3._Schedule_Material_Submittal.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- Renovation of Ten Gilley Houses
- Solicitation number
- FA466418B0005
About this file
schedule of Material Submittal
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 11._Updated_Floorplans_-_LVT_&_Carpet_Placement_Bldgs_243_249_250.pdf | ||
| SF_30_Amendment_0002.docx | DOCX document | |
| 2._SOW_Gilley_Houses_2018.docx | DOCX document | |
| 10._Asbestos_Survey_Report.pdf | ||
| 1._New_Gen_Decision_9-07-2018.pdf | ||
| 12._RFI_Responses_for_Gilley_Houses.docx | DOCX document | |
| Site_Walk_Notes_-_Attendance_Sheet.pdf | ||
| 2._SOW_Gilley_Houses.docx | DOCX document | |
| Amendment_0001.docx | DOCX document | |
| 9._Contractor_Security_Pamphlet.pdf | ||
| 8._FEP_March_ARB_June_2016_Signed.pdf | ||
| 1._Gen_Wage_Decision_8-17-18.txt | TXT text file | |
| Gilley_Houses_-_Floorplans.pdf | ||
| SF_1442_-_Solicitation.docx | DOCX document | |
| Map_and_Detailed_Drawings.pdf | ||
| 4._Carpet_Design_Samples.pdf | ||
| 7._Specifications.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| PDPG 18-0109 | Project Title: | ||
| Installation of New Carpet and Asbestos Abatement of Gilley Houses 238, 239, 240, 241, 243,249, 250, 381, 382 and 383. | Solicitation / Contract Number: FA466418B0005 |
| Line Number | (To be completed by Project Construction Inspector) | (To be completed by Contract Administrator) | ||||||||||||||
| Number of Copies Required | Remarks | |||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certification of Compliance | Detail Drawings | Samples | Color Selection | Manufacturer's Recommendation | Manufacturer's Warranty | Catalog / Product Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data / MSDS | Test Reports | Field Reports | Required Submission Date |
fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
Submittal Numbers fergusog: Enter the Submittal Number
| Date Contractor | ||
| Notified | Contractor Resubmittal |
fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date
(MM/DD/YY)
Approved fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
| Asbestos Abatement UFGS-Section 02 82 13.00 10 | |||||||
| 1.5 SUBMITTALS | |||||||
| ASBESTOS WORK PLAN | |||||||
| SD - 02 SHOP DRAWINGS | |||||||
| Detailed Drawings | 1 | NLT 5 days after MOD | |||||
| SD - 03 PRODUCT DATA | |||||||
| Asbestos Management Plan | 1 | NLT 10 days after MOD | |||||
| Respiratory Protection Program | 1 | 1 | NLT 10 days after MOD | ||||
| Qualifications | 1 | 1 | NLT 10 days after MOD | ||||
| Licenses, Permits and Notification | 1 | 1 | NLT 10 days after MOD | ||||
| Encapsulants | 1 | NLT 10 days after MOD | |||||
| Asbestos Hazard Abatement Plan | 1 | 1 | NLT 10 days after MOD | ||||
| Cleanup and Disposal | 1 | NLT 5 days after completion | |||||
| Asbestos Waste Shipment Records/Delivery Tickets | 1 | 1 | NLT 5 days after completion | ||||
| SD-06 TEST REPORTS | |||||||
| Exposure Assessment and Air Monitoring | 1 | 1 | NLT 5 days after completion | ||||
| Local Exhaust System | 1 | 1 | NLT 5 days after Completion | ||||
| SD - 07 CERTIFICATES | |||||||
| Local Exhaust System | 1 | 1 | NLT 10 days after MOD | ||||
| Medical Surveillance Requirements | 1 | 1 | NLT 10 days after MOD | ||||
| Encapsulants | 1 | 1 | NLT 10 days after MOD |
| PROJECT RENOVATION | |||||||||
| MATERIALS | |||||||||
| Carpet Tile 50cm style #146720250 9335 Pearl Grey or equivalent | 1 | 1 | 1 | 1 | 1 | NLT 10 days after NTP | |||
| Carpet Tile Cove Base Color 9335 Pearl Grey or equivalent | 1 | 1 | 1 | 1 | 1 | NLT 10 days after NTP | |||
| LVT Floor Tile: Level Set 50CM A00211 Washed Maple or equivalent | 1 | 1 | 1 | 1 | 1 | NLT 10 days after NTP | |||
| Vinyl Cove Base, Color / Design to match LVT | 1 | 1 | 1 | 1 | 1 | NLT 10 days after NTP | |||
| CARPETING UFGS SECTION 09 68 00 | |||||||||
| SD - 02 SHOP DRAWINGS | |||||||||
| Installation Drawings | 1 | NLT 10 days after NTP | |||||||
| SD-03 PRODUCT DATA | |||||||||
| Carpet | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| Moldings | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| SD - 04 SAMPLES | |||||||||
| Carpet | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| Moldings | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| SD - 07 CERTIFICATES | |||||||||
| Warranty | 1 | NLT 5 days after Final | |||||||
| SD - 08 MANUFACTURER'S INSTRUCTIONS | |||||||||
| Surface Preparation | 1 | NLT 5 days after NTP | |||||||
| RESILIENT FLOORING UFGS SECTION 09 65 00 | |||||||||
| SD - 02 SHOP DRAWINGS | |||||||||
| Resilient Flooring and Accessories | 1 | NLT 5 days after NTP | |||||||
| SD - 03 PRODUCT DATA | |||||||||
| Luxury Vinyl Tile | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| Wall Base | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| SD - 04 SAMPLES | |||||||||
| Resilient Flooring and Accessories | 1 | 1 | 1 | NLT 5 days after NTP | |||||
| SD - 08 MANUFACTURER'S INSTRUCTIONS | |||||||||
| Surface Preparation | 1 | NLT 5 days after NTP | |||||||
| Installation | 1 | NLT 5 days after NTP | |||||||
| SD - 10 OPERATION AND MAINTENANCE DATA | |||||||||
| Resilient Flooring and Accessories | 1 | NLT 5 days after NTP | |||||||
| ADDITIONAL REQUIREMENTS | |||||||||
| Contractor's Work Plan | 1 | NLT 5 days after NTP | |||||||
| Contractor's Quality Assurance Plan | 1 | NLT 5 days after NTP |