Addendum - Quantity Information 080912.pdf

PDF 49 KB Posted

Attached to
Repair Secondary South Sewer Lagoon Federal contract opportunity
Solicitation number
FA4659-12-R-0013
Issued by
Department of the Air Force Air Mobility Command

About this file

Addendum to Estimated Quantitys

View the file

Other files for this federal contract opportunity

Other files attached to Repair Secondary South Sewer Lagoon, newest first.
File Type Posted
Revised specifications.pdf PDF
Site Visit Sign In Sheet.pdf PDF
Lagoon Transfer Structure-C-27.TIF TIF image
Amendment 0002.pdf PDF
Structure2.JPG JPG image
Question and Answers Sewer Lagoon.pdf PDF
Lagoon Transfer Structure Layout.TIF TIF image
Lagoon Transfer Structure-C-12.TIF TIF image
Lagoon Transfer Piping.TIF TIF image
Structure3.JPG JPG image
Structure1.JPG JPG image
Amendment 0001.pdf PDF
JGAR200345 Material Submittal Schedule.pdf PDF
Solicitation Cover Letter.doc.pdf PDF
Financial Institution Reference Sheet.doc DOC document
JGAR200345 SPECIFICATIONS.pdf PDF
FA4659-12-R-0013.doc.pdf PDF
JGAR200345 DRAWINGS.pdf PDF
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx DOCX document
Attachment 3 - Climatological Data.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item Quantity Units Notes

Existing Riprap Removal ‐ 1.31' Depth 2722 CY

Assuming 30% Loss ‐820 CY

Salvaged Riprap Meeting Spec. 1902 CY

Riprap Placement ‐ 1' Depth 2080 CY

Salvaged Riprap Meeting Spec. ‐1902 CY

Contractor Furnished Riprap 178 CY

Item Quantity Units Notes

Common Excavation Total 956 CY

Topsoil Removal ‐733 CY

Common Excavation 223 CY

Due to cutting the slope of the dike under the fabric to be a 4:1

The Details on Sheet C‐302 are over exaggerated to give a better view of what is taking place. The contractor will remove 10‐11 ft. of riprap, separate out the material not in spec., which is estimated to be around 30%.

Then place back a 12 in. thick section of riprap in the same location. THe reason for the hatching underneath the riprap in the detail is to show that there might need to be a little bit of fill underneath the riprap in order to bring it up so the top of the riprap matches the existing riprap height. This is due to the average depth of the riprap being 1.31 ft. and only putting back 1 ft.NOte that this is just average, some areas will need it and others will not. The 12 in. riprap section wil lthen match the topsoil that is being graded at a 4:1 from the top of the dike. There will be some material excavated out to anchor the fabric but that will be palced back in the same trench.

JGAR200345 Maintain Sewage Lagoon ‐ Secondary South

RIPRAP BREAKDOWN

* Note: These quantities represent the government estimate and are for informaiton purposes only, Contractor's are to verfiy amounts needed. No modifications will be completed on these items.