Q A.docx

DOCX document 12 KB Posted

Attached to
Link Circuits Portales Substation Federal contract opportunity
Solicitation number
FA4855-16-B-0026
Issued by
Department of the Air Force Special Operations Command

About this file

Questions and Answers

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Need POC & Phone number for Xcell Energy for Coordination & pricing

Attachment no. 9 was revised on 13 Oct 2016 to remove the need for Xcell Energy Coordination.

2. Sheet 00E-02 Switch X Key Note 1 Is it the intent of the contract to Intercept the existing Conduits Between the Existing Substation Switchgear & Sec Cabinet 1101 and re-route to New Switch X Will the existing Circuit have to be replaced in its entirety, Or is the intent to re-use the existing cable.

The intent is to intercept the existing conductors. The Contractor shall anticipate replacing the conductor from the new switch X to existing switchgear to allow for additional slack required for terminations to the new switch. Splicing will not be allowed.

3. Lead time of Cooper Switches is out 16 weeks the 120 day performance time specified is not enough time to perform this project min of 180 days required.

Contracting will address this issue at the PRE-Con by either adjusting the POP or delaying the Notice to Proceed.

4. Sheet 00E-01 Refers to Note at Antennas refer to sheet 00E-05 there is no sheet 5.

The antenna are part of a separate contract and are not in the Scope for this project. The Antennas shall be considered as existing to remain for bid purposes.

File details come from the government source that posted it. Updated .