Attachment 1 - ACC_A4DX Statement of Work (SOW).pdf

PDF 136 KB Posted

Attached to
ACC/A4 Access Control System (ACS) Update
Solicitation number
FA489025Q0008-2
Issued by

About this file

This Statement of Work (SOW) is issued by the Department of the Air Force, Headquarters Air Combat Command, for updating the Access Control System (ACS) at Building 681 on Langley AFB. The project requires furnishing and installing new compatible ACS equipment, including hardware and infrastructure for seven interior doorways, updating the existing Genetec Advantage Security Center 5.9.3.0 system, providing an 8-hour runtime battery UPS, and establishing a 5-year service plan. The Government will fund the first year of the service plan at contract award. The current system controls seven doorways (5 exterior, 2 interior) with expired warranties, and all cables are to be relocated to the 1st floor communication room (Room 130), while maintaining the onsite workstation in the 2nd floor communication room (Room 237).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS AIR COMBAT COMMAND

JOINT BASE LANGLEY-EUSTIS VA

People First… Mission Always…

16 July 2025

Statement of Work (SOW) to

Update Access Control System (ACS) for Facility Bldg. 681

Air Combat Command’s Director of Logistics, Engineering, and Force Protection (ACC/A4) requests a proposal to furnish and install new compatible ACS equipment, hardware, mechanical door locking hardware, and infrastructure on seven (7) interior doorways; update existing ACS system; provide 8-hour runtime battery UPS; and provide 5-year service plan for the entire ACS system in building 681 at 130 Douglas St., Langley AFB, VA 23665. The Government will fund the first year of the service plan at contract award.

Site surveyors must take note that the facility currently has a Genetec Advantage Security Center 5.9.3.0 installed which controls seven (7) doorways (5 - exterior, 2 - interior). All warranties have since expired.

Panels for the existing system are installed on the 1st floor communication room (room 130).

Currently, all existing circuits/cables are pulled to one room (Room 130) via existing conduits with the onsite workstation located on the 2nd floor communication room (Room 237). The expectation is for all cables to be pulled back to the 1st floor communication room (room 130) and the onsite workstation remain in the 2nd floor communication room.

SOW Attachments:

Bldg. 681 GENTEC ACS Update Bldg. 681 Map of New and Existing Doors

File details come from the government source that posted it. Updated .