RFI answers dated 04222021.xlsx
XLSX spreadsheet 157 KB Posted
- Attached to
- Repair Facility 131 Federal contract opportunity
- Solicitation number
- FA487721B0003
About this file
This document contains questions submitted in response to a request for information (RFI) regarding a federal solicitation to renovate Facility 131 at Davis-Monthan Air Force Base.
The solicitation seeks to reconfigure and renovate restrooms and the janitor's closet, consolidate communications equipment, reconfigure the facility entrance, remove extraneous exterior materials, clean and paint exterior walls, provide a new wet sprinkler system including a fire water service line and fire department connection, replace the fire alarm system with a new Monaco analog/addressable system, install a new mechanical system including ductwork, controls, variable air volume systems, chillers, pumps, computer room air conditioning units, fans and insulation, replace the electrical service and install a new interior electrical system including service entrance equipment, panels, feeders, branch circuits, outlets and grounding. The questions and answers provided clarify details of the scope of work such as wall textures, roof deck materials, communications standards, and coordination of work during phasing.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 3-Revised C-500 sheet.pdf | ||
| Amendment 3-WD-AZ20210032 dated 03052021.pdf | ||
| Solicitation Amendment FA487721B00030003 SF 30.pdf | ||
| Final Sign-In Sheet Site Visit Fac 131.xlsx | XLSX spreadsheet | |
| Amendment 2_ Attachment 2- Air Force Approval Memorandum.pdf | ||
| Amendment 2_ Attachment 1- Sheet M-001.pdf | ||
| Amendment 2- SF 30 Final.pdf | ||
| Solicitation Amendment FA487721B00030001 SF 30.pdf | ||
| Solicitation Amendment - FA487721B00030001.pdf | ||
| Solicitation - FA487721B0003.pdf | ||
| 7 Plans_Bldg 131.pdf | ||
| 8 Asbestos and LBP Survey Report.pdf | ||
| 6 DMAFB Design Guide.pdf | ||
| 3 AF Form 3052.pdf | ||
| 2 WD - AZ20210032 Jan 2021.pdf | ||
| 5 Specifications.pdf | ||
| 9 Contractor Environmental Guide_2019.pdf | ||
| 10 Submittal Register.xlsx | XLSX spreadsheet | |
| 1 Template of Contractor EAL.xls | XLS spreadsheet | |
| 4 Bid Schedule.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFI LOG | ||||
| Solicitation Number | FA487721B0003 | |||
| Title | Facility 131 | |||
| RFI # | Question | Contractor | Response | |
| 1 | Is any “Design” required for this project? If so, will the USAF provide the full design requirements and a deliverable schedule? | D Square Construction LLC | All design requirements are detailed in the construction documents | |
| 2 | Sheets A-111 & A-401 depict a Shower Enclosure, Room 106. Will the Govt. clarify if this shower will require the typical ADA accessories (i.e., grab bars, shower seat, curtain rod, curtain, etc.)? | D Square Construction LLC | ADA shower accessories are shown on sheet A-501, Detail 5 & 6. Please see Specifications 10 28 13 for addition details and requirements for toilet accessories. | |
| 3 | Shall the existing Building 131 Vindicator v5’s, Security Tunnel, Site Commander and SAW II machines be removed and then reinstalled/reconfigured to the new IDS requirement? | Desert Datacom | The existing Building 131 Vindicator v5’s, Security Tunnel, Site Commander and SAW II machines shall be removed and then reinstalled/reconfigured to the new IDS requirement. | |
| 4 | Drawing Sheet ES-100, Keynote #7 states “NEW TELECOMMUNICATIONS DUCTBANK FROM COMM ROOM 109 TO EXISTING TELECOMMUNICATIONS MANHOLE. PROVIDE 2-4" C WITH 4 CELL INNERDUCT - PULL 36 STRAND FIBER, 25 PAIR COPPER. CONFIRM LOCATION OF MANHOLE WITH GOVERNMENT PRIOR TO INSTALLATION.” The manhole is not depicted on the Drawings. Will the Govt. provide the location or appx. distance of the existing manhole? | D Square Construction LLC | The circle with adjacent "COMM" verbiage on Sheet ES-100 is the approximate location of the manhole | |
| 5 | Drawing Sheet ES-100, Keynote #8 states “USE EXISTING CONDUIT PATHWAY TO ROUTE CABLES FROM BUILDING 88 TO COMMUNICATIONS MANHOLE (APPROXIMATELY 600'-0"). 36 STRAND SINGLE MODE FIBER OPTIC CABLE AND 25-PAIR COPPER FROM BUILDING 131 SHALL BE TERMINATED IN BUILDING 88. PROVIDE SPLICES AT BUILDING 88 FOR CONNECTION TO EXISTING BASE COMMUNICATIONS SYSTEM.” The manhole for Building 88 is not depicted on the Drawings. Will the Govt. provide the location or appx. distance of this existing manhole? | D Square Construction LLC | The distance between Bldg. 88 to the Comm manhole (location in response above) is approximately 600'. | |
| 6 | Drawing Sheet E-102, Keynotes #6 & #7, will the Govt. clarify if these outlets are designated as OM4 or Cat 6? | D Square Construction LLC | The outlets in keynote 6 and 7 are junction boxes to accommodate future cable pull. | |
| 7 | Drawing Sheet E-402, Detail 1 – Work Area Outlets, will the Govt. clarify if these 4-port faceplates are per SIPR, NIPR, JWICS, NSA cable and also specify the color of the fiber and connector? | D Square Construction LLC | Please Reference E-403 Detail 1,2, & 3 for outlet details. | |
| 8 | Can a drawing detail be provided through the MSF Yard canopy so we know what we are | |||
| attaching the sprinkler system to? | ONYX Construction Management,LLC | Please reference sheet A-201 for canopy elevations. Canopy is a pre-fabricated structure composed of beams and purlins. | ||
| 9 | Please confirm if we are to p aint all exposed steel members of the MSF canopy . Ref key | |||
| note #11/A 201 | ONYX Construction Management,LLC | Paint all exposed steel members | ||
| 10 | Does Dry Pipe Sprinkler System, Fire Protection spec 21 13 17.00 10 apply to this |
project? If so, where is the dry pipe to be installed? General Note #2 on FS100 indicates
| that the dry pipe was removed from this project. | ONYX Construction Management,LLC | Dry pipe not required | ||
| 11 | Note 4 on sheet G 111 directs the GC to provide temporary toilets. Is the GC to provide a | |||
| temporary restroom trailer, or will port a potty type toilets be acceptable? | ONYX Construction Management,LLC | Means and methods on meeting contract requirements is subject to the contractor's discretion. | ||
| 12 | If a temporary restroom trailer is required, can we connect to existing base utilities | |||
| (electric, water, sewer)? If so, where are these utilities | ONYX Construction Management,LLC | Contractor can connect to base utilities at own expense. Please reference Civil and Electrical sheets for exiting utilities. | ||
| 13 | Where on the site are the temporary toilet facilities to be located? | ONYX Construction Management,LLC | Exact location will be field coordinated with the government. | |
| 14 | How many personnel are housed in this facility? | ONYX Construction Management,LLC | Occupancy varies | |
| 15 | General note 1 on sheet G 111 requires the GC and subs to be escorted while working | |||
| inside the facility. Is the GC to include the cost to hire the escorts? | ONYX Construction Management,LLC | Escorts are government personnel | ||
| 16 | Is the GC to provide a temporary office trailer for displaced B131 staff? If so, what are | |||
| the requirements and where will this trailer be located on the site? | ONYX Construction Management,LLC | Temporary office trailer not required for facility personnel | ||
| 17 | How many working days should the GC allow in the schedule for the government to move | |||
| and relocate gove rnment property in the building for each phase? | ONYX Construction Management,LLC | Please allow up to 15 working days. | ||
| 18 | Please provide a detail for the temporary wall between PH1 & PH2. | ONYX Construction Management,LLC | Wall detail provided in ICD/ICS 705 Technical specifications | |
| 19 | Since rooms 103 & 109 are to remain occupied during all phases of construction, should |
the GC figure after hours work to renovate these rooms? How are these rooms to remain
| occupied if we are to replace the carpet, ceiling, and paint the walls in these rooms? | ONYX Construction Management,LLC | Close coordination with government is required to perform work within these spaces. Work in these spaces will be performed during normal duty hours. |
| 20 | At the site visit it was noted that much of the exterior metal trim, gutters, downspouts etc. |
have been damaged. Is it the intent for th e GC to repair these items or just repaint
| them? | ONYX Construction Management,LLC | Repairs are not required |
| 21 | It was noted at the site visit that the exterior paint is badly flaking. Can a photo be |
provided of exterior conditions so our subcontractors know the extent of prep work
| required? | ONYX Construction Management,LLC | Photos not available. Please be advised that the exterior facility paint is extremely poor condition. Extensive prep work will be required. |
| 22 | All doors and frames to b e replaced are within fully grouted CMU block walls. These will |
need to saw cut for removal leaving the new frames and doors to be toothed into the
| existing CMU walls. Is th is look acceptable? | ONYX Construction Management,LLC | Toothing masonry is acceptable. |
| 23 | G 111 Legend note requires temporary cooling for phase 2 rooms 110, 111, 112, 113, |
and 117 during phase 1. Are these phase 2 rooms going to be allowed to be renovated
| during phase 1 then? | ONYX Construction Management,LLC | Rooms are in phase II renovation. Limited work is anticipated in other spaces to isolate and provide continuous building systems. |
| 24 | Can the existing system be utilized for temporary cooling of phase 2 rooms during phase |
1? Or must we provide temporary cooling f rom an outside source and if so can the
| temporary cooling penetrate the exterior wall? | ONYX Construction Management,LLC | Means and methods on meeting contract requirements is subject to the contractor's discretion. Unscheduled exterior wall penetrations are not acceptable. | ||
| 25 | Has the exterior paint chips been tested for lead base paint? | ONYX Construction Management,LLC | Please reference LBP and Asbestos survey for test results | |
| 26 | A 111 general note 14 states for the GC to retain structural engineer as needed. Since |
this is a construct only project that is already designed and stamped by the structural
| engineer, please identify the need for the GC to provide or retain a structural engineer? | ONYX Construction Management,LLC | Project is not stamped by a structural engineer. Structural engineer service is not anticipated | ||
| 27 | Will the demoed raised flooring be returned to the Government or discarded during | |||
| demolition ph ase? | ONYX Construction Management,LLC | Material not reused or otherwise designated to remain the property of the Government shall become the property of the Contractor and shall be removed and disposed of off base in accordance with construction documents. Government reserves the right to salvage material not being reused. | ||
| 28 | Is there a proprietary DDC controls contractor mandated for DM AFB? | ONYX Construction Management,LLC | Davis-Monthan has a proprietary Energy Management Control System which includes all subsystems. The existing EMCS on base is the Talon Building Automation System manufactured and licensed by Siemens . The software is Niagara Tridium N4 (latest release). The network manager hardware is a Jace-8000 with LON, Staefa Smart II, Modbus and BACnet capability. All new hardware, software and system controller cards must integrate with Siemens JACE Network Managers and the existing Siemens Supervisor graphics server. New system controllers shall utilize the BACnet protocol. All new system components including, software, work stations, system controllers, JACE Network Managers must all meet Air Force approved industrial security standards and the Authority to Operate (ATO) requirements on the base. All Direct Digital Controls (DDC) components shall be provided in a secured control panel remotely installed from the equipment being controlled. No relays shall be allowed on the equipment. Only control wiring shall be installed on the equipment requiring DDC management. | |
| 29 | Section 13b of the SF1442 states that an offer guarantee is required, but note 7 of the |
solicitation states that GC shall submit evidence they have adequate bonding limits to cover a project magnitude of $1M 5M. Please clarify if a bid bond is required, or just
| bonding letter with limits, or both? | ONYX Construction Management,LLC | Please disregard Note 7. Bid guarantees must be submitted in accordance with Clause 52.228-1. See page 58 of the Invitation for Bid for further information.. | ||
| 30 | Please clarify if a full time dedicated Superintendent is required for construction? | ONYX Construction Management,LLC | Fulltime, dedicated superintendent is required for construction | |
| 31 | Please clarify if a full time dedicated QC is requi red for construction? | ONYX Construction Management,LLC | Fulltime, dedicated QC is required for construction | |
| 32 | If dedicated QC is required, can the Superintendent and QC duties be performed by the | |||
| same individual? | ONYX Construction Management,LLC | Superintendent and QC duties can be performed by a single individual if the individual is qualified to perform duties | ||
| 33 | RFP reference: Wall Texture | |||
| RFI: There are a variety of existing wall textures and, if a uniform wall texture is desired, all of the walls need to be skim coated. What is the expected wall texture for this facility? | Marsh Development | Uniform wall texture required each type of homogenous walls | ||
| 34 | RFP reference: Roof Deck | |||
| RFI: What is the existing roof deck constructed of? | Marsh Development | Facility has a metal roof deck | ||
| 35 | RFP reference: Submittal Register | |||
| RFI: The submittal register provided in the specifications isn’t typical of DMAFB. Will a revised AF66 be provided? | Marsh Development | Revised AF 66 will not be provided | ||
| 36 | RFP reference: Communications Squadron Installation Criteria | |||
| RFI: Will the 355th Comm Squadron Installation Criteria For Facilities Construction & Design be provided? | Marsh Development | Base cabling standards is an appendix in Base Design Guide | ||
| 37 | RFP reference: Phasing | |||
| RFI: Can the phasing, shown on Sheet G-111, be swapped? This will allow the fire riser to go in ahead of the rest of the piping. | Marsh Development | Perform phasing as indicated with the understanding that limited work is anticipated in other areas for isolation and continuation of building systems. | ||
| 38 | RFP reference: Quality Control Staff | |||
| RFI: Will there be a requirement for a separate QC staff to be onsite fulltime? | Marsh Development | Separate onsite/fulltime QC staff is not necessary required. Individual(s) preforming the QC Duties is required to be onsite and fulltime. | ||
| 39 | RFP reference: Plans/Specifications vs. DMDCG’s | |||
| RFI: When there is a conflict between the plans/specifications and the Davis Monthan Design Criteria Guidelines, which one governs? | Marsh Development | Davis-Monthan Design Guide governs | ||
| 40 | RFP reference: ICD/ICS 705 Technical Requirements | |||
| RFI: Can the Government provide the ICD/ICS 705 Technical Requirements? | Marsh Development | ICD/ICS 705 Technical Requirements is available on-line | ||
| 41 | RFP reference: As-Builts | |||
| RFI: Are there As-Builts for this building? | Marsh Development | Base has limited As-builts | ||
| 42 | RFP reference: ION Metering | |||
| RFI: ION Metering on the service entrance design drawings is not shown. Will ION Metering need to be installed on the new electrical service? | Marsh Development | Meter is shown on the one-line but not properly labeled. Provide meter IAW Davis-Monthan Design Guide | ||
| 43 | RFP reference: Monaco FA/MNS | |||
| RFI: Will the new Monaco FA/MNS system be required to be installed by a certified Monaco installer? | Marsh Development | New Monaco MAAPX is required. | ||
| 44 | RFP reference: Monaco FA/MNS “Announcement-Evacuate” Signs | |||
| RFI: Will the “announcement-evacuate” signs at each exit be required to be “PROGRAMMABLE TEXT DISPLAYS” or “LED LIT TEXT SIGNS”? | Marsh Development | TEXT signs shall be LED lit. | ||
| 45 | RFP reference: Fire Suppression Line (Exterior) | |||
| RFI: Details 3 & 4 on Sheet C-500 appear to be for domestic & irrigation water. Can the correct details be provided? | Marsh Development | Use attached tapping sleeve and gate valve detail in lieu of Details 3&4 on sheet C-500 detail. Plans will be modified to show the below details. |
| 46 | RFP reference: Fire Suppression Line (Exterior) | |||
| RFII: The 8” line supplying the building seems a bit excessive. Will a 6” line be acceptable, as the sprinkler demand is only 580.5 GPM? | Marsh Development | 8" Fire line based on EOR recommendations. Additional engineering is required to consider a smaller fire line. | ||
| 47 | RFP reference: Room 129 Deck | |||
| RFI: Room 129 appears to be a room within a room with a solid metal deck. Is this a SKIF area? And, can the engineer provide a detail of how to attach the fire sprinkler piping? | Marsh Development | Means and methods is subject to contractor's discretion. Detail will not be provided. | ||
| 48 | RFP reference: Rooms 119 & 130 | |||
| RFI: Sheet E-102, E-403, Sheet E-102 shows Comm outlets type “C” in rooms 119 & 130. As these are defined on E-403 as being SIPRNet outlets, and will be located outside the SCIP boundary, will a Protected Distribution System (PDS) be required for these outlets? | Marsh Development | Outlets shown in Room 119 130 will support NIPR only. | ||
| 49 | RFP reference: 4” Conduits | |||
| RFI: C2.0, ES100, E-102 – Sheet C2.0 calls for (3) 4” conduits from Bldg 131 to manhole, while ES100 & E-102 call for (d) 4”. Please clarify requirement. | Marsh Development | Provide 2 - 4" conduits per electrical sheets | ||
| 50 | RFP reference: Fuses | |||
| RFI: E-002 – What size fuses will be required for the new fused cut outs on the utility pole? | Marsh Development | Fuses will be sized to support new installation | ||
| 51 | RFP reference: Conductors | |||
| RFI: E-002, ESD10, ES100 – E-002 Note 3 calls for new conductors to Bldg 110 transformer, ESD10 Note 6 & ES100 Note 1 call for intercepting & splicing existing conductors for re-connection. Please clarify whether these conductors are to be replaced or re-used, and if to be re-used, please indicate where splicing is to be performed 9i.e.; existing transformer vault, new termination cabinet, etc.). | Marsh Development | Reuse existing conductors to refeed Bldg. 110. To clarify: Existing 225KVA transformer is a live front 208Y/120 live front. Transformer is currently acting like junction cabinet. XFMR served electrical equipment under the canopy which is no longer in use. Existing 300KVA transformer is alive front. H-2 is tapped to single phase feeding Bldg. 110 - 75 KVA XFMR (13.800 GNDY/7968-240/120). | ||
| 52 | RFP reference: Generator | |||
| RFI: Can the existing 200 kW generator set be used by the contractor to supply power to the building during the electrical service replacement, to minimize outage times to the user? | Marsh Development | Existing 200kw generators is not available | ||
| 53 | Was the site visit mandatory for General Contractors in order to bid this project? | JM Construction Inc. | Site visit not mandatory | |
| 54 | Will the contractors be required to have a Government or military escort when working within Fac 131? | JM Construction Inc. | Government escort is required when working in Facility 131. | |
| 55 | Per the site visit, the exterior CMU, coping, and corrugated metal panel painting is in worse shape than what the drawings indicate. Please provide pictures of the exterior of the building in order to provide painting personnel a realistic viewpoint of scope. | JM Construction Inc. | Photos not available. Please be advised that the exterior facility paint is extremely poor condition. Extensive prep work will be required. | |
| 56 | On Drawing GN001, General Note #9, please provide asbestos and lead-based paint Government report. If not provided, are the contractors required to provide these testings’ within the bid? | JM Construction Inc. | Asbestos LBP report provided in the initial solicitation. See attachment 8. | |
| 57 | 5) On Drawing G-111, the red-highlighted construction notes, Item 3: Contractor shall provide temporary building systems as necessary. Please clarify which additional systems are necessary, besides intruder detection and comm connectivity, and what are the durations necessary to keep those active. | JM Construction Inc. | To clarify: All building systems (HVAC, POWER, COMM, Fire, IDS, etc.) shall remain operational for all occupied spaces throughout construction. |
image1.png image2.png