Site Visit_Q&A Dated 25 January 2018

View the file

Other files for this federal contract opportunity

Other files attached to Lime Sludge Removal, newest first.
File Type Posted
18R0004_Amend_2_Prior_Year_Lab_Analysis.pdf PDF
18R0004_Amend_Acknowledge.pdf PDF
18R0004_Atch_3_Spent_Water_Permit.pdf PDF
18R0004_Atch_4_Clause_Full_Text_Info.pdf PDF
18R0004_Atch_1_SOW_5Jan18.pdf PDF
18R0004_Atch_2_Bid_Schedule.xlsx XLSX spreadsheet
18R0004_Combo_9Jan18.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEMORANDUM FOR RECORD

Subject: Lime Sludge Removal Site Visit/ Q&A

Contract/DO Number: FA462518R0004 Modification

Number:

Signature Title

Contract Specialist

Description:

Attendees:

Ted Anderson, KAT + 1 Disable, tedanderson@iland.net, (660)909-6834 DarDen Rhodes, RUFlogistics, darden@rvflogistics.com, (314)583-5999 Lindell Rhodes, RUFlogistics, (660)537-2585 Jerry Brown, Royal Hugh Septic, RoyalFlushSeptic2016@gmail.com, (785)521-0033 Brad Leonard, 417 Services, brad@417Services.com, (417)464-5588 Julie Leonard, 417 Services, (417)880-9888 Brian Carpenter, Ace Pipe, bcarpenter@acepipe.com, (816)241-2891 Timothy Walters, Ace Pipe, (811)719-0469 Mike Dale, Environmental Works, mdale@environmentalworks.com, (816)605-8977

During site visit the contractors were escorted to the water treatment plant to see the working area for the lime sludge removal contract. During this visit the following questions were asked:

1. When does the current contract expire?

The current contract ends on 31 March 2018.

2. What is the percentage of sludge?

Refer to the SOW.

3. Will the contractor need their permit before the award?

The contractor shall acquire all necessary permit(s) after the award. Once the permit(s) are acquired, the contractor shall provide a copy to the Government.

MEMORANDUM FOR RECORD

11.0.1.20130826.2.901444.899636

TextField1: Lime Sludge Removal Site Visit/ Q&A
TextField2: FA462518R0004
TextField3:
SignatureField1:
DropDownList1: Contract Specialist
TextField4: Attendees:

Ted Anderson, KAT + 1 Disable, tedanderson@iland.net, (660)909-6834 DarDen Rhodes, RUFlogistics, darden@rvflogistics.com, (314)583-5999 Lindell Rhodes, RUFlogistics, (660)537-2585 Jerry Brown, Royal Hugh Septic, RoyalFlushSeptic2016@gmail.com, (785)521-0033 Brad Leonard, 417 Services, brad@417Services.com, (417)464-5588 Julie Leonard, 417 Services, (417)880-9888 Brian Carpenter, Ace Pipe, bcarpenter@acepipe.com, (816)241-2891 Timothy Walters, Ace Pipe, (811)719-0469 Mike Dale, Environmental Works, mdale@environmentalworks.com, (816)605-8977

During site visit the contractors were escorted to the water treatment plant to see the working area for the lime sludge removal contract. During this visit the following questions were asked:

1. When does the current contract expire?

The current contract ends on 31 March 2018.

2. What is the percentage of sludge?

Refer to the SOW.

3. Will the contractor need their permit before the award?

The contractor shall acquire all necessary permit(s) after the award. Once the permit(s) are acquired, the contractor shall provide a copy to the Government.