INITIAL SITE VISIT
FA4625-16-R-0013
Metal Slat Fencing IDIQ
SIGN-IN SHEET
28 July 2016
NAME ORGANIZATION E-MAIL TELEPHONE #
Theodore Church-Reeves 509 CONS theodore.churchreeves@us.af.mil (660-687)-5415
Brad Phillips 509 CES bradley.phillips.6@us.af.mil x-6374 David Raley Vazquez Comm. Ctr davidr@vazquezcc.com 816-729-0630 Brian Raley IEC brianr@iec8a.com 660-687-0401
Tom Corbett IEC N/A 660-287-0568
Daniel Bond Matai Services Unknown. 816-456-8542
Ryan Bell Basteel Perimeter Systems ryan@basteel.com 765-654-5225
SSgt Lacaprucia 509 CES michael.lacaprucia@us.af.mil x-3417
Randy Eckert RCI reckert@rcicon.com 660-429-0100
Randy Ball CR Fence N/A 660-463-2597
Initial Site Visit Notes:
Brick columns will remain a Vertical Foot UOM only. Column measurements will vary based on location of work.
New fencing projects will be steel fencing only if possible.
Brick post expected to be for re-build of existing areas only.
Post in center of fence for spans over 8’ for structural integrity is acceptable.
Seed Project:
Posts in the trash area will remain.
Pipe will be removed on gates next to facility.
Brick columns will not be replaced.