Carrier 20 Ton Chiller_Questions and Anwsers dated 5 May 2026.pdf

PDF 59 KB Posted

Attached to
Carrier 20 Ton Chiller
Solicitation number
FA469026Q0021
Issued by

About this file

This is a Questions and Answers document for solicitation FA469026Q0021 issued on 5 May 2026 regarding a Carrier 20 Ton Chiller procurement.

The document addresses two clarifying questions from potential offerors. Regarding start-up requirements, the government defines start-up as execution of a detailed checklist provided in the operator manual's back section to ensure proper commissioning, operational verification, and data recording for both air-cooled and water-cooled chillers. The government clarified that both delivery and start-up are required services; however, the on-base HVAC shop will be responsible for the actual installation of the chiller. This distinction indicates that the contractor must deliver the equipment and perform start-up procedures, but installation labor will be handled by government personnel.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Carrier 20 Ton Chiller

Solicitation: FA469026Q0021

Questions and Answers

5 May 2026

Q1: Will you give your definition of start up?

A1: A chiller has a start-up sheet, which is a detailed checklist used to ensure proper commissioning, operational verification, and data recording for both air-cooled and water-cooled chillers. The sheet is in the back of the operator manual.

Q2: Please advise if you only need this delivered?

A2: Delivery and start up is required. The on base HVAC shop will install the chiller.