Attachment 12 - 27 SOW ETL02-12 and 27 SOCS COMM Standards.pdf

PDF 172 KB Posted

Attached to
Multiple Award Construction Contract
Solicitation number
FA4855-10-R-0006
Issued by

About this file

Attachment 12 - 27 SOW ETL02-12 and 27 SOCS COMM Standards Any attachments currently shown as draft will be finalized and a modification will be issued to incorporate them into the contract at a later date.

View the file

Other files

File Type Posted
MACC Solicitation Questions Part II.pdf PDF
MACC Solicitation Q A.pdf PDF
Attachment 61 - Bldg 206 Resurfacing.pdf PDF
Attachment 56 - Bldg 206 H208 Area.pdf PDF
Attachment 50 - Bldg 206 As Built Warehouse Supply Corrective Work.pdf PDF
Attachment 41 - Bldg 206 Proposed Roof Plan.pdf PDF
Attachment 48 - Bldg 206 As Built Warehouse Supply Equipment.pdf PDF
Attachment 62 - Bldg 206 Roof Plan.pdf PDF
Attachment 55 - Bldg 206 Square Footage.pdf PDF
Attachment 40 - Bldg 206 Existing Roof Plan.pdf PDF
Attachment 47 - Bldg 206 As Built Warehouse Supply Equipment Vault.pdf PDF
MACC Conformed Solicitation per Amendment 2.doc DOC document
Attachment 52 - Bldg 206 Floor Plan.pdf PDF
Attachment 59 - Bldg 206 Roll Up Door.pdf PDF
Attachment 60 - Bldg 206 Fire Inspection Reports.pdf PDF
Attachment 38 - Past Performance Questionaire.doc DOC document
MACC Amendment 2.doc DOC document
Attachment 39 - Bldg 206 Roof Location Plan.pdf PDF
Attachment 63 - ETL 07-4 Air Force Carpet Standard.pdf PDF
Attachment 54 - Bldg 206 ADAL Base Warehouse Addition Mechanical Plumbing Plan.pdf PDF
Attachment 58 - Bldg 206 Lead Based Paint Removal.pdf PDF
Attachment 57 - Bldg 206 Layout Asbestos Removal.pdf PDF
Attachment 22 - Cannon AFB Bldg 206 Lead Base Paint Data.pdf PDF
Attachment 51 - Bldg 206 As Built Regrade Drain Ditch.pdf PDF
Attachment 49 - Bldg 206 As Built ADAL Base Supply Warehouse.pdf PDF
Attachment 44 - Bldg 206 As Built Repair Elect Dist System.pdf PDF
Attachment 42 - Bldg 206 As Built Install Dock Leveler.pdf PDF
Attachment 53 - Bldg 206 BRAC Floor Plan.pdf PDF
Attachment 46 - Bldg 206 As Built Repair Gutter Seals.pdf PDF
Attachment 43 - Bldg 206 As Built Vehicle Area.pdf PDF
Bldg 206 AutoCAD files.zip ZIP file
Attachment 45 - Bldg 206 As Built Lights and Paint.pdf PDF
MACC Pre-Proposal Conference and Site Visit.pdf PDF
Pre-proposal Meeting and Site Visit Attended 20 July 2010.pdf PDF
Agenda for MACC Pre-Proposal Conference and Site Visit.pdf PDF
MACC Solicitation Conformed copy1.doc DOC document
MACC solicitation Amendment.doc DOC document
Pre-Proposal Meeting Site Visit Instructions Revised.pdf PDF
Pre-Proposal Meeting Site Visit Instructions.pdf PDF
Attachment 6 - GeoBase Initial Operating Capability Implementation.pdf PDF
Attachment 15 - Wage Determination-NM9.pdf PDF
Attachment 19 - Cannon AFB Bldg 206 Projected Construction 8 June 2010.pdf PDF
Attachment 38 - Past Performance Questionaire.doc DOC document
Attachment 13 - Wage Determination-NM1.pdf PDF
Attachment 28 - AF Form 3000 Material Approval Submittal.pdf PDF
Attachment 35 - SF 295 Summary Subcontract Report.pdf PDF
Attachment 20 - Cannon AFB Bldg 206 Projected Demolition 24 June 2010.pdf PDF
Attachment 34 - SF 294 Subcontracting Report for Individual Contracts.pdf PDF
Attachment 27 - Schedule of Material Submittals.xls XLS spreadsheet
Attachment 21 - Cannon AFB Bldg 206A As Built 9 March 2009.pdf PDF
Show 40 more

Latest 50 of 78 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 12 FA4855‐10‐R‐0006 15 June 2010

AFSOCI 33-105_CANNONAFBSUP

BY ORDER OF THE COMMANDER CANNON AIR FORCE BASE

AIR FORCE SPECIAL OPERATIONS INSTRUCTION 33-105

CANNON AIR FORCE BASE

Communications

AFSOC COMMUNICATIONS SPECIFICATIONS FOR FACILITY CONTRUCTION AND

ALTERATIONS

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

ACCESSIBILITY: Publications and forms are available for downloading or ordering on the e- Publishing website at www.e-Publishing.af.mil.

RELEASABILITY: There are no releasability restrictions on this publication.

OPR: 27 SOCS/SCX

Certified by: 27 SOCS/DO (Ms. Kuni Archer) Supersedes: AFSOCI33-105, 12 Nov 2009 Pages: 5

This supplement sets forth policies and procedures relating to design and implementation of facility telecommunications infrastructure and cabling systems for all Military Construction (MILCON), facility additions and/or alterations (ADAL) at Cannon AFB, NM. This instruction applies to all AFSOC and tenent units assigned to Cannon AFB, NM. Ensure that all records created as a result of processes prescribed in this publication are maintained in accordance with Air Force Manual (AFMAN) 33-363, Management of Records, and disposed of in accordance with Air Force Records Information Management System (AFRIMS) Records Disposition Schedule (RDS) located at https://www.my.af.mil/gcss-af61a/afrims/afrims/. Refer recommended changes and questions about this publication to the Office of Primary Responsibility (OPR) using the AF Form 847, Recommendation for Change of Publication; route AF Form 847s through local publications/forms managers.

AFSOCI33-105, 12 November 2009, is supplemented as follows:

SUMMARY OF CHANGES

This supplement revises and updates the guidance of Air Force Special Operations Command Instruction (AFSOCI) 33-105, AFSOC Communications Specifications For Facility Construction and Alterations,12 November 2009, as it applies to 27 Special Operations Wing (27 SOW). The AFI is published word-for-word without editorial review. This document reflects Cannon AFB communications installation standards used to meet operational mission requirements and infrastructure updates driven by technology updates.

2.4. (Amended) Communications Rooms.

The communications wiring rooms will include the following provisions as part of the construction effort:

2.4.1. (Amended) General Sizing and Configuration: Communications room shall be separated from other utility rooms (i.e. electrical/mechanical) and centrally located. Ground floor communications room dimensions will be a minimum of twelve foot by twelve foot (12' x 12', http://www.e-publishing.af.mil/ https://www.my.af.mil/gcss-af61a/afrims/afrims/ except in specialized cases). Include additional dedicated communications rooms for every additional floor vertically stacked above the main room, or as required to maintain cable termination distances requirements.

2.4.1.1. (Added) Rooms will be secured with Schlage model KC-5196-2 King Cobra 2 electronic keyless lock with programming, or equivalent as directed by Base CSO.

2.4.2. Electrical Power and Grounding. Installation activity will provide, at minimum:

2.4.2.1. (Amended) Four (4) dedicated duplex wall mounted 110/120 VAC 20-Amp circuits using the NEMA 5-20P outlet, one on each wall of the communications room.

2.4.2.2. (Amended) One (1) dedicated 208 VAC 30-Amp circuit using L6-30 R twist lock outlet mounted on the top of each equipment cabinet.

2.4.2.3. (Amended) One (1) dedicated duplex 110/120 VAC dedicated 30-Amp circuit utilizing L5-30 R twist lock outlet mounted on the top of each equipment cabinet.

2.4.2.3.1. (Added) One (1) dedicated 20-Amp circuit using NEMA 5-20P duplex outlet mounted on the top of each equipment cabinet.

2.6. Telephone Backboard (TBB) Requirements.

2.6.1. (Amended) At a minimum, install one (1) 8’x4’ 3/4-inch thick TBB with two (2) coats of insulating fire-retarding varnish. Mount the backboard in a horizontal position two (2) feet above finished floor (AFF).

2.7. Building Service Entrance Ducts (Conduit). Provide at minimum:

2.7.2. (Added) Install two (2) each 3x3 MAXCELL interducts in two of the conduits.

2.7.3. (Added) New Manholes: Manholes will be H-20 rated manholes with a standard dimension of 6’ X 8’ X 7’ (width, length, height) The manholes shall meet the requirements of TIA/EIA-758, paragraph 5.2.1. Prefabricated manholes are preferred. The manholes shall be furnished with a ladder and ladder hook, cable racks, a sump, and a grounding system.The MH will have 2 ladders cable racks per length and one per width attached to the walls with # 3 grade “8” 3/8 inch bolts. Each ladder rack will have 3 (8”) steps per ladder. It will be equipment with 2 grounds per length side using 8 ft grounding rods. Empty ducts will be filled to 4 inches. It will be level with 12 inches of sand underneath. All holes will be inspected by SCX or a designated rep before the MH is set. A 36 Inch size lid will be provided.

2.7.3.1. (Added) All manholes will be equipped with locking MH covers. Base CSO will provide information on locking lids and locks.

2.8. Additional Communications Closets.

2.8.1. (Amended) Ensure secured access for each communications closet. See para 2.4.1.1 for lock information.

2.8.4. (Amended) Install 2 each 3x3 MAXCELL interducts in two of the conduits.

2.9. Servicing Cable Plant.

2.9.1. (Amended) The installation activity will provide, install, and terminate all required Unshielded Twisted Pair (UTP) and single-mode, 9/125 micron (μm), fiber optic (FO) cable from the nearest usable manhole to the communications room demarcation points and between communications rooms as a provision of the Military Construction (MILCON) or Add/Alteration (ADAL) (typically, the AF Form 1391, Military Construction Document.)

2.9.1.1. (Amended) As a minimum, all mission (operations) facilities will include a minimum 24 gauge (24 AWG) PE-39, fifty (50) pair copper and twelve (12) strands of single-mode Fiber Optic (FO) cable loose tube, gel filled with a central strength pulling member from the nearest servicing location. The Base CSO will determine the route, specific cable type and count during the facility design review phases.

2.9.1.1.2. (Added) Terminate copper cable on TBB on 110 BET protection panels with protectors sufficient for number of pairs terminated.

2.10. Internal Cable Distribution and Vertical Conduits (for Unclassified Use).

2.10.1.2. (Added) Provide “tie” cables from TBB terminated in center of 19 inch lockable enclosure (referenced in para 2.4.1) on 19 inch Cabinet mount 110 blocks. Provide C4 modules in sufficient quantity to patch all pairs terminated.

2.11. Communications Service Outlets (for Unclassified Use Only).

2.11.1. (Amended) Standard outlets. Install one (1) quad-plex communications service outlet 18-inches above finished floor (AFF) in designated work locations. Ensure installation of a telephone/data modular outlet within 1 foot of an electrical 110 VAC outlet or every six (6) feet of linear wall space, whichever is greater. Note: Communications outlets are required in common areas, except for washrooms, bathrooms and hallways).

2.11.2. (Amended) Wall phone outlets. Install one (1) single modular, eight-position/eight pin (RJ-45) service outlet with a push-in/slide-down type back plate (Ref: EIA/TIA 570-1991, Figure 9) 60-inches AFF. Ensure installation of modular outlet within 1 foot of an electrical 110 VAC outlet.

2.11.4. <DELETED>

2.11.5.1 (Added) Use port nomenclature identifying cabinet (numerically), Panel (alphabetically), and port number listed on patch panel (numerically). (ie. 1.A.23 = cabinet 1, panel A, port 23).

2.12. Internal Facility Communications Cable Types (Unclassified Telephone and Data Only).

2.12.1. (Amended) Mission (operational) Facility Telecommunications Cabling. Install plenum-rated, Category 6 (CAT 6) copper cabling, color coded using blue for unclassified LAN and telephone, an overall insulated vinyl jacket for all data (LAN) and telephone service outlet connections. Use EIA/TIA 568B Cable Termination Guidelines for cable terminations at the servicing outlet and demarcation locations. Note: multi-mode fiber optic cable will NOT be used for internal facility unclassified data/voice requirements at any time.

2.13. Telephone Demarcation Requirements, Unclassified Service.

2.13.1.1. (Amended) CAT 6 Installation. Terminate the service delivery point cables to 19 inch rack mount 110 type CAT6 RJ45 patch panels in communications cabinets (as specified in TIA/EIA-568-B.2-1) identified in para 2.5. Terminate all cable conductors in numerical order.

Specifications will comply with T568B wiring patterns. Provide supports/cable management for of 48 ports per panel. Cable management may consist of either 1 unit (1U) below each 48 port patch panel, or 2 unit (2U) between two 48 port patch panels. Provide additional patch panels/supports as node requirements dictate. The modular RJ-45 will comply with all FCC, ISO, UL and CSA requirements.

2.13.1.2. (Amended) CAT 5e Reutilization. Install S66M1-50 or 110 type CAT 5e patch panels with cover. Terminate all cable conductors in numerical order.

2.13.2. <DELETED>

2.13.2.1. <DELETED>

2.14. Data (LAN) Wiring Demarcation Requirements, Unclassified Service.

2.14.2. (Amended) Patch Panels. Install FO/RJ-45 distribution panel within the enclosed rack for the termination of servicing cable plant. For facilities using a single communications cabinet, mount the patch panel a minimum of five (5) rack units (RU) from the top extent of the rack (this space is reserved for the switch). For multi-cabinet distribution, use separate cabinets for cable distribution and network equipment. Interconnect FO distribution panel with premise wiring patch panels. Note: Interconnect the FO distribution panels to secondary communications closet panels (as required) to accommodate a "bus and ring" configuration (for continuity); for additional information, see paragraph 2.9.1.1.

3.3. Classified (SECRET) Communication’s Closet Requirements.

3.3.2.1. (Amended) Additional dedicated electrical service. Install power for classified equipment cabinets IAW para 2.4.2.2., 2.4.2.3. and 2.4.2.3.1. for each additional cabinet.

3.3.2.3.2. (Amended) Power for IPS Safe. Power will be managed into the safe; provide a dedicated 20-Amp circuit using duplex NEMA 5-20P hospital grade outlet inside of the safe.

3.3.2.3.3. (Amended) Provide two CAT 6 copper cable connections terminated in a duplex RJ- 45 duplex outlet inside Hoffman Box attached to the safe. Multi-mode fiber will not be used for unclassified data/voice requirements at any time.

3.7. Internal Facility Communications Cable Types (Classified Only).

3.7.1. (Amended) Internal Facility Classified Cable (all applications). Use appropriate count of 62.5/125 micron multi-mode plenum-rated fiber optic cable using wall mount quad LC female connections at user locations. Rack-mounted FO patch panels will use LC connections. Cable must not contain a metal carrier of any sort (i.e. shielding, copper carrier, etc.). Utilize LC connectors at each end of the SECRET level connection. Splicing of cable is prohibited. This applies to all classified media installations, regardless of facility level certification.

3.7.1.1.2. (Amended) Connection between Classified and Unclassified racks. Provide a minimum of 6-strands FO with a minimum six (6) foot maintenance loop at each equipment rack and all junction boxes. Terminate cable utilizing either LC connectors (as specified by Base CSO).

Organize cable within the rack in a neat and orderly fashion, as specified in paragraph 2.10.

3.7.1.1.3. (Amended) Between CSDP and Junction/outlet box. Provide a minimum of two (2) strands M-M from each SECRET level communications service outlet to the equipment rack.

Terminate cable utilizing LC connectors (as specified by Base CSO). SECRET level communications service outlets within a surface mounted junction/outlet box require an additional 18-inch maintenance loop behind the face plate.

3.7.2. (Amended) Communications service Patch Panels (SECRET level all). Use LC connector type patch panels (at the discretion of the Base CSO). For facilities using a single communications cabinet, mount the patch panel a minimum of five (5) rack units (RU) from the top extent of the rack (this space is reserved for the switch). For multi-cabinet distribution, use separate cabinets for cable distribution and network equipment. Ensure each communications port on the patch panel is systematically numbered and labeled to correspond with the applicable communications service outlet.

3.7.2.2. (Added) Use port nomenclature identifying cabinet (numerically), Panel (alphabetically), and port number listed on patch panel (numerically). (ie. 1.A.23 = cabinet 1, panel A, port 23).

3.11. Adopted and Prescribed Forms.

3.11.1. Prescribed Forms. None.

3.11.2. Adopted Forms.

AF Form 847, Recommendation for Change of Publication

AF Form 1391, Military Construction Document

AFSOCI 33-105_CANNONAFBSUP
BY ORDER OF THE COMMANDER CANNON AIR FORCE BASE
AIR FORCE SPECIAL OPERATIONS INSTRUCTION 33-105
CANNON AIR FORCE BASE
Communications
AFSOC COMMUNICATIONS SPECIFICATIONS FOR FACILITY CONTRUCTION AND ALTERATIONS
COMPLIANCE WITH THIS PUBLICATION IS MANDATORY
ACCESSIBILITY: Publications and forms are available for downloading or ordering on the e-Publishing website at www.e-Publishing.af.mil.
RELEASABILITY: There are no releasability restrictions on this publication.
OPR: 27 SOCS/SCX
Certified by: 27 SOCS/DO (Ms. Kuni Archer)
Supersedes: AFSOCI33-105, 12 Nov 2009
Pages: 5
This supplement sets forth policies and procedures relating to design and implementation of facility telecommunications infrastructure and cabling systems for all Military Construction (MILCON), facility additions and/or alterations (ADAL) at Cannon AFB, NM. This instruction applies to all AFSOC and tenent units assigned to Cannon AFB, NM. Ensure that all records created as a result of processes prescribed in this publication are maintained in accordance with Air Force Manual (AFMAN) 33-363, Management of Records, and disposed of in accordance with Air Force Records Information Management System (AFRIMS) Records Disposition Schedule (RDS) located at https://www.my.af.mil/gcss-af61a/afrims/afrims/. Refer recommended changes and questions about this publication to the Office of Primary Responsibility (OPR) using the AF Form 847, Recommendation for Change of Publication; route AF Form 847s through local publications/forms managers.
AFSOCI33-105, 12 November 2009, is supplemented as follows:
SUMMARY OF CHANGES
This supplement revises and updates the guidance of Air Force Special Operations Command Instruction (AFSOCI) 33-105, AFSOC Communications Specifications For Facility Construction and Alterations,12 November 2009, as it applies to 27 Special Operations Wing (27 SOW). The AFI is published word-for-word without editorial review. This document reflects Cannon AFB communications installation standards used to meet operational mission requirements and infrastructure updates driven by technology updates.
2.4. (Amended) Communications Rooms.
The communications wiring rooms will include the following provisions as part of the construction effort:
2.4.1. (Amended) General Sizing and Configuration: Communications room shall be separated from other utility rooms (i.e. electrical/mechanical) and centrally located. Ground floor communications room dimensions will be a minimum of twelve foot by twelve foot (12' x 12', except in specialized cases). Include additional dedicated communications rooms for every additional floor vertically stacked above the main room, or as required to maintain cable termination distances requirements.
2.4.1.1. (Added) Rooms will be secured with Schlage model KC-5196-2 King Cobra 2 electronic keyless lock with programming, or equivalent as directed by Base CSO.
2.4.2. Electrical Power and Grounding. Installation activity will provide, at minimum:
2.4.2.1. (Amended) Four (4) dedicated duplex wall mounted 110/120 VAC 20-Amp circuits using the NEMA 5-20P outlet, one on each wall of the communications room.
2.4.2.2. (Amended) One (1) dedicated 208 VAC 30-Amp circuit using L6-30 R twist lock outlet mounted on the top of each equipment cabinet.
2.4.2.3. (Amended) One (1) dedicated duplex 110/120 VAC dedicated 30-Amp circuit utilizing L5-30 R twist lock outlet mounted on the top of each equipment cabinet.
2.4.2.3.1. (Added) One (1) dedicated 20-Amp circuit using NEMA 5-20P duplex outlet mounted on the top of each equipment cabinet.
2.6. Telephone Backboard (TBB) Requirements.
2.6.1. (Amended) At a minimum, install one (1) 8’x4’ 3/4-inch thick TBB with two (2) coats of insulating fire-retarding varnish. Mount the backboard in a horizontal position two (2) feet above finished floor (AFF).
2.7. Building Service Entrance Ducts (Conduit). Provide at minimum:
2.7.2. (Added) Install two (2) each 3x3 MAXCELL interducts in two of the conduits.
2.7.3. (Added) New Manholes: Manholes will be H-20 rated manholes with a standard dimension of 6’ X 8’ X 7’ (width, length, height) The manholes shall meet the requirements of TIA/EIA-758, paragraph 5.2.1. Prefabricated manholes are preferred. The manholes shall be furnished with a ladder and ladder hook, cable racks, a sump, and a grounding system.The MH will have 2 ladders cable racks per length and one per width attached to the walls with # 3 grade “8” 3/8 inch bolts. Each ladder rack will have 3 (8”) steps per ladder. It will be equipment with 2 grounds per length side using 8 ft grounding rods. Empty ducts will be filled to 4 inches. It will be level with 12 inches of sand underneath. All holes will be inspected by SCX or a designated rep before the MH is set. A 36 Inch size lid will be provided.
2.7.3.1. (Added) All manholes will be equipped with locking MH covers. Base CSO will provide information on locking lids and locks.
2.8. Additional Communications Closets.
2.8.1. (Amended) Ensure secured access for each communications closet. See para 2.4.1.1 for lock information.
2.8.4. (Amended) Install 2 each 3x3 MAXCELL interducts in two of the conduits.
2.9. Servicing Cable Plant.
2.9.1. (Amended) The installation activity will provide, install, and terminate all required Unshielded Twisted Pair (UTP) and single-mode, 9/125 micron (μm), fiber optic (FO) cable from the nearest usable manhole to the communications room demarcation points and between communications rooms as a provision of the Military Construction (MILCON) or Add/Alteration (ADAL) (typically, the AF Form 1391, Military Construction Document.)
2.9.1.1. (Amended) As a minimum, all mission (operations) facilities will include a minimum 24 gauge (24 AWG) PE-39, fifty (50) pair copper and twelve (12) strands of single-mode Fiber Optic (FO) cable loose tube, gel filled with a central strength pulling member from the nearest servicing location. The Base CSO will determine the route, specific cable type and count during the facility design review phases.
2.9.1.1.2. (Added) Terminate copper cable on TBB on 110 BET protection panels with protectors sufficient for number of pairs terminated.
2.10. Internal Cable Distribution and Vertical Conduits (for Unclassified Use).
2.10.1.2. (Added) Provide “tie” cables from TBB terminated in center of 19 inch lockable enclosure (referenced in para 2.4.1) on 19 inch Cabinet mount 110 blocks. Provide C4 modules in sufficient quantity to patch all pairs terminated.
2.11. Communications Service Outlets (for Unclassified Use Only).
2.11.1. (Amended) Standard outlets. Install one (1) quad-plex communications service outlet 18-inches above finished floor (AFF) in designated work locations. Ensure installation of a telephone/data modular outlet within 1 foot of an electrical 110 VAC outlet or every six (6) feet of linear wall space, whichever is greater. Note: Communications outlets are required in common areas, except for washrooms, bathrooms and hallways).
2.11.2. (Amended) Wall phone outlets. Install one (1) single modular, eight-position/eight pin (RJ-45) service outlet with a push-in/slide-down type back plate (Ref: EIA/TIA 570-1991, Figure 9) 60-inches AFF. Ensure installation of modular outlet within 1 foot of an electrical 110 VAC outlet.
2.11.4. <DELETED>
2.11.5.1 (Added) Use port nomenclature identifying cabinet (numerically), Panel (alphabetically), and port number listed on patch panel (numerically). (ie. 1.A.23 = cabinet 1, panel A, port 23).
2.12. Internal Facility Communications Cable Types (Unclassified Telephone and Data Only).
2.12.1. (Amended) Mission (operational) Facility Telecommunications Cabling. Install plenum-rated, Category 6 (CAT 6) copper cabling, color coded using blue for unclassified LAN and telephone, an overall insulated vinyl jacket for all data (LAN) and telephone service outlet connections. Use EIA/TIA 568B Cable Termination Guidelines for cable terminations at the servicing outlet and demarcation locations. Note: multi-mode fiber optic cable will NOT be used for internal facility unclassified data/voice requirements at any time.
2.13. Telephone Demarcation Requirements, Unclassified Service.
2.13.1.1. (Amended) CAT 6 Installation. Terminate the service delivery point cables to 19 inch rack mount 110 type CAT6 RJ45 patch panels in communications cabinets (as specified in TIA/EIA-568-B.2-1) identified in para 2.5. Terminate all cable conductors in numerical order. Specifications will comply with T568B wiring patterns. Provide supports/cable management for of 48 ports per panel. Cable management may consist of either 1 unit (1U) below each 48 port patch panel, or 2 unit (2U) between two 48 port patch panels. Provide additional patch panels/supports as node requirements dictate. The modular RJ-45 will comply with all FCC, ISO, UL and CSA requirements.
2.13.1.2. (Amended) CAT 5e Reutilization. Install S66M1-50 or 110 type CAT 5e patch panels with cover. Terminate all cable conductors in numerical order.
2.13.2. <DELETED>
2.13.2.1. <DELETED>
2.14. Data (LAN) Wiring Demarcation Requirements, Unclassified Service.
2.14.2. (Amended) Patch Panels. Install FO/RJ-45 distribution panel within the enclosed rack for the termination of servicing cable plant. For facilities using a single communications cabinet, mount the patch panel a minimum of five (5) rack units (RU) from the top extent of the rack (this space is reserved for the switch). For multi-cabinet distribution, use separate cabinets for cable distribution and network equipment. Interconnect FO distribution panel with premise wiring patch panels. Note: Interconnect the FO distribution panels to secondary communications closet panels (as required) to accommodate a "bus and ring" configuration (for continuity); for additional information, see paragraph 2.9.1.1.
3.3. Classified (SECRET) Communication’s Closet Requirements.
3.3.2.1. (Amended) Additional dedicated electrical service. Install power for classified equipment cabinets IAW para 2.4.2.2., 2.4.2.3. and 2.4.2.3.1. for each additional cabinet.
3.3.2.3.2. (Amended) Power for IPS Safe. Power will be managed into the safe; provide a dedicated 20-Amp circuit using duplex NEMA 5-20P hospital grade outlet inside of the safe.
3.3.2.3.3. (Amended) Provide two CAT 6 copper cable connections terminated in a duplex RJ-45 duplex outlet inside Hoffman Box attached to the safe. Multi-mode fiber will not be used for unclassified data/voice requirements at any time.
3.7. Internal Facility Communications Cable Types (Classified Only).
3.7.1. (Amended) Internal Facility Classified Cable (all applications). Use appropriate count of 62.5/125 micron multi-mode plenum-rated fiber optic cable using wall mount quad LC female connections at user locations. Rack-mounted FO patch panels will use LC connections. Cable must not contain a metal carrier of any sort (i.e. shielding, copper carrier, etc.). Utilize LC connectors at each end of the SECRET level connection. Splicing of cable is prohibited. This applies to all classified media installations, regardless of facility level certification.
3.7.1.1.2. (Amended) Connection between Classified and Unclassified racks. Provide a minimum of 6-strands FO with a minimum six (6) foot maintenance loop at each equipment rack and all junction boxes. Terminate cable utilizing either LC connectors (as specified by Base CSO). Organize cable within the rack in a neat and orderly fashion, as specified in paragraph 2.10.
3.7.1.1.3. (Amended) Between CSDP and Junction/outlet box. Provide a minimum of two (2) strands M-M from each SECRET level communications service outlet to the equipment rack. Terminate cable utilizing LC connectors (as specified by Base CSO). SECRET level communications service outlets within a surface mounted junction/outlet box require an additional 18-inch maintenance loop behind the face plate.
3.7.2. (Amended) Communications service Patch Panels (SECRET level all). Use LC connector type patch panels (at the discretion of the Base CSO). For facilities using a single communications cabinet, mount the patch panel a minimum of five (5) rack units (RU) from the top extent of the rack (this space is reserved for the switch). For multi-cabinet distribution, use separate cabinets for cable distribution and network equipment. Ensure each communications port on the patch panel is systematically numbered and labeled to correspond with the applicable communications service outlet.
3.7.2.2. (Added) Use port nomenclature identifying cabinet (numerically), Panel (alphabetically), and port number listed on patch panel (numerically). (ie. 1.A.23 = cabinet 1, panel A, port 23).
3.11. Adopted and Prescribed Forms.
3.11.1. Prescribed Forms. None.
3.11.2. Adopted Forms.
AF Form 847, Recommendation for Change of Publication
AF Form 1391, Military Construction Document
Word Bookmarks
OLE_LINK1
OLE_LINK2

File details come from the government source that posted it. Updated .