Questions and Answers.docx
DOCX document 13 KB Posted
- Attached to
- Access Floor Tiles Federal contract opportunity
- Solicitation number
- FA480320QB106
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001.pdf | ||
| Salient Charateristics.pdf | ||
| SOW- Raised Floor Tiles-edit 17Aug20.pdf | ||
| Solicitation Raised Floor Tiles.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers FA480320QB106 - Raised Floor Tile 8 September 2020
· Question One: Is the contractor required to cut the internal holes for the electric box in the new raised floor panels, place the new box into the hole that has been cut, and wire the electrical box to an underfloor electrical distribution system?
Government Response:
Contractor is required to cut the holes and install the boxes, the connections will be performed by other comm and electrical personnel.
· Question Two: Is the frame that the floor tiles will be installed into on a regular bolted stringer support or heavy-duty bolted stringer support?
Heavy-duty Bolted Stringer Support System
· Question Three: What are the unloading logistics for the building to include any stairs or steps?
Backdoor area nearest to the locations of the offices where the work is required; four steps to go from ground to the doorway.