Exhibit B - Geo-Tech Report for Nearby Site.pdf

PDF 4 MB Posted

Attached to
Langley AFB Accessible Playground
Solicitation number
FA480025QA081
Issued by

About this file

This document is a Geotechnical Engineering Report prepared by the US Army Corps of Engineers Norfolk District for the Air Force Targeting Center Facility project at Langley Air Force Base in Hampton, Virginia. The report details the results of a limited subsurface exploration conducted in August 2015, which involved drilling five Standard Penetration Test (SPT) borings to depths ranging from 35 to 94.3 feet to investigate soil and geological conditions.

Key findings include the presence of man-placed fill material, very loose to loose sandy soils, and a shallow groundwater table. The report recommends using a deep pile foundation system, specifically square precast pre-stressed concrete (SPPC) piles, due to variable soil conditions. The proposed two-story facility will be approximately 94,800 square feet and include 1,750 workstations, communications equipment, mechanical spaces, and support areas. The report also notes the planned demolition of four existing buildings (326, 333, 337, and 339) and includes environmental site assessment information highlighting the potential presence of asbestos-containing materials and other hazardous substances.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AIR FORCE TARGETING CENTER FACILITY

LANGLEY AIR FORCE BASE

HAMPTON, VIRGINIA

Revised Limited Subsurface Exploration and Preliminary

Geotechnical Engineering Report

January 2016

PREPARED BY:

Geo Environmental Section, Norfolk District U.S. Army Corps of Engineers Fort Norfolk, 803 Front Street Norfolk, VA 23510

INTRODUCTION

This report has been prepared by Norfolk District U.S. Army Corps of Engineers (NAO) to provide a general characterization of the subsurface conditions at the project site and provides a general overview of the soil and geologic conditions with detailed descriptions at discrete soil boring locations.

SUMMARY

The Norfolk District, U.S. Army Corps of Engineers was requested by Langley Air Force Base (LAFB) to prepare a preliminary geotechnical report. It is our understanding that information from the report will be used at a Planning Charrette scheduled for the end of October 2015. As part of Norfolk District’s Services to LAFB, the Geo-Environmental Section performed a limited subsurface exploration and prepared a preliminary geotechnical engineering report within the boundaries of the proposed project site as specified by LAFB personnel. The report provides a general characterization of the subsurface conditions at the project site, provides an overview of the soil conditions, and provides general guidance with respect to geotechnical engineering considerations. A limited environmental site assessment was performed as a part of this study.

The Contractor will be required to perform a geotechnical investigation to design and construct the appropriate foundation as part of their contract. This report is for information only and presents our understanding of the project, reviews the exploration procedures, and presents our observations, and provides general guidance with respect to geotechnical engineering considerations.

Due to man placed fill of variable consistency which overlies very loose to loose soils, and shallow water table conditions, it is our opinion that the proposed facility should be supported by means of a deep pile foundation system. Square precast pre-stressed concrete piles (SPPC) will be the most economical of the driven pile options and are one of the most widely utilized deep foundation systems in the Tidewater Area.

TABLE OF CONTENTS

1. PURPOSE

2. PROJECT INFORMATION

2.1 Scope of Work

2.2 Proposed Facility

2.3 Site Description

3. LIMITED SUBSURFACE EXPLORATION

3.1 General

3.2 Location

3.3 Soil Testing and Sampling

3.4 Laboratory Testing

4. SUBSURFACE CONDITIONS

4.1 Regional Geology

4.2 Subsurface Stratigraphy

4.3 Groundwater Conditions

5. PRELIMINARY GEOTECHNICAL ENGINEERING CONSIDERATIONS

5.1 Foundation Design

5.2 Ground Floor Slab-on-Grade

5.3 Seismic Site Classification for Design

5.4 Pavement Design Recommendations

5.5 Groundwater and Site Drainage

6. PRELIMINARY EARTHWORK CONSIDERATIONS

6.1 Site Preparation

6.2 Foundation Construction

6.3 Controlled Structural Fill

6.4 Suitability of On-site Material

6.5 Compaction Requirements

7. LIMITED ENVIRONMENTAL SITE ASSESSMENT CONCLUSIONS

AND RECOMMENDATIONS

7.1 Assessment

7.2 Conclusions

7.3 Recommendations

REFERENCES

Appendix A: Location and Geologic Maps Appendix B: Boring Location Plan, Boring Logs, and Profiles Appendix C: Laboratory Test Results Appendix D: Site Pictures

1. PURPOSE

This report has been prepared to provide a general characterization of the subsurface conditions at the project site and to provide a general overview of the soil and geologic conditions with detailed descriptions at discrete boring locations. It is furnished for information purposes.

The purpose of the report is to summarize the results of the subsurface exploration and laboratory testing undertaken by the Norfolk District, U.S. Army Corps of Engineers for a proposed Air Force Targeting Center Facility to be located at Langley Air Force Base (LAFB). The report is for information only and presents our understanding of the project, reviews the exploration procedures, and presents our observations, and provides general guidance with respect to geotechnical engineering considerations.

2. PROJECT INFORMATION

2.1 Scope of Work: The Norfolk District, U.S. Army Corps of Engineers was requested by Langley Air Force Base (LAFB) to prepare a preliminary geotechnical report. It is our understanding that information from the report will be used at a Planning Charrette scheduled for the end of October 2015. As part of Norfolk District’s Services to LAFB, the Geo-Environmental Section performed a limited subsurface exploration and prepared a preliminary geotechnical engineering report within the boundaries of the proposed project site as specified by LAFB personnel. A location map provided by LAFB personnel is attached in Appendix A.

The Norfolk District, U.S. Army Corps of Engineers (USACE) Geo-Environmental Section has also been requested by LAFB to provide information pertaining to the demolition of four (4) existing structures (Buildings 326, 333, 337, and 339) in association with the proposed project. A limited environmental assessment (ESA) was performed consisting of site reconnaissance, record search and interviews with base environmental and engineering offices.

2.2 Proposed Facility: According to documents provided by the Norfolk District Engineering Management Section, it is the understanding of the Norfolk District Geo- Environmental Section that the proposed Air Force Targeting Center Facility (AFTCF) is to be constructed as a two-story building and shall contain a total area of 94,800 square feet. The proposed facility must include space for 1,750 workstations and associated racks and communications equipment, mechanical space, conditioned computer warehouse space, and command staff offices for Center and three Squadrons. The facility space must accommodate crew size based on number, duration and frequency of worldwide targeting and geospatial intelligence operations in support of Allied Forces. The facility must also include space for operations, mission support, logistics support, and administrative support. It was also suggested that the facility include an emergency generator, site improvements, a foundation so that the building finished floor is ten (10) feet above mean high tide sea level, parking, and all necessary support. Due to the flooding in the Langley area, the building shall have finished floors above the appropriate design flood. Two intramural softball fields will also be demolished and relocated.

It is also our understanding that the project will also include the demolition of Buildings 326, 333, 337, and 339, which are located on the south side of the runway area. A location map is provided in Appendix A.

2.3 Site Description: The Air Force Targeting Center Facility will be constructed at Langley Air Force Base, Hampton, Virginia. The proposed building site lies southeast of the intersection of Helms Avenue and South Roma Road. Currently the site is a softball field, which is used for recreational purposes. Ground surface elevation was interpolated from USGS/FEMA LiDAR-2014 contour elevation maps provided by the Geospatial Section, Water Resources Division, Norfolk District USACE. A location map and project site contour elevation maps are provided in Appendix A.

3. LIMITED SUBSURFACE EXPLORATION

3.1 General: A limited subsurface exploration consisting of soil borings was performed to identify the subsurface material properties and define the subsurface stratigraphy. The subsurface exploration program consisted of soil borings with standard penetration tests (SPT). The soil borings tests were performed by Savannah District, U.S. Army Corps of Engineers under the supervision of an Engineer from Norfolk District, U.S. Army Corps of Engineers.

3.2 Location: A limited number of borings were evenly spaced across the site of the proposed facility. Boring locations were flagged in the field based on measurements from existing features. Latitude and Longitude coordinates for each boring location were interpolated on Google Earth Pro and converted to UTM Northing and Easting coordinates using the website http://www.latlong.net/lat-long-utm.html. Ground surface elevations for each boring were interpolated by USGS/FEMA LiDAR-2014 contour elevation maps provided by the Geospatial Section, Water Resources Division, Norfolk District USACE. The location and elevation are accurate only to the degree implied by this method used to their determination. Prior to drilling, all locations were cleared for underground utilities by Virginia Miss Utility, personnel from Safety and Quality Assurance Alliance (SQA2) at NASA Langley Research Center, and utility personnel at LAFB. Boring locations are shown on the enclosed subsurface exploration plan, provided in Appendix B.

3.3 Soil Testing and Sampling: Five (5) Standard Penetration Test (SPT) borings, designated as B-1 through B-5, were drilled at the proposed site. SPT boring:

B-5 was performed on 7 August and 8 August 2015 and drilled to an approximate depth of 70 feet below ground surface (bgs); B-2 was performed on 8 August and 9

August 2015 and drilled to an approximate depth of 94.3 feet bgs; B-4 was performed on 9 August and 10 August 2015 and drilled to an approximate depth of 75 feet bgs;

B-1 was performed on 10 August 2015 and drilled to an approximate depth of 35 feet bgs; and B-3 was performed on 11 August 2015 and drilled to an approximate depth of 35 feet bgs. SPT borings were performed in accordance with ASTM D 1586 with an All-Terrain mounted drill rig utilizing 3-inch roller cone open hole mud rotary procedures and 3 ¼-inch I.D. hollow stem auger procedures. Borings B-2, B-4, and B-5 were performed using the 3-inch roller cone open hole mud rotary procedures, and Borings B-1 and B-3 were performed using the 3 ¼-inch I.D. hollow stem auger procedures. Soil samples were obtained with a standard 2-inch outer diameter and 24-inch long split-spoon sampler driven with a 140-lb automatic hammer falling 30 inches. The number of blows required to drive the sampler for each six (6) inch penetration increment was recorded. The recovered soil samples were visually classified in the field in general accordance with ASTM D 2488. Portions of the recovered soil were placed in plastic storage bags, sealed, and tested for Volatile Organic Compounds (VOCs) using a MiniRAE 2000 portable VOC monitor, also known as a Photo-Ionization Detector (PID). The detector stores hundreds of Low, High, Time Weighted Average (TWA), and Short Term Exposure Limits (STEL) in its library. The preset limits vary and depend on which gas is detected by the device.

If VOC exposures exceed preset limits, an alarm will sound on the detector emitting three (3) beeps and flashes per second. The samples were then returned to the Norfolk District Office for review. Boring logs are included in Appendix B.

3.4 Laboratory Soil Testing: Laboratory soil testing was performed by Savannah

District, U.S. Army Corps of Engineers Materials Testing Regional Technical Center of Expertise, located in Marietta, Georgia. Twenty-two (22) soil samples, which were generally representative of the subsurface materials, were selected for classification tests (ASTM D 422, D 2216, D 2487, and D 4318). After the final laboratory testing report was submitted, it was brought to the attention of the Norfolk District Engineer that the project had been renamed. Although the laboratory test results were performed on the currently titled Air Force Targeting Center Facility project site, the results are designated with the previous project title, the 363 Intelligence, Surveillance, Reconnaissance, and Wing Facility (ISRWF). The laboratory test results were used to aid in soil classifications. Laboratory test results are provided in Appendix C.

4. SUBSURFACE CONDITIONS

4.1 Regional Geology: Langley Air Force Base is located approximately four (4) miles north-northwest of Hampton, Virginia and approximately 10 miles east of Newport News, Virginia. It is located in the Coastal Plain Physiographic Province.

Numerous transgressions and regressions of the Atlantic Ocean have deposited marine, lagoonal, and fluvial (stream lain) sediments. The regional geology is very complex, and generally consists of interbedded layers of varying mixtures of sands, silts, and clays. According to the Geologic Map of Virginia, the surficial soils belong to the Lynnhaven Member (Qtl) of the Tabb formation. These soils are described as pebbly and cobbly, fine to coarse gray sand grades upward into clayey and silty fine sand and sandy silt. Thickness varies from 0 to 20 feet (USGS). A copy of the geologic map of the site can be seen in Appendix A. These surficial deposits are underlain by the soils of the Yorktown formation. The Yorktown formation is Miocene in age. The top of the Yorktown formation typically consists of a relatively thin layer of bluish gray to gray highly plastic clay. The layer typically acts as an aquaclude between overlying soils and the underlying Yorktown soils. The underlying soils of the Yorktown formation typically consist of bluish gray to gray, fossiliferous, medium dense silty sands, and firm to very stiff sandy silts and silty sands. Shell beds are often abundant in this formation. The Yorktown stratum, once encountered, generally extends to depths in excess to 150 feet below sea level.

4.2 Subsurface Stratigraphy: The subsurface conditions discussed in the following section and those shown on the boring test logs represent interpretations of the boring data and are for information only. The lines designating strata breaks on the boring logs and those indicated below represent approximate boundaries between soil types, as the transition may be gradual or may occur between samples. The generalized subsurface stratigraphy is our interpretation of the soil stratigraphy and subsurface condition at the project site based on our subsurface exploration and available information. The interpretation necessarily assumes uniform subsurface conditions across the site, which is probably, but not necessarily, correct. The general descriptions, below, should not be considered as a substitute for the boring logs.

Generalized subsurface profiles for the site are also included in Appendix B of this report.

A surficial soil layer was encountered to a depth of approximately 4-inches bgs in the soil borings. This soil is typically a Very Loose to Loose, Brown Silty Fine SAND with organics and roots. Roots (organic matter) were encountered in all borings to a depth of 4.0-inches to 4.0 feet bgs. Boring B-5 contained trace roots extending from depths 4.0 to 6.0 feet bgs.

For Borings B-1 through B-4, underlying the surficial soils is a layer of man placed fill material which consists of Loose to Medium Dense, Brown, Yellowish Brown, Reddish Brown, Orangish Brown, Tan and Black, Fine to Coarse, Silty SAND, with pea gravel, gravel and roots, classified as SM. Boring B-2 encountered a hard object at its original drilling location approximately 5.0 feet bgs. The drill rig moved east

3.0 feet and encountered a hard object at approximately 2.5 feet bgs. The drill rig moved east an additional 3.0 feet (6.0 feet total offset) and encountered another hard object at approximately 2.5 feet bgs. The 3-inch roller cone was removed and a hollow stem auger was installed to drill through the hard material. The hollow stem auger penetrated through the hard material to approximately 4.0 feet bgs, where the 3-inch roller cone was re-installed and the next split-spoon sample was collected.

Based on auger cuttings and debris encountered in the split spoon samples, it was determined that the hard material encountered was red brick and gravel. Refer to Photo 1 in Appendix D. Red brick and a cobble rock measuring approximately 4-inches in diameter was also encountered at Boring B-4 while advancing the hollow stem auger through hard material ranging in approximate depth of 2.0 to 4.0 feet bgs.

This is shown in Photo 2 in Appendix D. The fill material for Borings B-1 through B-4 was encountered to an approximate depth between 2.0 to 5.3 feet bgs. Boring B- 5 contained possible fill material which consists of Loose, Brown, Yellowish Brown, Orangish Brown and Gray Silty and Clayey Fine to Medium SAND with trace pea gravel and roots, classified as SM or SC. This material was encountered to an approximate depth of 6.0 feet bgs. SPT N-values for Borings B-1 through B-4 ranged from 9 to 19 blows per foot (bpf) with an average of 14.1 bpf. SPT N-values for Boring B-5 ranged from 7 to 10 blows per foot (bpf) with an average of 8.5 bpf.

Refer to Table 1 below for the approximate depths of fill and possible fill for each boring.

According to the laboratory soil tests on selected samples, the moisture content for the fill and possible fill material ranged from 8.2 to 19.9 percent with an average of

14.1 percent. The percent passing the No. 200 Sieve ranged from 30.1 to 36.7 percent with an average of 33.4 percent.

PID readings recorded for the fill material appeared to range consistently in value.

The readings for the fill material were encountered to range in value of 1.5 to 9.3 parts per million (ppm) with an average of 5.7 ppm. The PID meter did not detect VOCs for Boring B-5 from depths 0 to 38 feet bgs possibly due to the poor sealing capability of the plastic storage bags used to store the samples. At depth 38 feet bgs different storage bags were used to store the samples and the PID meter was capable of detecting VOCs for the samples through termination of boring. The PID meter did not exceed preset levels of VOCs, which would have allowed the detector to beep, flash, or set off an alarm. No odors were detected for the fill and possible fill material. PID readings are shown in Table 1 below.

Table 1. Fill Material and Possible Fill Material Depths and PID Readings

Boring Approximate Depth Range bgs

(feet)

PID

(ppm) B-1 (fill material) 0.3 - 2.0 6.0 B-2 (fill material) 0.3 - 5.0, possibly deeper 1.5 to 7.1 B-3 (fill material) 0.3 - 5.3 2.0 to 9.3 B-4 (fill material) 0.3 - 4.0 5.4 to 8.7

B-5 (possible fill material) 0.3 - 6.0 No Reading

Underlying the layer of fill and possible fill materials, is a layer which consists of Very Loose to Loose, Brown, Orangish Brown, Yellowish Brown, Reddish Brown, Tan and Black, Fine to Coarse Silty and Clayey SAND, classified as SM or SC. This material was encountered to an approximate depth of 9.8 to 12.0 feet bgs. Shell fragments were encountered in Borings B-2 and B-3, ranging in depths from approximately 8.0 to 12.0 feet bgs. Little pea gravel was encountered in Boring B-4 ranging in depth from approximately 4.0 to 6.0 feet bgs. SPT N-values ranged from 0 to 13 bpf with an average of 4.6 bpf. This material has been designated as Stratum I for this site.

According to the laboratory soil tests on selected samples, the moisture content for the Stratum I ranged from 20.5 to 36.5 percent with an average of 25.6 percent. The percent passing the No. 200 Sieve ranged from 14.4 to 39.5 percent with an average of 24.5 percent.

PID readings recorded for Stratum I consistently decreased with depth. The readings for Stratum I were encountered to range in value of 3.2 to 9.3 parts per million (ppm) with an average of 5.2 ppm. The PID meter did not exceed preset levels of VOCs, which would have allowed the detector to beep, flash, or set off an alarm. No odors were detected for Stratum I. PID readings are shown in Table 2 below.

Table 2. Stratum I Depths and PID Readings

Boring Approximate Depth Range bgs (feet)

PID

(ppm) B-1 2.0 - 12.0 2.5 to 9.3 B-2 5.0 - 12.0 3.2 to 4.3 B-3 5.3 - 12.0 3.7 to 8.2 B-4 4.0 - 12.0 4.4 to 7.6 B-5 6.0 - 9.8 No Reading

Underlying Stratum I was a Very Loose to Very Dense, Gray and Bluish Gray, Silty and Clayey Fine SAND with varying sizes and amounts of shell fragments, classified as SM or SC. This material was encountered to the depth of termination for all borings. Boring B-2 contained a layer of Stiff to Very Stiff, Gray and Bluish Gray CLAY with some silt and shell fragments, classified as CL, ranging in depth from approximately 68.0 to 72.0 feet bgs. SPT N-values ranged from 1 to 50+ bpf with an average of 8.6 bpf. This material has been designated as Stratum II for this site.

The moisture content for the Stratum II ranged from 23.2 to 38.0 percent with an average of 33.5 percent. The percent passing the No. 200 Sieve range from 14.7 to

55.5 percent with an average of 23.9 percent.

PID readings recorded for Stratum II varied with depth and were found to be inconsistent for all borings. The readings for Stratum II were encountered to range in value of 0.8 to 25.4 parts per million (ppm) with an average of 5.4 ppm. In Boring B- 2 PID readings were encountered to range in value of 17.1 to 25.4 ppm, at the approximate depths of 23 to 25 feet and 38 to 50 feet bgs. The PID meter did not exceed preset levels of VOCs, which would have allowed the detector to beep, flash, or set off an alarm. Naturally occurring chemical compounds and hot, sunny, and humid weather conditions may be a possible cause for the higher VOC levels detected in Boring B-2. No odors were detected for Stratum II. PID readings are shown in Table 3 on the following page.

Table 3. Stratum II Depths and PID Readings

Boring Approximate Depth Range bgs (feet)

PID

(ppm) B-1 12.0 - 35.0 0.9 to 2.8 B-2 12.0 - 94.3 1.2 to 25.4 B-3 12.0 - 35.0 2.8 to 9.2 B-4 12.0 - 75.0 0.8 to 9.3 B-5 9.8 - 70.0 **1.3 to 10.1

**Beginning at 38 feet bgs.

4.3 Groundwater Conditions: Groundwater was measured at each borehole approximately after auger removal and 24 hours after drilling operations. The water level was observed to range approximately 5.0 to 6.8 feet bgs approximately 24 hours after drilling operations were complete. A temporary well was also installed approximately 6.0 feet south of Boring B-4 on 9 August 2015. It was installed to a depth of approximately 10.0 feet bgs with approximately 5.0 feet of screen and 5.0 feet of riser. The water level was observed at approximately 6.5 and 7.0 feet approximately 24 hours after installation and 48 hours after installation.

The depth to groundwater that was observed at time of the exploration does not reasonably represent the conditions that will be encountered during construction or for the life of the building. Due to the shallow water table conditions encountered in the borings, groundwater could be found close to the ground surface. Groundwater levels are expected to fluctuate with seasonal changes, periods of heavy or little rainfall, tides, pumping from wells, and other factors. The near surface soils can become soft and wet.

5. PRELIMINARY GEOTECHNICAL ENGINEERING

CONSIDERATIONS

5.1 Foundation Design: Based on the results of the preliminary subsurface exploration program, it is our opinion that the proposed facility should be supported by means of a deep pile foundation system. Square precast pre-stressed concrete piles (SPPC) will be the most economical of the driven pile options and are one of the most widely utilized deep foundation systems in the Tidewater Area. The piles are available in sizes from 10 to 24 square inches, and are typically designed for allowable pile loads of between 35 to 250 tons (70 to 500 kips). Lengths of piles typically in the Tidewater Area may vary between 40 to 80 feet to obtain the required capacity.

Table 4 on the following page provides our preliminary estimates of pile capacities for various SPPC dimensions and tip elevations for the facility’s foundation system while using a factor of safety of 3. These values are not for design but for general planning. The design needs to consider other factors but not limited to building loads, site grading, and horizontal deflections. The Contractor will need to perform an analysis to determine the actual pile capacity and settlements. Verification load testing shall be included as part of the contract for production piles during construction. The capacity of a group of piles should not be spaced less than three (3) pile diameters apart, center to center, and a reduction of capacity will be needed for pile groups. The final order lengths and tip elevations will be adjusted based on the results of the test piles and load test programs.

Table 4. Square Precast Pre-stressed Concrete Pile Sizes and Approximate Capacities

SPPC

Dimensions

(ft)

Embedment Depth

(ft)

Approximate Allowable

Compression Capacity (kips)

Approximate Allowable

Tension Capacity (kips)

12-in x 12-in

90 45 16-in x 16-in 150 70 18-in x 18-in 200 85 12-in x 12-in

95 50

16-in x 16-in 160 75 18-in x 18-in 215 95 12-in x 12-in

100 55

16-in x 16-in 170 85 18-in x 18-in 225 105 12-in x 12-in

110 60

16-in x 16-in 180 90 18-in x 18-in 240 115 12-in x 12-in

115 65

16-in x 16-in 190 100 18-in x 18-in 255 125

The piles are expected to derive the majority of their capacity from shaft friction with minor end bearing in sand layers at deeper depths. The soil materials typically exhibit time-dependent strength characteristics. The dynamics of driving piles will cause excess pore pressures to develop, thereby decreasing driving resistance during initial pile installation. Once driving is complete, the excess pore pressures dissipate with time and the bearing capacity of the pile increases. Several days will be required for the excess pore pressures to dissipate. Due to these reasons, it will not be possible to confirm pile capacities with a simple driving criterion such as number of hammer blows per foot or advanced pile. Instead, driving criteria will likely consist of a target tip elevation and/or certain embedded length in a bearing material with specified driving resistance. The specified driving resistance should be based on a Wave Equation Analysis of the Contractor’s selected hammer. Pre-drilling may also be required to certain depths below the ground surface to aid in the installation of the piles through existing fill and debris, and to reduce the potential of breakage.

The proposed facility finished floor shall be constructed above the appropriate design floor. Several feet of controlled structural fill, selected by the Contractor, shall be necessary to raise the final floor of the facility above future flood elevation. Refer to section 6.3 for controlled structural fill recommendations.

5.2 Ground Floor Slab-on-Grade: The ground floor slabs-on-grade for the proposed building may be supported on properly compacted controlled structural fill resting above the in-situ fill soils. The existing man-placed fill can remain in place if the ground floor slab is lightly loaded with general office furniture. Some undercutting and replacement of existing fill soils may be required if soils are soft or unsuitable as identified during the proof-rolling procedure of the subgrade. If the slab will be heavily loaded with large equipment, then the slab shall be structurally supported on the deep foundation system.

A four-inch thick granular base layer consisting of open-graded crushed stone (VDOT 57 crushed stone) or clean sand (ASTM C-33 Sand) should be placed beneath the floor slabs. This granular base would function as a leveling and load disturbing material for the slab and provide a capillary break beneath the slab.

A vapor barrier should be used beneath ground floor slabs that will be covered by tile, wood, carpet, impermeable floor coatings, and/or if other moisture-sensitive equipment or materials will be in contact with the floor. Utility and other excavations within the subgrade of the floor slabs shall be backfilled with properly compacted structural fill in accordance with the project specifications to provide uniform floor slab support.

5.3 Seismic Site Classification for Design: The site soils were classified in accordance with ASCE Standard ASCE 7-05, Chapter 20 based on the Standard Penetration Resistance (N) obtained from the 94.3 foot boring. The average N values over the upper 100 feet of soil was determined to be less than 15 bpf, and in accordance with this method the site class is defined as Site Class E. The most accurate site classification can be obtained by using the average shear wave velocity procedure; however, this requires special testing such as surface wave tests or seismic cross-hole tests. Performing such tests may lead to a more favorable site classification which will lead to lower design forces and possible savings in the building structure.

5.4 Pavement Design Recommendations: The following general pavement recommendations are made: design adequate grading to provide runoff away from paved surfaces and beyond the limits of paved area and building areas. We recommend underdrains at low points in the pavement to limit water penetration into the base course and subbase.

The ability of the existing subgrade soils to support pavement structures may be variable across the site. The existing subgrade soils are moisture sensitive and will lose stability when subjected to moisture and construction traffic. It is recommended that pavement construction be performed during the summer months and to provide positive drainage to prevent moisture from ponding on the subgrade.

5.5 Groundwater and Site Drainage: Groundwater was encountered in all borings at a relatively shallow depth. Approximately 24 hours after drilling the water level in the borings ranged from 5.0 to 7.0 feet below the surface. Based on our observations the relatively shallow groundwater will probably impact excavations performed on this site. Dewatering such as sumps with pumps or wells will be required for most utility excavations. Temporary drainage ditches should also be employed by the Contractor to accentuate drainage during construction.

6. PRELIMINARY EARTHWORK CONSIDERATIONS

6.1 Site Preparation: Proper site preparation will be critical to this project in order to achieve satisfactory performance of the structure. It is recommended that a Geotechnical Engineer be retained to provide soil engineering services during the actual site preparation and foundation construction phase of the project to perform appropriate evaluations to help assure that conditions encountered during construction are similar to the conditions encountered in the subsurface exploration. The Geotechnical Engineer can also assist in interpretation of differing subsurface conditions that may be encountered and recommend remedial work, if needed.

Site preparation for the building pad and pavements should include complete removal of surface vegetation, surficial soils, organic material, trees, tree stumps, roots and organic soils. Measured topsoil in the borings was generally four (4) inches thick.

However, some roots were encountered in borings extending 2.0 to 6.0 feet below the surface. Topsoil is defined as the upper surface soils that contain roots and other organic material. Due to groundwater conditions encountered on the site, the removal of the existing fill would be an expensive undertaking.

Stripping of topsoil should be performed to a horizontal distance of at least 10 feet beyond the limits of the building footprints, and five (5) feet beyond the limits of pavement in the undeveloped areas. Areas of construction should also be cleared of soft, wet, or disturbed soils. Over-excavated areas should be backfilled with properly compacted suitable fill. During the clearing and stripping operations, positive surface drainage should be maintained to prevent the accumulation of water.

After stripping, the exposed subgrade soils in the areas of development should be proof-rolled with a 15-ton loaded dump truck or other pneumatic-tired vehicle of similar size and weight. Proof-rolling should be observed by a Geotechnical Engineer and the Contracting Officer. Proof-rolling should be performed during a period of favorable weather and not while the site is wet, frozen, above planned grade, or severely desiccated. Any unsuitable materials that are observed to yield or rut noticeably during proof-rolling should be under and replaced with compacted imported controlled structural fill or stabilized in-place as recommended by the Geotechnical Engineer and approved by the Contracting Officer.

The near surface subgrade soils are moisture sensitive and will lose stability if these soils become wet and are subjected to construction traffic. As a result, site preparation should be performed during an extended period of dry weather.

Undercutting or reworking by aerating or discing or the near surface soils may be necessary if the exposed subgrade soils become unstable during construction. Any fill materials, aggregates, and/or concrete should be placed as soon as possible over the approved subgrade in order to reduce exposure of the subgrade to weather and construction activity. It is important to stress that the subgrade needs to be properly prepared and protected during construction to minimize the degradation of these soils.

6.2 Foundation Construction: Test piles should be driven at the site within the proposed foundation areas prior to installation of production piles. The purpose of the test piles is to attempt to verify bearing depths, axial compressive capacities, and driving conditions across the site. Test piles should be 10 feet longer than the anticipated pile design length and should be driven to the indicated design bearing depth. The Geotechnical Engineer of record should witness the test pile installation.

The test piles should be located to provide coverage over the planned foundation areas. The number of test piles will be dependent upon the combination of the pile types and bearing elevations selected for the project. Test piles may be installed at planned permanent pile locations and utilized if adequate capacity is achieved. The test pile locations should be reviewed and approved by the Geotechnical Engineer of record. As a minimum, two static load tests per ASTM D 1143 shall be performed for the building. Pile re-strikes shall be performed in accordance with ASTM D 4945. A dynamic pile analysis shall be performed on each pile. The pile re-strikes shall not be performed until at least 3-days after test pile installation. The pile hammer used in the test pile program shall have sufficient energy to “prove” at least 250% of the specified allowable pile design capacity(ies). Application of the test load should be performed under the direction of a Geotechnical Engineer.

A wave equation and drivability evaluation should be performed for the proposed pile hammer assembly prior to the start of the test pile program. CAPWAP analyses should be performed on the PDA measurements obtained from the test piles indicated. Depending on the findings of the dynamic testing, the specified pile load test may be deleted at the discretion of the Geotechnical Engineer of record. In addition, some adjustment of the design capacities or bearing depths may be necessary.

6.3 Controlled Structural Fill: Fill placed beneath buildings, structures, and under roadways which will raise the site to the finished subgrade shall be compacted structural fill. Controlled structural fill material under buildings and the roadways should be non-expansive and free of organic matter, debris, and particles larger than two (2) inches in size. Proposed fill materials should be subjected to laboratory tests consisting of, but not necessarily limited to, moisture density determinations, Atterberg limits, and sieve analysis. Controlled Structural Fill under buildings, pavements, and structures should classify per USCS as SW, SP, SP-SM, SM, or SC with a maximum of 35 percent fines passing the No. 200 sieve.

6.4 Suitability of On-site Material: Due to existing fill, groundwater elevations, and debris encountered in the borings on the site, it is our opinion that structural fill will need to be imported from off-site. The imported fill shall conform to the recommendations above. The on-site soils will not be suitable for reuse as backfill in excavated utility trenches. Backfill material in utility trenches within the construction areas should consist of structural fill (as described in the previous section), and should be compacted to at least 95 percent of the standard Proctor maximum dry density in accordance with ASTM D 698. This fill should be placed in 4 to 6 inch loose lifts when hand compaction equipment is used.

6.5 Compaction Requirements: The contractor shall provide proper equipment to meet compaction requirements based on a modified Proctor (ASTM D 1557). Due to the higher energy from the modified Proctor, the optimum moisture content of the material will be lower than a standard Proctor. The in-situ moisture content of the subsurface material is expected to be higher than the optimum moisture content from a modified Proctor. The contractor should be prepared to adequately dry the in-situ soils prior to placement as backfill. The compaction requirements for this project are listed below:

Structures, Foundations, and Concrete Slabs: Compact top 12 inches of subgrade and subsequent structural fill to 95 percent of ASTM D 1557.

Roads and parking areas: Compact top 12 inches of subgrade and subsequent fill to 95 percent of ASTM D 1557.

Green Areas: Compact to 85 percent of ASTM 1557.

Maximum loose lift thickness shall be eight (8) inches and 12 inches under buildings and pavements, respectively. Proper compaction equipment should be utilized by the contractor to achieve the required compaction. For areas which do not permit the use of heavy compaction equipment (utility trenches) lift thickness shall be reduced to six

(6) inch loose lifts to achieve the required compaction. During fill operations, positive surface drainage should be maintained to prevent the accumulation of water.

Each lift of fill should be tested in order to confirm that the degree of compaction is attained. Field density tests to verify fill compaction should be as required by the earthwork specification.

The moisture of backfill material should be maintained within three (3) percentage points of the optimum moisture content as determined from the modified Proctor.

Compaction requirements may be reduced by five (5) percent for cohesive material, defined as material contained more than 50 percent fines (material passing the No.

200 sieve).

Care should be used when operating the compactors near existing structures to avoid transmission of the vibrations that could cause settlement damage or disturb occupants. In this regard, it is recommended that the vibratory roller remain at least 25 feet away from existing structures; these areas should be compacted with small, hand-operated compaction equipment.

7. LIMITED ENVIRONMENTAL SITE ASSESSMENT

CONCLUSIONS AND RECOMMENDATIONS

7.1 Assessment: Discussions with the 633 Civil Engineer Squadron, Environmental Element personnel and records review provided copies of Hazardous Material Inspections that were performed on the four (4) buildings slated for demolition.

During the time spanning April 1991 through July 1991, Asbestos surveys were performed on all four (4) buildings. The surveys provided visual inspection and destructive sampling of suspected Asbestos Containing Materials (ACM). The resulting reports provided percent concentrations of asbestos and locations, along with projected costs for removal. It is believed that these surveys were performed prior to a planned renovation and it is apparent that this and/or additional renovations have occurred to the buildings since 1991. These reports did not provide any information about other potential hazardous materials (mercury or PCB containing components and lead paint). An additional Asbestos Inspection and Hazardous Material Inspection was performed at Building 326 in May 2011. This work was performed in preparation for renovations specifically associated with rooms 104, 106, 108, and 112 and was not performed on the entire building. Environmental research for the Air Force Targeting Facility site was also performed during the assessment, but no historical information could be found.

7.2 Conclusions: The asbestos assessments performed in 1991 positively identified the presence of ACM in buildings 326, 333, 337, and 339. Additionally, the limited Asbestos Inspection of Building 326 performed in 2011, also confirmed the presence of ACM in rooms 104, 106, 108, and 112. Further inquiries to the engineering department at LAFB revealed that removal of ACM from the four (4) buildings could not be confirmed from existing records. The continued presence of ACM in Building 326 in May 2011 supports the conclusion that ACM is likely remaining in all the building slated for demolition.

The limited 2011 Hazardous Materials Inspection performed at building 326 in 2011, concluded mercury containing fluorescent bulbs and potentially PCB containing light ballasts is present. No information on the presence of lead based paint was discovered during the document review.

7.3 Recommendations: The LAFB should procure a comprehensive HAZMAT Survey and provide these results (as well as previous assessments) to the Contractor.

The Contractor should be directed that all ACM and hazardous materials be removed and disposed of in accordance with applicable law prior to demolition of the buildings.

Hard copies of historic assessments reside in-house and at the Langley 633 Civil

Engineer Squadron, Environmental Element.

REFERENCES

Google. Map of Langley Air Force Base, Hampton, Virginia.

<https://www.google.com/maps/@?hl=en >

USACE. GIS Map of Virginia. < http://nao-ap-oracle.nad.ds.usace.army.mil:7777/pls/apex/f?p=106:1:622262098569401:::::>

USGS. “Tabb Formation, Lynnhaven Member.”

<http://mrdata.usgs.gov/geology/state/sgmc-unit.php?unit=VAQtl%3B0>

APPENDIX A:

LOCATION AND GEOLOGIC MAPS

A1

Map 2. Langley Air Force Base, Hampton Virginia. Red circle indicates project site (Google).

Map 3. Air Force Targeting Center Facility project site. Red circle indicates location (Google).

A2

Sweeney Blvd Sweeney Blvd

Lee R d.

Lee

R d.

E lm

S t

E lm

S t

Worley Rd Worley Rd

Nealy Ave

Nealy Ave

W ard

R d.

W ard

R d.

Weyland Rd

Weyland Rd

Dod d

Blvd

Dod d

Blvd

K ing

S t

K ing

S t

Clarke Ave

Clarke Ave

Poplar Rd.

Poplar Rd.

Dan fo rth Ave

Dan fo rth Ave

Eag an

Ave

Eag an

Ave

Be ne di ct

Ave

Be ne di ct

Ave

Durand St.Durand St.

H olly S t H olly S t

Gray Ave Gray Ave

Glover Ave

Glover Ave

Bur re ll S t

Bur re ll S t

Plumb St

Plumb St

Th or ne ll

Av e

Th or ne ll

Av e

Em mons

Rd

Em mons

Rd

Douglas St.

Douglas St.

Spaatz Dr.

Spaatz Dr.

Bowen St.

Bowen St.

P ine R d.

P ine R d.

Helms AveHelms Ave

Dur an d Rd

Dur an d Rd

Dogwood Ave Dogwood Ave

Harris Ave Harris Ave

C ook A ve

C ook A ve

H un tin g

A ve

H un tin g

A ve

Wright AveWright Ave

W illow

S t

W illow

S t

Thompson St

Thompson St

Walnut Ave.

Walnut Ave.

O ak R d.

O ak R d.

Cedar Ave Cedar Ave

Hamm ond Ave

Hamm ond Ave

Andrews St

Andrews St

Durand Loop Rd

Durand Loop Rd

Ash Ave Ash Ave

A lert D r.

A lert D r.

H ickory R d.

H ickory R d.

Sm yth e Rd.

Sm yth e Rd.

T aylor R d.

T aylor R d.

Bryant Ave

Bryant Ave

B irch S t.

B irch S t.

LaS alle

A ve

LaS alle

A ve

Hilla rd

St

Hilla rd

St

N . R om a

R d.

N . R om a

R d.

Rickenbacker Rd.

Rickenbacker Rd.

W atts

A ve.

W atts

A ve.

M aple S t.

M aple S t.

C herry S t.

C herry S t.

Bur re ll L oo p

Bur re ll L oo p

R ya n A ve

R ya n A ve

Juniper A ve.

Juniper A ve.

S . R om a

R d.

S . R om a

R d.

Beech Ave.

Beech Ave.

S pruce S t S pruce S t

Butternut Ave Butternut Ave

M agnolia S t.

M agnolia S t.

Basswood Ave Basswood Ave

Sperry C t

Sperry C t

Lee Rd Lee Rd

W right Ave

W right Ave

Wrig ht Ave

Wrig ht Ave

Dogwood Ave Dogwood Ave

Sweeney B lvd

Sweeney B lvd

King S t King

S t

Elm St

Elm St

330330 290290

291291

643643

328328

257257

351351

752752

751751

757757

226226

753753

768768

750750

791791

789789

790790

648648

777777

658658

361361

633633

412412

926926

247247

602602

272272

338338

621621

355355

781781

140140

775775

681681

693693

13621362

642642

161161

661661

252252

664664

362362

763763

367367 367367

640640

647647

10231023

764764

369369

162162

374374

254254

224224

371371

372372

373373

131131

130130

10271027

782782

3636 3535

641641

801801

945945

121121122122

584584

794794

10871087

635635

546546

587587

623623

703703

326326

760760 586586

606606

671671

669669

123123

407407

222222

617617

329329

608608

378378

325325

258258

590590

558558

888888 889889

591591

321321

520520

331331

366366

246246

368368

13011301

339339

10691069

580580

385385

891891

333333

583583

342342

472472

467467

943943

10531053

759759

253253

442442

13161316

221221

244244

714714

340340

10651065

583583

337337

190190 141141

271271

994994

10041004

788788

952952

13511351

10571057

10981098

646646

10641064

727727

615615

582582

192192

550550

147147

10791079

10461046

13071307

448448

10801080

640640

10361036

747747

10181018

763763

10261026

10621062

630630

13291329

741741

10671067

619619

13101310

148148

655655

784784

13321332

142142

10201020

10441044

267267 266266 265265

700700

143143

641641

645645

293293

13091309

999999

10771077

347347

596596

13581358

648648

10931093

10951095

10971097

10921092

10941094

10501050

632632

13311331

441441

13341334

566566

732732

13521352

10961096

10161016

223223

10351035

774774

13301330

13611361

10381038

379379

13911391

10751075

860860

861861

10021002

10021002

10311031

641641

568568

720720

13891389

981981

560560

685685

905905

544544 543543

248248

418418

261261

10611061

21872187

684684

993993

504504

421421

13121312

87879393

422422

549549

220220

463463 557557

505505

605605

13881388

648648

556556

502502

567567 570570

451451

513513

453453

454454

431431

596596

424424449449

514514 506506

428428

21862186

452452

435435

436436

327327

415415

880880

21842184

860860

21832183

435435

505505504504

554554

21842184

13001300

426426

728728

510510

507507

446446

429429

771771

502502

548548454454

430430

551551

452452

510510

851851

417417

453453

446446

512512

508508 508508

423423

944944

449449

447447 429429

512512

434434

10601060

507507

503503

450450

430430

445445

10301030

810810

414414

423423

445445

426426

640640

942942

817817

949949

735735

644644

948948

13801380

534534

10251025

530530

542542

691691

524524

533533

527527

537537

525525

535535

335335

731731

691691

536536

688688

538538

534534

690690

526526

532532

907907

695695

983983

869869

980980

607607

950950

459459

808808

873873

928928

989989

976976

688688

823823

853853

974974

806806

539539

146146

519519

830830

614614

819819

852852

959959

262262

816816

857857

324324

804804

10521052

826826

840840

833833

541541

829829

10661066

809809

854854

882882

805805

820820

835835

849849

807807

971971

868868

689689

875875

523523

971971

648648

988988

991991

821821

974974

878878

816816

957957

951951

815815

969969

803803

21822182

825825

986986

845845

821821

956956

10071007

455455

475475

842842

827827

460460

985985

982982

911911838838

831831

363363 462462

744744

13901390

827827

580580

707707

458458

268268

995995

911911

10631063

461461

870870

884884

978978

972972

139139

970970

10201020

342342

894894

343343

626626

320320

793793

10471047

376376

10851085

10391039

631631

10411041

10491049

360360

13851385

10561056

914914

10591059

758758

13261326

636636

910910

943943

13811381

10421042

13811381

904904

10001000

1037103710401040

914914

559559

13711371

416416

680680

10991099

419419

13701370

10081008

13921392

10091009

13921392

13351335

634634

935935

10081008

795795

662662

903903

10321032

846846

10131013

910910

322322

440440

10131013

13801380

13461346

706706

656656

299299

443443

432432

10881088

911911

10781078

910910

733733

521521

13611361

796796

796796

938938

914914

694694

912912

637637

914914

712712

13111311

937937

665665

384384

787787

555555

10761076

298298

10031003

10831083

402402

10541054

13211321

10201020

10341034

10511051 10211021

10101010 10081008

722722

408408

295295

439439

13031303

381381

Although every effort has been made to ensure the accuracy of information, errors and conditions originating from physical sources used to develop the database maybe reflected in the data supplied. The end user must be aware of the data conditions and ultimately bear responsibility and the appropriate use of the information with respect to possible errors, original map scale, collection methodology, currency of data, and other conditions specific to certain data.

LIMITED DISTRIBUTION

Distribution authorized to DoD, IAW 10 U.S.C. §130 & 455. Release authorized to U.S. DoDcontractors IAW 48 C.F.R.

§252.245-7000.

Removal of this caveat is prohibited.

This material is For Official Use Only.

Unauthorized reproduction, distribution, publication, or exhibition of this material is STRICTLY PROHIBITED. Refer other requests to 1CES/CEG. Destroy as "For Official Use Only". 1CES/CEG shall not be liable for any errors, omissions, or damages that result from noncompliance of this message.

Langley AFB, VA

Coordinate System:

NAD 83 Virginia State Plane South Zone 4502

Vertical Datum:

NAVD 88

Data Provided By:

1FW Geo Integration Office

Mapping Consultant Geobase Project ID Print Date

BASE MAP

SRA SOTO

CUSTOM

02AUG05

0 2,500 5,0001,250 Feet

A3

E4TSEJLS

Oval

E4TSEJLS

Oval

E4TSEJLS

Oval

E4TSEJLS

Text Box Map 3. The blue circles indicate the buildings to be demolished as a part of the project (Buildings 326, 333, 337, and 339).

US Army Corps of Engineers Norfolk District

Map: Targeting_Facility_Contours Developed By: Jason O'Neal Date: 10/16/2015I

1 in = 100 feetAir Force Targeting Center Facility Langley Air Force Base

Hampton, Va

Elevation Data Source:

USGS/FEMA LiDAR - 2014 Coordinate System:

NAD_1983_HARN_StatePlane_Virginia_South

0 10050 Feet

US Army Corps of Engineers Norfolk District

Map: Targeting_Facility_Contours Developed By: Jason O'Neal Date: 10/16/2015I

NAVD88 (feet) High : 23

Low : 4

1 in = 100 feetAir Force Targeting Center Facility Langley Air Force Base

Hampton, Va

Elevation Data Source:

USGS/FEMA LiDAR - 2014 Coordinate System:

NAD_1983_HARN_StatePlane_Virginia_South

0 10050 Feet

Map 7. Surficial soils located near LAFB, Hampton, Virginia. Red circle indicates LAFB

(USACE).

Map 8. Surficial soils at Air Force Targeting Center site belong to the Lynnhaven Member (Qtl).

Red circle indicates project site location (USACE).

APPENDIX B:

BORING LOCATION PLAN, BORING LOGS,

AND PROFILES

AIR FORCE TARGETING CENTER

LANGLEY AIR FORCE BASE, HAMPTON, VIRGINIA

BORING LOCATION PLAN

B‐4

B‐5

B‐2

B‐1

B‐3

Google 2015

0.3 0.5

2.0

3.0

4.0

6.0

12.0

27.0

[TOPSOIL] Very Loose, Brown and Yellowish Brown, Silty Fine to Coarse SAND with organics and roots, (4 inches) [FILL] Medium Dense, Brown, Black, Yellowish Brown and Orangish Brown, Silty Fine SAND, with small pea gravel, moist [FILL] Medium Dense, Orangish Brown and Black, Silty Fine to Coarse SAND with pea gravel, moist, roots [SM] Loose, Brown and Tan Silty Fine to Coarse SAND with some clay and roots, moist [SC] Loose, Brown and Orangish Brown Clayey Fine to Coarse SAND, moist [SC] Loose, Brown Mottled Gray and Orangish Brown Clayey Fine to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .