropriate action and/or violations may result in the immediate termination and removal of said individual and/or Contractor from the base.

13.0 PERSONNEL

13.1 The Contractor shall employ sufficient management and contract administration resources, including personnel responsible for project management, field superintendence, change order administration, estimating, coordination, inspection, and quality control, to ensure proper execution and timely completion of work.

13.2 The Contractor shall designate a principal of the firm or other senior management official to provide executive oversight and problem resolution resources to projects for the life of the contract.

13.3 The Contractor shall employ and require its subcontractors to employ only qualified personnel to perform work required for each project.

13.4 The Government reserves the right to exclude, or remove from the worksite, any personnel for reasons of incompetence, carelessness, or insubordination, who violate rules and regulations concerning conduct on federal property, or whose continued employment on the worksite is otherwise deemed by the Government to be contrary to the public interest.

13.5 Under this Contract, the contractor may “dual-hat” the positions of Superintendent, Safety, and Quality Control manager.

13.6 The Contractor shall ensure their designee meets or exceeds the required qualifications of each role for which they are designated. Prior to construction, the Contractor shall provide the KO with written designation of each role, proof of qualifications for each designee, and work contact information (desk/mobile phone, email).

https://www.mountainhome.af.mil/Base-Resources-Helping-Agencies/Visitors-Control-Center/ https://www.mountainhome.af.mil/Base-Resources-Helping-Agencies/Visitors-Control-Center/

13.6.1 Superintendent: The project superintendent must be an individual with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting the schedule and construction drawings. If the superintendent is permitted to also serve as the Quality Control (QC) Manager, the superintendent must also possess those qualifications.

13.6.2 Quality Control Manager (QCM): The QC Manager must be an individual with a minimum of 5 years of combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on a similar size and type construction contracts which included the major trades that are part of this contract. The individual must have at least 2 years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability.

13.6.3 Site Safety and Health Officer (SSHO): All SSHOs will have met the training and experience requirements in EM 385-1-1 and this contract.

13.6.4 Environmental Manager: The Environmental Manager must be an individual trained to adequately accomplish the following duties: ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure Contractor personnel are trained in 40 CFR requirements in accordance with their position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

13.7 The Contractor and Subcontractor personnel shall present a neat appearance and be easily recognizable as Contract employees when they are on MHAFB.

13.8 Contractor and subcontractor vehicles shall have identification and shall be neatly stenciled or printed (not handwritten). Magnetic signs are acceptable. The identification shall be legible from 25 feet and be on the driver and passenger side of each vehicle. The sign shall include contractor name, contactor address, and contractor phone number.

13.9 The Air Force has banned use of all tobacco products on Air Force bases except in designated outdoor locations. Contractor employees and visitors are subject to the same restrictions as are Government personnel.

14.0 PROJECT CLOSEOUT

14.1 Contractor shall notify the Contracting Officer at least 14 calendar days prior to the date a final acceptance inspection can be held. State within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the date of the final inspection.

14.2 The Contractor must be represented by the QC Manager, the Project Superintendent, and others deemed necessary. Attendees for the Government will include the Contracting Officer, other Government QA personnel, and personnel representing the Client.

14.3 Failure of the Contractor to have all Contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government’s additional inspection cost in accordance with the Contract Clause entitled “Inspection of Construction”.

14.4 Contractor shall leave premises “broom clean”. Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances; polish transparent and glossy surfaces; vacuum carpeted and soft surfaces. Clean equipment and fixtures to a sanitary condition. Clean filters of operating equipment. Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas. Remove waste and surplus materials, rubbish and construction facilities from the site.

15.0 WARRANTY OF CONSTRUCTION: In addition to any other warranties in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, workmanship or contractor furnished design or that furnished by any subcontractor or supplier at any tier. This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes and/or fraud.

15.1 This warranty shall continue for a period of one (1) year from the date of final acceptance of the work.

15.1.1 If the Government takes beneficial occupancy of a portion of the project, prior to final acceptance of the entire project, the warranty for the portion occupied will commence on the date of its occupancy.

15.1.2 For all other portions not beneficially occupied, the warranty shall begin on the date of their beneficial occupancy, or final acceptance of the entire project, whichever occurs first.

15.1.3 In the event the Contractor’s warranty of this clause has expired, the Government may bring suit, at Government expense, to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.

15.2 The Contractor shall remedy, at the Contractor’s expense, any failure to conform or any defect. In addition, the Contractor shall remedy, at the Contractor’s expense, any damage to Government-owned or controlled real or personal property when that damage is the result of:

15.2.1 The failure by the Contractor, subcontractor, or supplier at any tier, to conform to contract requirements or,

15.2.2 Any defect of equipment, material, workmanship, or design furnished.

15.3 The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for one year from the date of repair or replacement.

15.4 The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

15.5 If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

15.6 With respect to all warranties, express or implied, from subcontractors, manufacturers or suppliers for work performed and materials furnished under this contract, the Contractor shall:

15.6.1 Obtain all warranties that would be given in normal commercial practice.

15.6.2 Require all warranties to be executed, in writing, for the benefit of the Government if directed by the Contracting Officer and enforce all warranties for the benefit of the Government if directed by the…

This is the start of the file's text. The full file is on GovTribe.