MATOC Questions (FA465922R0003) - 31 Aug 22.pdf

PDF 123 KB Posted

Attached to
Multiple Award Task Order Contract for Construction Projects Federal contract opportunity
Solicitation number
FA465922R0003
Issued by
Department of the Air Force Air Mobility Command

About this file

This document outlines a Multiple Award Task Order Contract solicitation for construction projects at Grand Forks Air Force Base. The solicitation is a 100% small business set-aside with a five-year ordering period and $75 million maximum value of task orders to be awarded. Offerors must submit pricing for a demonstration project between $500,000 to $1 million by September 15th, 2022 for evaluation purposes only. The contract has a minimum guarantee of $1,000. Offerors should provide past performance on projects over $300,000 and have at least $9.9 million in bonding capacity. The pre-proposal conference was on August 22nd and the demonstration project involves renovations to building 242.

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Task Order Contract for Construction Projects, newest first.
File Type Posted
Solicitation Amendment FA465922R00030004 SF 30 (1).pdf PDF
2E JFSD210011 Building Wage Determination Feb 2022.pdf PDF
MATOC Questions (FA465922R0003) - 23 Sep 22.pdf PDF
Solicitation Amendment FA465922R00030003 SF 30.pdf PDF
(Conformed Copy) FA465922R00030003.pdf PDF
Solicitation Amendment FA465922R00030002 SF 30 (1).pdf PDF
2A JFSD210011 Demonstration Project Specifications Aug 2022 v2.pdf PDF
6. CSI Breakdown Example 16 Sep 22.pdf PDF
5. MATOC Questions (FA465922R0003) - 16 Sep 22.pdf PDF
Demonstration Project_ Room 112A Electrical Room Photos.pdf PDF
Solicitation Amendment FA465922R00030001.pdf PDF
Demonstration Project_ Room 8 Mechanical Room Photos.pdf PDF
Demonstration Project_ Room 7 Comm Room Photos.pdf PDF
Solicitation - FA465922R0003.pdf PDF
2B JFSD210011 Demonstration Project Drawings Jul 2021.pdf PDF
4 JFSD210011 Past Performance Questionnaire MATOC.pdf PDF
3 Past Performance Reference.docx DOCX document
2D JFSD210011 Demonstration Project Bid Schedule Jul 2021.pdf PDF
2A JFSD210011 Demonstration Project Specifications Jul 2021.pdf PDF
JFSD210011 MATOC Technical Specifications - Aug 22.pdf PDF
2C JFSD210011 Demonstration Material Submittal Schedule Jul 2021.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Question Answer

The solicitation states a Bid Bond is required. Given that no project will be awarded would a letter from our surety stating our ability to bond suffice this requirement?

Yes, this will be acceptable. For further information, see FAR 52.228‐1 Bid

Guarantee.

Please provide clarification, or an example, of the size of the Past Performance projects (pages 54‐

55). It is stated that the project experience provided should range from $2,000 ‐ $9.9M, but also states it should be equal to or greater than $300,000.

The selected contractors that will be awarded the MATOC contract should be prepared to take on projects that range from $2K ‐ $9.9M. However, as the majority of the projects that will be awarded are anticipated to be over the SAT ($250K), the government would like offerors to submit past performance information for evaluation purposes that is over $300K.

The east and south exterior canopies don’t have fire protection. Sheet FX101 does not show the fire protection system extend to protect these areas. Does the fire protection need to be extended to protect these canopies?

Qualified Fire Protection Engineer (QFPE) shall determine this requirement per UFC

3‐600‐01

Will the Government accept CPARS ratings in lieu of PPQs so we will not burden our government clients to repeat evaluations already completed?

The government is looking into this question and a response will be provided at a later date.

5 Is the schedule included in the 40‐page limitation? Yes it's included.

6 Please provide a sign in sheet from the pre‐proposal/site visit

The sign‐in sheet was emailed out to all parties in attendance. If you did not receive it, please email carly.larson@us.af.mil

7 Please provide any information provided at the pre‐proposal/site visit

The pre‐proposal site visit consisted of viewing the demonstration project location.

Some areas were not accessible and photos were provided in Amendment 1.

Contractors were advised to read through Sections L and M of the solicitation carefully to ensure proper proposals are submitted for evaluation. No questions were answered on site; contractors were directed to submit questions in writing by

3 business days after the pre‐proposal site visit, IAW the solicitation

Construction material costs have increased significantly in recent times, and the construction material market continues to be volatile and unpredictable. It is anticipated that construction material costs will continue to increase into the foreseeable future; however, it is not possible to predict how much prices will increase by the time the task order is awarded, the design effort is complete, and/or construction commences. To protect both the Government and the Contractor, would the Government consider incorporating FAR 52.216‐4 Economic Price Adjustment‐Labor and Material or a substantially similar and suitable price adjustment clause in the FOPR and resulting task order to allow for an adjustment to the FFP in the event of significant and unpredictable material costs fluctuation during the term of the task order? Inclusion of this clause will protect and benefit the Government because the offered prices will not need to account for the elevated risk of unknown future material cost escalations.

If the need for this clause is determined to be necessary during Fiscal Year 23 (Oct 1 ‐

Sep 30), the government will consider adding this clause as a modification to the base contract or include this clause in each released Task Order Proposal Request.

Will the government accept projects that are considered 50% complete for the general requirement construction section? Do submitted projects for past performance have to be 100% complete? If not, what percent completion do they need to have achieved at the time of proposal submittal? Submitted projects for past performance evaluation shall be 100% complete.

Will the government please provide a sample CSI breakdown format/sheet for the requirement in

Project Content 48 Divisions of the Construction Specification Institute (CSI) evaluation (Subfactor

1) See attachment CSI Breakdown Example.

Please consider projects in a 10‐year range instead of the current six‐year range in order to allow the offeror to provide our best portfolio of projects for consideration

The government is not going to increase the range for the Past Performance

Information. Please see Section L ‐ Part III Past Performance

12 Does this IDIQ MATOC require awardees to bid every task order Please see Section L‐3(e) ‐ Annual Performance Review ("Off‐Ramp)

For the sample project, please provide the work week model expected or anticipated to be used.

Monday through Friday, 8:00AM to 5:00PM (regular normal working hours)

This submittal is due right after Government year‐end. Please consider allowing CPAR ratings and/or previously submitted PPQ forms (standard USACE/NAVFAC) to be included in the submittal in order to alleviate the undue burden of re‐evaluating projects on our already overworked federal clients during this time Please see response on question #4.

Proposal Submittal: Per page 53 of the solicitation, please confirm that Parts I, II, and III shall be submitted as separate .pdfs when submitting our proposal via email Yes, please submit each volume as a separate PDF

Section B‐ Supplies or Services & Prices or Costs is located on page 4 of the solicitation. Should we include a blank copy of page 4 and submit it with our proposal along with a completed

Demonstration Bid Schedule and Evaluation/Award Criteria form that was included as an attachment labeled “2D JFSD210011 Demonstration Project Bid Schedule Jul 2021

No ‐ the contractor can solely use "2D JFSD210011 Demonstration Project Bid

Schedule Jul 2021" to submit their pricing information for the Demonstration

Project.

Questions and Answers for MATOC FA465921R0003 (Version Date: 31 Aug 22)

17 Are cover letters allowed to be submitted?

Yes, however, please be advised that this will be counted towards the page limitation.

Duplication of Projects: Can a project submitted for Subfactor 1 also be submitted under

Subfactor 2 if it meets the criteria for both? Yes

On page 55 of the solicitation, under section ii. Federal, State, Local Government and Commercial

Contracts (Subfactor 2), it is stated that we are to include, “no less than one (1) but not more than three (3) construction projects of varying disciplines equal to or greater than $300,000 each in scope and magnitude on DOD military installations, Homeland Security, the Department of

Veterans Affairs (VA), other Federal Government agencies, State and local government agencies and commercial customers, within 5 years of release of this solicitation. The Department of

Defense includes but is not limited to U.S. Department of the Army, U.S. Department of the Navy, U.S. Department of the Air Force, and U.S. Space Force.” However, in Section M on page 66, subsection B. Federal, State, Local Government and Commercial Contracts (element 2‐‐see section L‐2.3): “The contractor must provide a minimum of one (1) but not more than three (3) construction projects showing experience of varying disciplines equal to or greater than

$300,000.00 each on DOD military installations, Homeland Security, or the Department of

Veterans Affairs (VA) within the last five (5) years. The Department of Defense includes U.S.

Department of the Army, the U.S. Department of the Navy, and the U.S. Department of the Air

Force.” In Section M, “other Federal Government agencies, State and local government agencies and commercial customers” was left out. Please confirm that we are allowed to use projects from other Federal Government agencies, State and local government agencies and commercial customers, such as the General Services Administration, National Park Service, etc. Yes

Per page 56 of the solicitation, “The offeror shall provide proof from the offeror's bonding company that their firm has, as a minimum, $9,999,999.00 in available bonding capability in accordance with Contract Clause FAR 52.228‐1.” Can this proof be in the form of a Bondability

Letter issued by our bonding company? Also, please confirm where our Bondability Letter should be included with our proposal. Should we include it with Part I or with Part III?

Question Part 1 ‐ See response on question #1

Question Part 2 ‐ Include the "Bondability Letter" with Part 1 ‐ Price Proposal

RFI Due Date Extension: We respectfully request an extension to the due date to ask RFIs so that our subcontractors have enough time to submit questions to us after the site visit The due date to submit questions has been extended; see Amendment 1.

Division 2 Heading: On page 2 of the specifications in the Table of Contents, the Division 2 heading is listed as “Division 2‐ Site Work”. Should the heading be changed to “Division 2‐ Existing

Conditions? Please see revised MATOC Demonstration Project Specifications (Aug 2022).

Executive Summary: On page 55 of the solicitation, subsection L‐2.4 #4, “Technical proposals shall be limited to 40 pages excluding the Executive Summary and the Sample project specifications.”

We cannot locate any instructions regarding an “Executive Summary” on page 53 Section PART II

Technical. Could you please clarify what information you would like us to provide?

The name, location, and mission of your company. A description of your company, including management, advisors, and brief history. Your product or service, where your product fits in this market, and how your product compares or differs from competitors in the industry.

24 Will this contract contain Controlled Unclassified Information (CUI)?

The government is looking into this question and a response will be provided at a later date.

DFARS 252.204‐7012 states that contractor shall implement NIST 800‐171. Part of being compliant with NIST 800‐171 is a self‐assessment. What is the required self‐assessment score for this contract?

The government is looking into this question and a response will be provided at a later date.

Will this contract contain DFARS 252.204‐7020? If this contract will contain DFARS 252.204‐7020, will 319 CONS be verifying the contractor Supplier Performance Risk System (SPRS) scores?

The government is looking into this question and a response will be provided at a later date.

Sheet ET101 Note 2 is asking for a new fire alarm panel and connecting to existing devices. In the last year there have been projects that were bid to change out the Simplex panel like this one to new Monaco system. Can we can keep the fire alarm panel Simplex or do we need to install a

Monaco System? Is new control panel to be MONACO MAP‐X? Monaco is required.

Can we please see a picture of the electrical Panels in Rm 112A so we can add and move this equipment in this room? Photos provided in Amendment 1.

29 What is the period of performance for the demonstration project? 150 days

For the demonstration project, Sheet FX101 calls for head replacement in areas. Are there as‐ builts available? Would these show number of heads per area and ceiling type? As‐builts for sprinklers are not available.

31 For the locker room, 133, what type of corrosion resistant pipe is required?

Qualified Fire Protection Engineer shall determine proper piping per code requirements.

For the demonstration project and assembling our schedule, What would be the notice to proceed date? Notice to Proceed date of 1 March 2023

For the demonstration project, are we to assume the building will be occupied during the construction? Facility will be vacant, except for one section that is minimally manned.

Technical Approach Narrative (Sub‐Factor 2), States the offer must provide a narrative that reflects an approach consistent with the Architectural Compatibility Guide (ACG). a. If we should be using the ACG, is this guide titled the Grand Forks AFB “Whole Building Design Guide”? b. Can you please provide a copy?

A. No. B. Use the folloiwng website to download the installation facility standards:

https://www.wbdg.org/ffc/af‐afcec/installation‐facilities‐standards‐ifs/grand‐forks‐ afb‐ifs

For the Technical Approach Narrative (Sub‐Factor 2), are you looking specifically for information on the demonstration project only, or for the overall MATOC? Demonstration Project Only

For the Technical Approach Narrative (Sub‐Factor 2), is the reference to “this project” a reference to the demonstration project only, or the overall MATOC?

Demonstration Project Only

37 Can you please consider adding FAR clause 16.203‐1 to the MATOC? See response on question #8

NIST 800‐171 security requirement 3.4.8 calls for least functionality authorized software / whitelisting. Can you please provide a list of the whitelisted or authorized software? a. Are we required to implement application whitelisting before contract award? The government is looking into this question and a response will be provided at a later date.

Will this contract require submission of a System Security Plan in accordance with NIST 800‐171

Section 3.12.4?

The government is looking into this question and a response will be provided at a later date.

Please confirm/clarify that the project viewed at the site visit, and in the solicitation, will not be awarded The demonstration project will not be awarded.

41 Please confirm/clarify that we are only to provide a lump sum for the project as a whole

The bid schedule (Attachment 2D) has two CLINs (001 and 002). Each CLIN must be priced separately and then added together for a total price

42 Can the page limit be increased to 65 pages for the Part II‐Technical? The limitation has been increased from 40 pages to 50 pages.

43 Who is the controls contractor on the GFAFB? Honeywell

44 Do drawings contain full building fire suppression as‐builts? If not, can a full set be provided? There are no fire suppression as‐builts.

45 Will full time supervision be required for the duration of the project?

Prime contractor will supply superintendent, government will provide escort into controlled areas of facility with notice.