Attachment 3 - 10 Jan 24 Paint Estimate FY24 through FY29.xlsx

XLSX spreadsheet 52 KB Posted

Attached to
Painting and Protective Coating IDIQ Federal contract opportunity
Solicitation number
FA480324B0003
Issued by
Department of the Air Force Air Combat Command

About this file

This document provides details regarding a forthcoming solicitation for painting and protective coating services from the Department of the Air Force Air Combat Command. The 20th Contracting Squadron intends to issue solicitation number FA480324B0003 for an Indefinite-Quantity Indefinite-Delivery contract to provide painting and protective coating from fiscal year 2024 through fiscal year 2029. The pre-solicitation notice indicates the resulting award will be a firm-fixed price construction contract. The attached estimate spreadsheet provides anticipated painting needs and budgets for the duration of the potential IDIQ. Interested parties should monitor the Federal Business Opportunities website for release of the full solicitation.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Year

Project:Protective CoatingsProject Engineer:Mr. Patrick Holland
Location:Shaw AFBDepartment:20 CES
Contractor:Date:
Address:
PR No.:

Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total

Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor HoursAvg. Rate ($/hr)Total
1Exterior PaintingSF54,075
2Partial Exterior and TrimSF20,980
3Paint InteriorSF47,929
4Partial Interior and TrimSF7,245
5Remove Pavement MarkingsSF100
6Apply Pavement MarkingsLF23,945
7Prime Interior / ExteriorSF17,746
8Repair Drywall SurfacesSF1,723
9Remove Wall Coverings / WallpaperSF781
10Paint HydrantsEA2
11Prepare / Paint Special StructuresSF3,122
12Prepare / Paint Swimming PoolSF3,080
13Pressure WashingSF75,055
14Fabrication of Sign BlanksSF253
15Fabricate / Apply Letters & NumbersEA2,539
16Glass Door StencilingSF41

Total: $0.00

Option Year 1

Project:Protective CoatingsProject Engineer:Mr. Patrick Holland
Location:Shaw AFBDepartment:20 CES
Contractor:Date:
Address:
PR No.:

Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total

Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor HoursAvg. Rate ($/hr)Total
1Exterior PaintingSF54,075
2Partial Exterior and TrimSF20,980
3Paint InteriorSF47,929
4Partial Interior and TrimSF7,245
5Remove Pavement MarkingsSf100
6Apply Pavement MarkingsLF23,945
7Prime Interior / ExteriorSF17,746
8Repair Drywall SurfacesSF1,723
9Remove Wall Coverings / WallpaperSF781
10Paint HydrantsEA3
11Prepare / Paint Special StructuresSF3,122
12Prepare / Paint Swimming PoolSF3,080
13Pressure WashingSF75,055
14Fabrication of Sign BlanksSF253
15Fabricate / Apply Letters & NumbersEA2,539
16Glass Door StencilingSF41

Total: $0.00

Option Year 2

Project:Protective CoatingsProject Engineer:Mr. Patrick Holland
Location:Shaw AFBDepartment:20 CES
Contractor:Date:
Address:
PR No.:

Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total

Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor HoursAvg. Rate ($/hr)Total
1Exterior PaintingSF54,075
2Partial Exterior and TrimSF20,980
3Paint InteriorSF47,929
4Partial Interior and TrimSF7,245
5Remove Pavement MarkingsSF100
6Apply Pavement MarkingsLF23,945
7Prime Interior / ExteriorSF17,746
8Repair Drywall SurfacesSF1,723
9Remove Wall Coverings / WallpaperSF781
10Paint HydrantsEA3
11Prepare / Paint Special StructuresSF3,122
12Prepare / Paint Swimming PoolSF3,080
13Pressure WashingSF75,055
14Fabrication of Sign BlanksSF253
15Fabricate / Apply Letters & NumbersEA2,539
16Glass Door StencilingSF41

Total: $0.00

Option Year 3

Project:Protective CoatingsProject Engineer:Mr. Patrick Holland
Location:Shaw AFBDepartment:20 CES
Contractor:Date:
Address:
PR No.:

Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total

Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor HoursAvg. Rate ($/hr)Total
1Exterior PaintingSF54,075
2Partial Exterior and TrimSF20,980
3Paint InteriorSF47,929
4Partial Interior and TrimSF7,245
5Remove Pavement MarkingsSF100
6Apply Pavement MarkingsLF23,945
7Prime Interior / ExteriorSF17,746
8Repair Drywall SurfacesSF1,723
9Remove Wall Coverings / WallpaperSF781
10Paint HydrantsEA3
11Prepare / Paint Special StructuresSF3,122
12Prepare / Paint Swimming PoolSF3,080
13Pressure WashingSF75,055
14Fabrication of Sign BlanksSF253
15Fabricate / Apply Letters & NumbersEA2,539
16Glass Door StencilingSF41

Total: $0.00

Option Year 4

Project:Protective CoatingsProject Engineer:Mr. Patrick Holland
Location:Shaw AFBDepartment:20 CES
Contractor:Date:
Address:
PR No.:

Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total

Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor HoursAvg. Rate ($/hr)Total
1Exterior PaintingSF54,075
2Partial Exterior and TrimSF20,983
3Paint InteriorSF47,932
4Partial Interior and TrimSF7,249
5Remove Pavement MarkingsSF100
6Apply Pavement MarkingsLF23,945
7Prime Interior / ExteriorSF17,749
8Repair Drywall SurfacesSF1,727
9Remove Wall Coverings / WallpaperSF785
10Paint HydrantsEA3
11Prepare / Paint Special StructuresSF3,124
12Prepare / Paint Swimming PoolSF3,080
13Pressure WashingSF75,058
14Fabrication of Sign BlanksSF254
15Fabricate / Apply Letters & NumbersEA2,539
16Glass Door StencilingSF43

Total: $0.00

6 Month Extension

Project:Protective CoatingsProject Engineer:Mr. Patrick Holland
Location:Shaw AFBDepartment:20 CES
Contractor:Date:
Address:
PR No.:

Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total

Unit Cost (Means)TotalLabor Hours per Unit (Means)Labor Cost per Unit (Means)Labor HoursAvg. Rate ($/hr)Total
1Exterior PaintingSF27,038
2Partial Exterior and TrimSF10,490
3Paint InteriorSF23,965
4Partial Interior and TrimSF3,623
5Remove Pavement MarkingsSF50
6Apply Pavement MarkingsLF11,973
7Prime Interior / ExteriorSF8,873
8Repair Drywall SurfacesSF862
9Remove Wall Coverings / WallpaperSF391
10Paint HydrantsEA2
11Prepare / Paint Special StructuresSF1,562
12Prepare / Paint Swimming PoolSF1,540
13Pressure WashingSF37,528
14Fabrication of Sign BlanksSF127
15Fabricate / Apply Letters & NumbersEA1,270
16Glass Door StencilingSF21

Total: $0.00

Totals

Protective Coatings
Base Year Line Total$ - 0
Option Year Line Total$ - 0
Option Year 2 Line Total$ - 0
Option Year 3 Line Total$ - 0
Option Year 4 Line Total$ - 0
6 Month Extension Line Total$ - 0
Total Contract Cost$ - 0
Company Name
POC Name
POC Telephone Number
POC Signature