Pre-Proposal Site Visit Meeting Minutes.doc

DOC document 31 KB Posted

Attached to
RECOVERY-- NZAS062004 - Repair Missile Alert Facility Asphalt
Solicitation number
FA462609R0011
Issued by

About this file

Site Visit Meeting Minutes

View the file

Other files

File Type Posted
Amendment 2.doc DOC document
QUESTION RESPONSE.docx DOCX document
2 QUESTION RESPONSE.docx DOCX document
Solicitation.doc DOC document
Attach 5 Wage Determination.docx DOCX document
CHIP SEAL PDFS.zip ZIP file
Attach 6 Past Performance.docx DOCX document
Attach 2 Submittal Schedule.xls XLS spreadsheet
Chip Seal Specs.zip ZIP file
Attach 3 Schedule of Drawings.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-PROPOSAL CONFERENCE / SITE VISIT

REPAIR/CHIP SEAL ASPHALT MAFS

FA4626-09-R-0011

21 Apr 2009 / 8:00 am

· PROJECT: Repair Chip Seal Asphalt at 15 MAFs

· INDIVIDUALS IN ATTENDANCE: Aaron Jewett, Project Engineer, 341 CES; Larry Weimer, Project Inspector, 341 CES; Douglas Welsh, Century Companies, Inc.; Deborah Lacy, Contract Administrator, 341 CCS.

· PERFORMANCE PERIOD: 240 calendar days with winter exclusion period from 1 November to 1 April. No chip sealing allowed between 1 September and 30 May.

· LIQUIDATED DAMAGES: $658.48 per day

· PAST PERFORMANCE: Past/Present Performance is due 1400 MST, 8 May 09, but NLT 1400 MST, 11 May 09.

· CLOSING DATE: 11 May 2009 at 1400 hours

· REPRESENTATION & CERTIFICATION: Fill them out completely and make sure they are submitted along with your proposal. Online Representations and Certifications Application (ORCA).

· REMINDERS:

· Any questions regarding Specs and Drawings must be submitted in writing NLT 1400 hrs, 27 Apr 09. FAX: 406-731-3748

· All amendments and answers to any questions will be posted on the internet (FBO http://www.fedbizopps.gov/)

· Read sections L & M thoroughly, pay attention to dates.

· Make sure you have a DUNS & CAGE CODE number—see website (sec I)

· Magnitude of project: $500,000 -$1,000,000

· Discuss specs and drawings: There were no immediate requests for clarification.

· Went to Charlie 1, did not enter site, and looked around outside the fence.

Meeting is adjourned.