Atch_9_Additional_Questions_Amendment_3.pdf

PDF 169 KB Posted

Attached to
AFFSC Support Services Federal contract opportunity
Solicitation number
FA4690-19-R-0001
Issued by
Department of the Air Force Air Combat Command

About this file

Atch 9 Questions and Answers_Amendment 3

View the file

Other files for this federal contract opportunity

Other files attached to AFFSC Support Services, newest first.
File Type Posted
FA4690-19-R-0001_Amendment_03_SF30.pdf PDF
Atch_1_PWS_Amendment_2.pdf PDF
FA469019R0001_SF30_Amendment_2.pdf PDF
Atch_8_Questions_and_Answers_Amendment_2.pdf PDF
Atch_4_Bid_Schedule_Rev._1.xlsx XLSX spreadsheet
SF30_Amend_1.pdf PDF
FA469019R0001;_SF1449.pdf PDF
Atch_3_WD_15-5367_(Rev._8).pdf PDF
Atch_5_Past_Performance_Questionnaire_Letter.pdf PDF
Atch_6_Past_Performance_Questionnaire.docx DOCX document
Atch_4_Bid_Schedule.xlsx XLSX spreadsheet
Atch_2_Composite_Accuracy_Table_(Appendix_A).pdf PDF
Atch_7_AFFSC_QASP.pdf PDF
Atch_1_Performance_Work_Statement.pdf PDF
DRAFT_RFP.pdf PDF
Composite_Accuracy_Table.pdf PDF
DRAFT_PWS.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

28TH CONTRACTING SQUADRON (AFGSC)

ELLSWORTH AIR FORCE BASE SOUTH DAKOTA

10 April 2018

MEMORANDUM FOR SOLICITATION VENDORS

FROM: 28 CONS/PKA

1000 Ellsworth Street, Suite 1200 Ellsworth AFB SD 57706

SUBJECT: Amendment 3 to Request For Proposal – AFFSC Support Services, FA4690-19-R-0001

A. Amendment 3 is hereby issued for subject requirement to provide answers to questions asked.

B. The following questions were asked and answers are provided:

1. Q. Please clarify whether Volumes I, II, and III to be titled as indicated in the Proposal Organization Table on Page 20 or as indicated under 2. General Format and Content on Pages 20-22, or as indicated under (unending question).

A: “Volume Title” in the proposal organization table on Page 20 of the SF1449 solicitation has been changed to “Volume Content” and shall be included in each Volume. As corrected in the 52.212-1 Addendum under Amendment 1 to the solicitation, the Volume order and Volume Titles shall be as follows:

Volume I – Completed Request for Proposal (RFP) Volume II – Written Technical Proposal Volume III – Past and Present Performance

Volume titles under FAR 52.212-2 Addendum, Paragraphs 2.b-d. have also been corrected to match volume titles under FAR 52.212-1 Addendum.

2. Q. The conflicting instruction is unclear as to the required content and order of appearance within the Volumes. We respectfully request that the government clarify what information must be included in Volume I, what information must be included in Volume II, and either clarify the order of appearance or confirm that the order of appearance is left to the Offeror.

A: The Proposal Organization Table under 52.212-1 Addendum has been revised with general content. Refer to 52.212-1 Addendum, Paragraph 2-General Format and Content, for proposal Volume naming, required content and order.

3. Q. Does the government want one Table of Contents for the entire proposal to be presented in Volume I or does the government prefer that each volume has its own Table of Contents?

A: Each volume should have its own Table of Contents (TOC). The TOC will not be counted in the Maximum Number of Pages indicated in the Proposal Organization Table under 52.212-1 Addendum.

4. Q. Does a Table of Contents count into the page count?

A: No.

5. Q. Is it permissible to include a two-page Executive Summary in the Proposal and include it within the page limit? If yes, where would the government prefer that it be located?

A: Yes, a two-page Executive Summary is acceptable. Include it in front of the Table of Contents for Volume I-Completed Request for Proposal (RFP).

6. Q. What is the “competitive range”? This statement indicates that there is a hidden standard which could further delineate higher and lower scores amongst Acceptable offers. We respectfully request that the Government provide the evaluation criteria that is used in the above scenario to distinguish the “most highly rated proposals” from the less highly rated proposals if there are too many acceptable ones to evaluate.

A: As referenced in FAR 52.212-2 Addendum, Paragraph 1.a. this acquisition will utilize Lowest Price Technically Acceptable (LPTA) following FAR 15.101-2 and 15.3 as supplemented by the DoD Source Selection Procedures referenced in DFARS 215.300 to assess a best value award decision. Evaluations will be made on all proposals to assess technical acceptance and acceptable past performance. If a large amount of proposals are received and have passed the technical and past performance acceptance evaluation, the contracting officer will identify the range of proposals that are highly rated amongst all proposals to make a competitive range determination. Among those offerors who have acceptable technical and past performance ratings, the award will be made to the offeror having the lowest total evaluated price.

C. The response date for receipt of proposals remains unchanged at 11 May 2018, 2:00 pm (MST) as revised under Amendment 1.

D. Per request for proposal requirements, please mail your proposal to reach 28 CONS/PKA as soon as possible but not later than 2:00 p.m. Mountain Standard Time on 11 May 2018.

BERNARD CLEMENS

Contracting Officer