Whiteman AFB Pickleball SOW 15-8-24.pdf
PDF 105 KB Posted
- Attached to
- FY24 Pickleball Court
- Solicitation number
- FA462524R0009
About this file
This document is a Statement of Work (SOW) for the resurfacing and conversion of an existing activity court into a pickleball court at Whiteman AFB in Missouri. The key requirements include:
The contractor shall execute a complete project to resurface the existing 40' x 50' activity court under the Alpha Warrior rig pavilion and convert it into a practice pickleball court. This includes general crack-filling, patching, application of colored acrylic surfacing, installation of a 4' divider net, and painting of regulation pickleball playing lines. The contractor will also have the option to pour an additional 4" concrete slab on both ends of the court. The facility must be returned to a complete and usable state upon project completion.
The related federal contract opportunity is Solicitation FA462524R0009 for the "FY24 Pickleball Court" project at Whiteman AFB, issued by the Department of the Air Force Global Strike Command. The contract will resurface and convert the existing activity court into a pickleball court as detailed in the provided SOW.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Resurface Activity Court Under Alpha Warrior Rig Pavilion – Convert to Pickleball Court
Revised: 15 August 2024
1. PROJECT INFORMATION:
A. PROJECT TITLE: Resurface Activity Court Under Alpha Warrior Rig Pavilion – Convert to Pickleball Court
B. PROJECT LOCATION: Structure 20014, Whiteman AFB, MO, 65305
2. DESCRIPTION OF PROJECT:
A. PROJECT BACKGROUND: Resurface existing activity court under Alpha Warrior rig pavilion and convert it into a practice pickleball court at Whiteman AFB, MO, 65305. This project includes general crack-filling repairs and patching, application of a colored acrylic surfacing, and pickleball court conversion.
B. CONSTRUCTION SCOPE: The contractor shall execute the project as shown in this SOW.
3. GENERAL PROVISIONS:
A. The contractor shall supply all labor, materials, transportation, equipment, and supervision to provide a complete, finished, functional product.
B. Pre-Construction Site Survey: The contractor, prior to the start of any on site construction activities, shall conduct a condition survey with the construction inspector, after which the contractor shall note the condition of trees, shrubs, grassed areas, concrete, and any structural damage that may exist immediately within or adjacent to work site.
4. SPECIFIC REQUIREMENTS:
Resurface activity court under Alpha Warrior rig pavilion (40’ X 50’) and convert into one practice pickleball court. Install 4’ divider net for pickleball. The existing fence and gates surrounding the courts are adequate and will remain.
A. Mobilization to the site
B. Prepare the site – Scrape the court surface of all dirt debris and loose material.
C. Prepare the site – Pressure wash courts for major mildew and debris.
D. Divider Net Posts – Dig and set one set of pickleball net posts in concrete.
E. Divider Net – Provide non-permanent, rolling 4’ divider net with brakes for pickleball. Net shall be approved by the government before purchase.
F. Sanding – Machine-sand the surface of the court as necessary to smooth and repair any uneven areas including remaining fixtures (e.g. bolts, poles) from previously used equipment.
G. Crack Fill – Apply outdoor court grade patching materials to all low spots and/or cracks to bring each area flush with surrounding gravel.
Patching – Using outdoor, court-grade patch compounds:
A. One application will be made to each low spot/crack.
B. Cover and fill any rough areas of asphalt.
C. The edges of all patches will be scraped or ground smooth so that patches are not visible through the finished surface.
D. Light sanding on edges to smooth down
H. Leveling Course – Apply one coat of acrylic resurfacer with sand over the entire surface of the courts with a broad squeegee according to manufacturer’s recommended coverage rates.
I. Texture and Finish Courses – Apply two successive coats of outdoor-grade filler coat (sand-filled acrylic color coating) to the entire area of the courts with a broad squeegee according to manufacturer’s recommended coverage rates.
J. Finished Color – Will be owner’s choice of any two manufacturer’s standard colors (separate colors for non-volley zone and service area).
K. Lines – Paint one set of regulation 2”-wide white playing lines for pickleball.
L. Clean-up – Remove all excess materials and debris from the job after completion of the work. Repair all portions of the facility damaged during construction, including exterior grounds, to provide a complete and usable facility. If fencing must be removed during construction, it shall be returned to its original state upon project completion.
M. Option 1 – Pour and finish additional 4”-deep slab of concrete measuring approximately 40’ X 4’ on both ends of the existing activity court. Concrete shall not extend past pre-existing fence perimeter.
N. The facility manager must be contacted for coordination before the start of any repairs. The repair schedule may include after hours and weekend time periods.
O. Any exceptions to this performance work statement must be detailed in the contractor proposal.
5. ATTACHMENTS:
A. Existing Concrete Slab Overview
File details come from the government source that posted it. Updated .