QandA.pdf
PDF 71 KB Posted
- Solicitation number
- FA483025R0007
About this file
This document is a Questions and Answers (Q&A) file for Solicitation Number FA483025R0007, a 100% Small Business Set-Aside contract for picnic shelter and storage building repairs at Moody Air Force Base and Grassy Pond. Key details include a 90-day period of performance, work hours of Monday-Friday 0800-1700, and a requirement for a licensed electrician to handle electrical components. The project involves demolishing and replacing multiple shelters and storage buildings damaged during Hurricane Helene, including 10'x15' aluminum screened picnic shelters, 20'x12'x8' metal storage sheds, and 12'x30' wooden storage sheds.
Critical administrative requirements include no material substitutions allowed, color selections to be made immediately post-award, and a final walkthrough with punch list before warranty begins. The government anticipates awarding the contract within two weeks of solicitation end, with evaluation factors weighted equally based on technical acceptability. Contractors must provide their own equipment, dumpster, and portable restroom, and will be responsible for site preparation, demolition, and installation following specific material and construction specifications. A site visit was conducted on June 6th, with questions due by June 10th, and a standard 1-year warranty is required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pictures.pdf | ||
| Combo Synopsis Shelters.pdf | ||
| Base Pass Template.pdf | ||
| SOW - Picnic Shelters and Storage Structures.pdf | ||
| Combo Synopsis Shelters.pdf | ||
| base map.pdf | ||
| SOW - Paintball Main Building 12x20.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A
Scope of Work Clarifications
Q. Site Visit Photos or Drawings: Will the government provide site photos, structural drawings, or past blueprints of the shelters and buildings to better understand existing conditions?
A. See the attached pictures. No structural drawings or blueprints exist on the buildings.
Q. Extent of Demolition: Are foundations to be removed with each demolished structure, or will they remain in place for reuse?
A. There are no poured concrete foundations that need to be demoed and removed. All the buildings that are currently in place are set on concrete blocks. The damaged blocks will need to be replaced when the new structures are put in place.
Q. New Structure Anchoring: What anchoring system is required for new shelters and storage sheds (e.g., concrete piers, tie-downs)?
A. No anchoring systems required for new shelters and sheds.
Q. Grading Requirements: Will the government provide the required elevation/grade specs for site leveling, or is it up to the contractor?
A. Up to the contractor.
Q. Sub-Floor Specs: Is there a preferred brand, thickness, or fire rating for the plywood subflooring to be used in the buildings?
A. No preferred brand. Per the SOW, ¾” thickness
Utilities / Electrical Work
Q. Licensed Electrician Requirement: Is a licensed electrician required for disconnection and reconnection of electrical components (e.g., fans, outlets)?
A. Yes
Q. Electrical Scope Clarification: For shelters that include outdoor fans/lights, are the electrical lines already stubbed and available, or does the contractor need to provide wiring and connections?
A. Electrical is already stubbed and available in the picnic shelters that are being repaired and replaced.
Q. Inspections: Will the base electrical or building inspector conduct inspections at any phase (rough-in, final)?
Material Substitutions & Approvals
Q. Equivalent Products: Will the CO accept "equivalent" materials for Hardi siding, VCT tile, or fiberglass screening, and what is the process for material approval?
A. No
Q. Color Selections Timeline: When will final decisions be made on VCT tile and any other customer-selected finishes to avoid delay?
A. Immediately following award, color choices can be presented to the customer by the contractor and decisions will be made quickly to ensure that long lead items have enough time to come in.
Timeline & Work Access
Q. Period of Performance: What is the expected or allowable timeline for project completion after contract award?
A. 90 days
Q. Work Hours & Base Access: Are there restricted work hours on Moody AFB or Grassy Pond? What is the base access protocol for contractor crews?
A. Monday – Friday 0800-1700 are the normal work hours. Any weekend work or after-hours requests will need to be submitted in writing to Contracting and the customer 48 hours before work is to commence. Contracting will provide the proper EAL documentation to the contractor so that their work crews can gain proper access to Moody following a thorough background check.
Q. Phased Work: Can work on multiple buildings be performed simultaneously, or must it follow a particular order?
A. Work on multiple buildings can be performed simultaneously.
Waste Disposal & Logistics
Q. Waste Disposal Location: Can the contractor use the base landfill or must all waste be hauled o -site?
A. Waste must be hauled o -site unless the contractor can gain approval in writing from CES to utilize their on-base Recycling Center to dispose of things like metal, aluminum, etc.
Q. Restroom Access: While the contractor must provide a portable toilet, is water access available on site?
A. No
Q. Staging Area Details: What are the exact dimensions and location of the staging area being provided?
A. A designated staging area will be provided at each project location. The specific dimensions of this area will be determined post-award, contingent upon the Contractor's operational requirements and the available space at each site. The Contractor is responsible for maintaining a clean and safely cordoned-o staging area at the conclusion of each workday.
Warranty / Acceptance
Q. Warranty Inspections: Will there be a final walkthrough and punch list before acceptance and start of the warranty period?
Q. Warranty Start Date: Does the 1-year warranty begin on substantial or final completion?
A. Final completion
Administrative / Submission
Q. Award Timeline: What is the anticipated award date following bid submission?
A. Anticipating award within two weeks of solicitation ending
Q. Evaluation Weighting: Is price the primary determinant under LPTA, or will technical approaches have an equal role in evaluation?
A. Evaluation factors listed in description. Weighted the same, based on acceptability or non-acceptability