This document contains questions submitted in response to a request for information (RFI) regarding a federal solicitation to renovate Facility 131 at Davis-Monthan Air Force Base.

The solicitation seeks to reconfigure and renovate restrooms and the janitor's closet, consolidate communications equipment, reconfigure the facility entrance, remove extraneous exterior materials, clean and paint exterior walls, provide a new wet sprinkler system including a fire water service line and fire department connection, replace the fire alarm system with a new Monaco analog/addressable system, install a new mechanical system including ductwork, controls, variable air volume systems, chillers, pumps, computer room air conditioning units, fans and insulation, replace the electrical service and install a new interior electrical system including service entrance equipment, panels, feeders, branch circuits, outlets and grounding. The questions and answers provided clarify details of the scope of work such as wall textures, roof deck materials, communications standards, and coordination of work during phasing.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Facility 131, newest first.
File Type Posted
Amendment 3-Revised C-500 sheet.pdf PDF
Amendment 3-WD-AZ20210032 dated 03052021.pdf PDF
Solicitation Amendment FA487721B00030003 SF 30.pdf PDF
Final Sign-In Sheet Site Visit Fac 131.xlsx XLSX spreadsheet
Amendment 2_ Attachment 2- Air Force Approval Memorandum.pdf PDF
Amendment 2_ Attachment 1- Sheet M-001.pdf PDF
Amendment 2- SF 30 Final.pdf PDF
Solicitation Amendment FA487721B00030001 SF 30.pdf PDF
Solicitation Amendment - FA487721B00030001.pdf PDF
Solicitation - FA487721B0003.pdf PDF
7 Plans_Bldg 131.pdf PDF
8 Asbestos and LBP Survey Report.pdf PDF
6 DMAFB Design Guide.pdf PDF
3 AF Form 3052.pdf PDF
2 WD - AZ20210032 Jan 2021.pdf PDF
5 Specifications.pdf PDF
9 Contractor Environmental Guide_2019.pdf PDF
10 Submittal Register.xlsx XLSX spreadsheet
1 Template of Contractor EAL.xls XLS spreadsheet
4 Bid Schedule.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFI LOG
Solicitation NumberFA487721B0003
TitleFacility 131
RFI #QuestionContractorResponse
1Is any “Design” required for this project? If so, will the USAF provide the full design requirements and a deliverable schedule?D Square Construction LLCAll design requirements are detailed in the construction documents
2Sheets A-111 & A-401 depict a Shower Enclosure, Room 106. Will the Govt. clarify if this shower will require the typical ADA accessories (i.e., grab bars, shower seat, curtain rod, curtain, etc.)?D Square Construction LLCADA shower accessories are shown on sheet A-501, Detail 5 & 6. Please see Specifications 10 28 13 for addition details and requirements for toilet accessories.
3Shall the existing Building 131 Vindicator v5’s, Security Tunnel, Site Commander and SAW II machines be removed and then reinstalled/reconfigured to the new IDS requirement?Desert DatacomThe existing Building 131 Vindicator v5’s, Security Tunnel, Site Commander and SAW II machines shall be removed and then reinstalled/reconfigured to the new IDS requirement.
4Drawing Sheet ES-100, Keynote #7 states “NEW TELECOMMUNICATIONS DUCTBANK FROM COMM ROOM 109 TO EXISTING TELECOMMUNICATIONS MANHOLE. PROVIDE 2-4" C WITH 4 CELL INNERDUCT - PULL 36 STRAND FIBER, 25 PAIR COPPER. CONFIRM LOCATION OF MANHOLE WITH GOVERNMENT PRIOR TO INSTALLATION.” The manhole is not depicted on the Drawings. Will the Govt. provide the location or appx. distance of the existing manhole?D Square Construction LLCThe circle with adjacent "COMM" verbiage on Sheet ES-100 is the approximate location of the manhole
5Drawing Sheet ES-100, Keynote #8 states “USE EXISTING CONDUIT PATHWAY TO ROUTE CABLES FROM BUILDING 88 TO COMMUNICATIONS MANHOLE (APPROXIMATELY 600'-0"). 36 STRAND SINGLE MODE FIBER OPTIC CABLE AND 25-PAIR COPPER FROM BUILDING 131 SHALL BE TERMINATED IN BUILDING 88. PROVIDE SPLICES AT BUILDING 88 FOR CONNECTION TO EXISTING BASE COMMUNICATIONS SYSTEM.” The manhole for Building 88 is not depicted on the Drawings. Will the Govt. provide the location or appx. distance of this existing manhole?D Square Construction LLCThe distance between Bldg. 88 to the Comm manhole (location in response above) is approximately 600'.
6Drawing Sheet E-102, Keynotes #6 & #7, will the Govt. clarify if these outlets are designated as OM4 or Cat 6?D Square Construction LLCThe outlets in keynote 6 and 7 are junction boxes to accommodate future cable pull.
7Drawing Sheet E-402, Detail 1 – Work Area Outlets, will the Govt. clarify if these 4-port faceplates are per SIPR, NIPR, JWICS, NSA cable and also specify the color of the fiber and connector?D Square Construction LLCPlease Reference E-403 Detail 1,2, & 3 for outlet details.
8Can a drawing detail be provided through the MSF Yard canopy so we know what we are
attaching the sprinkler system to?ONYX Construction Management,LLCPlease reference sheet A-201 for canopy elevations. Canopy is a pre-fabricated structure composed of beams and purlins.
9Please confirm if we are to p aint all exposed steel members of the MSF canopy . Ref key
note #11/A 201ONYX Construction Management,LLCPaint all exposed steel members
10Does Dry Pipe Sprinkler System, Fire Protection spec 21 13 17.00 10 apply to this

project? If so, where is the dry pipe to be installed? General Note #2 on FS100 indicates

that the dry pipe was removed from this project.ONYX Construction Management,LLCDry pipe not required
11Note 4 on sheet G 111 directs the GC to provide temporary toilets. Is the GC to provide a
temporary restroom trailer, or will port a potty type toilets be acceptable?ONYX Construction Management,LLCMeans and methods on meeting contract requirements is subject to the contractor's discretion.
12If a temporary restroom trailer is required, can we connect to existing base utilities
(electric, water, sewer)? If so, where are these utilitiesONYX Construction Management,LLCContractor can connect to base utilities at own expense. Please reference Civil and Electrical sheets for exiting utilities.
13Where on the site are the temporary toilet facilities to be located?ONYX Construction Management,LLCExact location will be field coordinated with the government.
14How many personnel are housed in this facility?ONYX Construction Management,LLCOccupancy varies
15General note 1 on sheet G 111 requires the GC and subs to be escorted while working
inside the facility. Is the GC to include the cost to hire the escorts?ONYX Construction Management,LLCEscorts are government personnel
16Is the GC to provide a temporary office trailer for displaced B131 staff? If so, what are
the requirements and where will this trailer be located on the site?ONYX Construction Management,LLCTemporary office trailer not required for facility personnel
17How many working days should the GC allow in the schedule for the government to move
and relocate gove rnment property in the building for each phase?ONYX Construction Management,LLCPlease allow up to 15 working days.
18Please provide a detail for the temporary wall between PH1 & PH2.ONYX Construction Management,LLCWall detail provided in ICD/ICS 705 Technical specifications
19Since rooms 103 & 109 are to remain occupied during all phases of construction, should

the GC figure after hours work to renovate these rooms? How are these rooms to remain

occupied if we are to replace the carpet, ceiling, and paint the walls in these rooms?ONYX Construction Management,LLCClose coordination with government is required to perform work within these spaces. Work in these spaces will be performed during normal duty hours.
20At the site visit it was noted that much of the exterior metal trim, gutters, downspouts etc.

have been damaged. Is it the intent for th e GC to repair these items or just repaint

them?ONYX Construction Management,LLCRepairs are not required
21It was noted at the site visit that the exterior paint is badly flaking. Can a photo be

provided of exterior conditions so our subcontractors know the extent of prep work

required?ONYX Construction Management,LLCPhotos not available. Please be advised that the exterior facility paint is extremely poor condition. Extensive prep work will be required.
22All doors and frames to b e replaced are within fully grouted CMU block walls. These will

need to saw cut for removal leaving the new frames and doors to be toothed into the

existing CMU walls. Is th is look acceptable?ONYX Construction Management,LLCToothing masonry is acceptable.
23G 111 Legend note requires temporary cooling for phase 2 rooms 110, 111, 112, 113,

and 117 during phase 1. Are these phase 2 rooms going to be allowed to be renovated

during phase 1 then?ONYX Construction Management,LLCRooms are in phase II renovation. Limited work is anticipated in other spaces to isolate and provide continuous building systems.
24Can the existing system be utilized for temporary cooling of phase 2 rooms during phase

1? Or must we provide temporary cooling f rom an outside source and if so can the

temporary cooling penetrate the exterior wall?ONYX Construction Management,LLCMeans and methods on meeting contract requirements is subject to the contractor's discretion. Unscheduled exterior wall penetrations are not acceptable.
25Has the exterior paint chips been tested for lead base paint?ONYX Construction Management,LLCPlease reference LBP and Asbestos survey for test results
26A 111 general note 14 states for the GC to retain structural engineer as needed. Since

this is a construct only project that is already designed and stamped by the structural

engineer, please identify the need for the GC to provide or retain a structural engineer?ONYX Construction Management,LLCProject is not stamped by a structural engineer. Structural engineer service is not anticipated
27Will the demoed raised flooring be returned to the Government or discarded during
demolition ph ase?ONYX Construction Management,LLCMaterial not reused or otherwise designated to remain the property of the Government shall become the property of the Contractor and shall be removed and disposed of off base in accordance with construction documents. Government reserves the right to salvage material not being reused.
28Is there a proprietary DDC controls contractor mandated for DM AFB?ONYX Construction Management,LLCDavis-Monthan has a proprietary Energy Management Control System which includes all subsystems. The existing EMCS on base is the Talon Building Automation System manufactured and licensed by Siemens . The software is Niagara Tridium N4 (latest release). The network manager hardware is a Jace-8000 with LON, Staefa Smart II, Modbus and BACnet capability. All new hardware, software and system controller cards must integrate with Siemens JACE Network Managers and the existing Siemens Supervisor graphics server. New system controllers shall utilize the BACnet protocol. All new system components including, software, work stations, system controllers, JACE Network Managers must all meet Air Force approved industrial security standards and the Authority to Operate (ATO) requirements on the base. All Direct Digital Controls (DDC) components shall be provided in a secured control panel remotely installed from the equipment being controlled. No relays shall be allowed on the equipment. Only control wiring shall be installed on the equipment requiring DDC management.
29Section 13b of the SF1442 states that an offer guarantee is required, but note 7 of the

solicitation states that GC shall submit evidence they have adequate bonding limits to cover a project magnitude of $1M 5M. Please clarify if a bid bond is required, or just

bonding letter with limits, or both?ONYX Construction Management,LLCPlease disregard Note 7. Bid guarantees must be submitted in accordance with Clause 52.228-1. See page 58 of the Invitation for Bid for further information..
30Please clarify if a full time dedicated Superintendent is required for construction?ONYX Construction Management,LLCFulltime, dedicated superintendent is required for construction
31Please clarify if a full time dedicated QC is requi red for construction?ONYX Construction Management,LLCFulltime, dedicated QC is required for construction
32If dedicated QC is required, can the Superintendent and QC duties be performed by the
same individual?ONYX Construction Management,LLCSuperintendent and QC duties can be performed by a single individual if the individual is qualified to perform duties
33RFP reference: Wall Texture
RFI: There are a variety of existing wall textures and, if a uniform wall texture is desired, all of the walls need to be skim coated. What is the expected wall texture for this facility?Marsh DevelopmentUniform wall texture required each type of homogenous walls
34RFP reference: Roof Deck
RFI: What is the existing roof deck constructed of?Marsh DevelopmentFacility has a metal roof deck
35RFP reference: Submittal Register
RFI: The submittal register provided in the specifications isn’t typical of DMAFB. Will a revised AF66 be provided?Marsh DevelopmentRevised AF 66 will not be provided
36RFP reference: Communications Squadron Installation Criteria
RFI: Will the 355th Comm Squadron Installation Criteria For Facilities Construction & Design be provided?Marsh DevelopmentBase cabling standards is an appendix in Base Design Guide
37RFP reference: Phasing
RFI: Can the phasing, shown on Sheet G-111, be swapped? This will allow the fire riser to go in ahead of the rest of the piping.Marsh DevelopmentPerform phasing as indicated with the understanding that limited work is anticipated in other areas for isolation and continuation of building systems.
38RFP reference: Quality Control Staff
RFI: Will there be a requirement for a separate QC staff to be onsite fulltime?Marsh DevelopmentSeparate onsite/fulltime QC staff is not necessary required. Individual(s) preforming the QC Duties is required to be onsite and fulltime.
39RFP reference: Plans/Specifications vs. DMDCG’s
RFI: When there is a conflict between the plans/specifications and the Davis Monthan Design Criteria Guidelines, which one governs?Marsh DevelopmentDavis-Monthan Design Guide governs
40RFP reference: ICD/ICS 705 Technical Requirements
RFI: Can the Government provide the ICD/ICS 705 Technical Requirements?Marsh DevelopmentICD/ICS 705 Technical Requirements is available on-line
41RFP reference: As-Builts
RFI: Are there As-Builts for this building?Marsh DevelopmentBase has limited As-builts
42RFP reference: ION Metering
RFI: ION Metering on the service entrance design drawings is not shown. Will ION Metering need to be installed on the new electrical service?Marsh DevelopmentMeter is shown on the one-line but not properly labeled. Provide meter IAW Davis-Monthan Design Guide
43RFP reference: Monaco FA/MNS
RFI: Will the new Monaco FA/MNS system be required to be installed by a certified Monaco installer?Marsh DevelopmentNew Monaco MAAPX is required.
44RFP reference: Monaco FA/MNS “Announcement-Evacuate” Signs
RFI: Will the “announcement-evacuate” signs at each exit be required to be “PROGRAMMABLE TEXT DISPLAYS” or “LED LIT TEXT SIGNS”?Marsh DevelopmentTEXT signs shall be LED lit.
45RFP reference: Fire Suppression Line (Exterior)
RFI: Details 3 & 4 on Sheet C-500 appear to be for domestic & irrigation water. Can the correct details be provided?Marsh DevelopmentUse attached tapping sleeve and gate valve detail in lieu of Details 3&4 on sheet C-500 detail. Plans will be modified to show the below details.
46RFP reference: Fire Suppression Line (Exterior)
RFII: The 8” line supplying the building seems a bit excessive. Will a 6” line be acceptable, as the sprinkler demand is only 580.5 GPM?Marsh Development8" Fire line based on EOR recommendations. Additional engineering is required to consider a smaller fire line.
47RFP reference: Room 129 Deck
RFI: Room 129 appears to be a room within a room with a solid metal deck. Is this a SKIF area? And, can the engineer provide a detail of how to attach the fire sprinkler piping?Marsh DevelopmentMeans and methods is subject to contractor's discretion. Detail will not be provided.
48RFP reference: Rooms 119 & 130
RFI: Sheet E-102, E-403, Sheet E-102 shows Comm outlets type “C” in rooms 119 & 130. As these are defined on E-403 as being SIPRNet outlets, and will be located outside the SCIP boundary, will a Protected Distribution System (PDS) be required for these outlets?Marsh DevelopmentOutlets shown in Room 119 130 will support NIPR only.
49RFP reference: 4” Conduits
RFI: C2.0, ES100, E-102 – Sheet C2.0 calls for (3) 4” conduits from Bldg 131 to manhole, while ES100 & E-102 call for (d) 4”. Please clarify requirement.Marsh DevelopmentProvide 2 - 4" conduits per electrical sheets
50RFP reference: Fuses
RFI: E-002 – What size fuses will be required for the new fused cut outs on the utility pole?Marsh DevelopmentFuses will be sized to support new installation
51RFP reference: Conductors
RFI: E-002, ESD10, ES100 – E-002 Note 3 calls for new conductors to Bldg 110 transformer, ESD10 Note 6 & ES100 Note 1 call for intercepting & splicing existing conductors for re-connection. Please clarify whether these conductors are to be replaced or re-used, and if to be re-used, please indicate where splicing is to be performed 9i.e.; existing transformer vault, new termination cabinet, etc.).Marsh DevelopmentReuse existing conductors to refeed Bldg. 110. To clarify: Existing 225KVA transformer is a live front 208Y/120 live front. Transformer is currently acting like junction cabinet. XFMR served electrical equipment under the canopy which is no longer in use. Existing 300KVA transformer is alive front. H-2 is tapped to single phase feeding Bldg. 110 - 75 KVA XFMR (13.800 GNDY/7968-240/120).
52RFP reference: Generator
RFI: Can the existing 200 kW generator set be used by the contractor to supply power to the building during the electrical service replacement, to minimize outage times to the user?Marsh DevelopmentExisting 200kw generators is not available
53Was the site visit mandatory for General Contractors in order to bid this project?JM Construction Inc.Site visit not mandatory
54Will the contractors be required to have a Government or military escort when working within Fac 131?JM Construction Inc.Government escort is required when working in Facility 131.
55Per the site visit, the exterior CMU, coping, and corrugated metal panel painting is in worse shape than what the drawings indicate. Please provide pictures of the exterior of the building in order to provide painting personnel a realistic viewpoint of scope.JM Construction Inc.Photos not available. Please be advised that the exterior facility paint is extremely poor condition. Extensive prep work will be required.
56On Drawing GN001, General Note #9, please provide asbestos and lead-based paint Government report. If not provided, are the contractors required to provide these testings’ within the bid?JM Construction Inc.Asbestos LBP report provided in the initial solicitation. See attachment 8.
575) On Drawing G-111, the red-highlighted construction notes, Item 3: Contractor shall provide temporary building systems as necessary. Please clarify which additional systems are necessary, besides intruder detection and comm connectivity, and what are the durations necessary to keep those active.JM Construction Inc.To clarify: All building systems (HVAC, POWER, COMM, Fire, IDS, etc.) shall remain operational for all occupied spaces throughout construction.