This is a Questions and Answers document for solicitation FA465426R0006, addressing key contracting requirements for small business prime contractors responding to the pavement repair opportunity at Grissom Air Reserve Base.

The document clarifies three critical requirements for proposal submission: small business contractors must strictly comply with FAR clause 52.219-14 regarding subcontracting limitations and small business performance requirements; the prime contractor's past performance will be the primary basis for evaluation under Section M, with subcontractors evaluated only during the responsibility determination phase; and offerors cannot rely on proposed subcontractors' experience, qualifications, or past performance to meet technical capability or past performance evaluation criteria. The document confirms no anticipated amendments or clarifications are expected prior to the June 30, 2026 proposal deadline.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA465426R0006 – Grissom ARB Pavement Repair, Sustainment, and Construction Questions and Answers.

1. As a small business prime contractor responding to FA465426R0006, are there any specific limitations on subcontracting or small-business performance requirements that offerors should pay particular attention to when proposing significant subcontractor participation?

Yes. See FAR clause 52.219-14 and it is strictly enforced.

1. Will the Government evaluate the experience and past performance of proposed subcontractors when assessing overall technical capability and past performance?

The prime contractor’s past performance will be evaluated under Section M. All subcontractors will also be evaluated for the Determination of Responsibility for the prospective awardee.

1. For proposal evaluation purposes, may offerors rely upon the experience, qualifications of key personnel, and past performance of proposed subcontractor team members as part of their submission?

No.

1. Are there any anticipated amendments, updates, or additional clarifications expected prior to the proposal due date that offerors should be aware of?

No.