FA4625‐16‐R‐0013
Attachment 1 1
STATEMENT OF WORK
FOR
CONSTRUCT/REPAIR FENCE
Whiteman AFB, Missouri 12 August 2016
Attachment 1 2
SUMMARY OF WORK
PART 1 – GENERAL
1. SUMMARY
1.1 DESCRIPTION: Contractor shall furnish all design, labor, equipment, material, manufactured articles, transportation, supervision, and all else necessary to perform all operations in connection with successfully completing task orders under the contract construct/repair fence IDIQ specified herein, as required per below specifications and referenced documents, and as shown on respective project drawings. The Contract will govern in the case of any conflicts with this section.
1.2 DEFINITIONS:
1.2.1 Contracting Officer: The term Contracting Officer refers to the Contracting Officer or his/her contract specialist, and the term Contractor refers to the general contractor. The general contractor is responsible for all subcontractors, suppliers, and consultants under his employ.
1.2.2 Contracting Officer’s Representative: The Base Civil Engineer or his authorized representative is designated as the Contracting Officer's Representative (COR) (Construction Manager), for the purpose of technical surveillance and evaluation of the work performed under this contract.
This designation in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract.
2. LOCATION: The project sites will be located at Whiteman AFB, Missouri.
2.1 WHITEMAN AIR FORCE BASE (WAFB) is located approximately three (3) miles south of Knob Noster, Mo. The specific project location is indicated on drawings accompanying each task order issued against this contract.
3. DESCRIPTION OF WORK: The scope shall include, but not be limited to the following descriptions. Not all items will be needed or specified in a particular project.
3.1 DEMOLITION: Note the term demolition includes haul and disposal, OR return to the government, of all demolished/removed material.
3.1.1 Remove Chain Link Fence: Work shall include labor and materials to demolish, haul, and return to the government various heights of chain link fence fabric (no higher than 10 feet), Demo posts and footings. Replace topsoil and seed/mulch. Location will be as shown on the individual task order.
3.1.2 Demo Miscellaneous Fence: Work shall include labor and materials to demolish, haul, and dispose of numerous varieties of fence (chain link, wooden board-on-board privacy, composite privacy, welded/woven wire, barbed wire, etc.), demo posts and footings. Replace topsoil and seed/mulch. Location will be as shown on the individual task order.
Attachment 1 3
3.2 CONCRETE WORK:
Construct Concrete Mow Strip: Concrete curbing along the bottom of a chain link fence.
Work includes surveying, excavation, placing and compacting 6” type II base, forming 24” wide by 4” deep mow strip and placing concrete.
3.3 CONSTRUCT METAL SLAT FENCING:
3.3.1 Materials: In order to match existing slat metal fencing, the Contractor shall utilize brand name/type and color: BASTEEL Perimeter Systems™, “Shadowbox Picket Layout” with square posts, and Bronze (BASF #872T109) color, or equal. If submitting an equal brand name/type or color, the Contractor shall submit specifications, photos/images, and color sample/swatch with the proposal.
3.3.1.1 All fencing components shall have protective galvanized G-90 under coat applied prior to the top coat protection. Then a two-coat, thermo cured paint system consisting of a primer bottom coat and a fluoropolymer top coat shall be applied. Fluoropolymer top coat shall contain not less than 70 percent polyvinylidene fluoride (Kynar 500®/ Hylar 5000®) resin by weight meeting minimum performance requirements of 10 years outdoor exposure of South Florida 45° with less than 5 units color change as per ASTM D2244 and a chalk rating of no less than 8 as per ASTM D4214.
3.3.1.2 Infill pickets 5” minimum in width shall be roll formed from either minimum 0.017” (25 gauge) full hard 80,000 psi or minimum 0.030” (22 gauge) 50,000 psi yield strength steel in accordance with ASTM A653.
3.3.1.2.1 Vertical picket/ infill orientation
3.3.1.2.1.1 Shadow-box (pickets on both faces of rail, 3-7/8” gap, 21 pickets per section)
3.3.1.3 Rails, channels and brackets shall be 0.073” (14 gauge) ASTM A653 high strength
50,000 minimum psi yield steel. A protective galvanized G-90 under coat is applied prior to the thermo cured top coat protection.
3.3.1.3.1 “C” roll formed channel rails 1 ¼” x 1 ½”
3.3.1.3.1.1 Flat square back brackets (to be used with square posts)
3.3.1.3.1.2 Column brackets (to be used on masonry pillars or walls)
3.3.1.4 Contractor shall tool bottom of post at entry to concrete creating a 3/8 inch depth x 1/4 inch width cavity. After concrete has cured 7 days, apply matching sealant to cleaned cavity creating positive drainage away from post. Refer to gate frames for additional notes on the hinging post.
3.3.1.4.1 Square Posts shall have 3.0 mils minimum thickness thermocured fluoropolymer top coat protection
3.3.1.4.1.1 4.0”x 4.0” x 0.120” wall (11 gauge) high strength 50,000 psi minimum yield in accordance with ASTM A500 and shall be zinc coated in accordance with ASTM F1043 type B.
3.3.1.4.1.2 6.0”x 6.0” x 0.250” wall in accordance with ASTM A500 and shall be hot dipped galvanized with a minimum 1.8 ounce per square foot.
3.3.1.5 All gate frames shall meet the same material and performance specifications as sited above. All gate infill or pickets shall conform to the standards specified for pickets and infill
Attachment 1 4 material as sited above. Welding of gate frames and other components, as necessary and recommended by the manufacturer, shall be with silicon bronze welding wire, conforming to AWS A5.7 ERCuSi-A and/or ASME SFA5.7 requirements, as to inhibit corrosion. Perimeter gate frame shall have miter cut corners, welded and ground smooth. Remove all sharp edges from cuts, bends and welding splatter prior to factory finish being applied. All picket or infill materials shall be in-cased on all four sides by perimeter gate frame. Hinges shall be welded to gate frame vertical and clamped around hinging post allowing for field adjustability. Pivot points shall be double sealed bearings. Industrial cane rod shall be supplied on each gate leaf. Provide receiver in ground plane for rod in the closed & fully open positions.
3.3.1.5.1 Single Swing Gate
3.3.1.5.1.1 Gate frame shall be comprised of 2.0”x 4.0” x 0.073” wall (14 gauge) minimum and reinforced with 1.0”x 2.0” x 0.060” wall (16 gauge) minimum high strength 50,000 psi minimum yield in accordance with ASTM A500 and shall be zinc coated in accordance with ASTM F1043 type B. Provide lockable gate latch to allow access from both sides. Industry standard fork latch will NOT be accepted.
3.3.1.5.2 Double Swing Gate
3.3.1.5.2.1 Gate frame shall be comprised of 2.0”x 4.0” x 0.073” wall (14 gauge) minimum and reinforced with 1.0”x 2.0” x 0.060” wall (16 gauge) minimum high strength 50,000 psi minimum yield in accordance with ASTM A500 and shall be zinc coated in accordance with ASTM F1043 type B. Pad-lock ready 1.0” stainless steel industrial slide bolt assembly shall be supplied.
3.3.1.6 Infill fasteners shall be color coated to match infill color. Infill fasteners shall have a minimum pull out tensile strength of 5,500N. Carriage bolts, nuts and bracket screws shall be stainless steel. All other miscellaneous hardware shall be corrosion resistant.
3.3.1.7 Brick column construction shall match existing column color and layout. Bricks shall be 8” and color shall be BL121 or an approved matching color. Mortar color shall be Solomon Grind 30A or an approved matching color.
4. FABRICATION AND INSTALLATION
4.1 Pickets, rails, posts and accessories shall be provided as detailed in shop drawings or as otherwise suggested by the manufacturer.
4.2 The installed system shall be in accordance with the manufacturer’s instructions. The finished fence system shall surpass the vertical and horizontal loads, and infill performance of industrial weight fences under ASTM F2408.
4.3 The jobsite shall be cleaned of excess materials; post-hole excavations shall be scattered uniformly away from posts.
4.4 Contractor shall identify and mark the location of underground utility service or other below grade hazards prior to installation.
4.5 Contractor shall seek the consultation and approval from the manufacturer for footings based on local requirements and other factors such as frost line and soil conditions.
4.6 Gates must be designed per application considering location, elements, security and frequency of cycles. Gate posts shall be per manufacturer’s recommendation and in accordance with applicable codes, standards and acceptable jurisdictional practices.
4.7 Adjusting
Attachment 1 5
4.7.1 Gate: Adjust gate to operate smoothly, easily, and quietly, free from binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that latches and locks engage accurately and securely without forcing or binding.
4.8 Fencing installation shall match that of exisisting slat metal fencing.
5. SUBMITTALS
5.1 Shop Drawing: Site plan showing the layout of the fence location with dimensions, location of gate and opening size, cleared area, elevation of fences and gates, details of attachments and footings as required. Note: footing requirements may vary due to soil conditions, frost line and other local conditions. Consult with jurisdictional authority regarding requirements of local conditions.
5.2 Certifications: Manufacturers material certification shall be in compliance with current ASTM or other applicable specifications.
5.3 Domestic certifications: Made in U.S.A, Buy American Act or otherwise as required.
5.4 LEED certification: Not required for this project.
5.5 There shall be NO material changes proposed to alter the specified system after the acceptance of bids.
5.6 The manufacturers’ literature, steel mill certifications, paint documentation, and shop drawings shall be submitted and approved by Government prior to material shipment or installation.
5.7 Specifying agent shall choose color choice from manufactures’ stock colors.
6. QUALITY ASSURANCE
6.1 Manufacturers Qualifications: Company must have five years of experience specializing in the fabrication, assembly and design of specialty fluoropolymer-coated decorative metal fences, gates and enclosures as utilized by the US Department of Defense.
6.2 Contractor Qualifications: Installer shall have demonstrated successful experience installing similar projects and have a thorough understanding of local conditions, jurisdictional requirements and the necessity to identify under grade hazards and utility services.
7. DELIVERY, STORAGE AND HANDLING
7.1 Upon delivery to either the job site or any other location designated by contractor, verification by recipient shall confirm that all materials were delivered in good condition and that items cosigned are all accounted for.
7.2 Materials shall be securely stored in a manner to provide proper ventilation, drainage and protection from the elements of weather.
7.3 Product shall be handled in a manner to preserve the integrity of the high performance coating.
8. Reserved
Attachment 1 6
9. SITE VISIT:
Contractors are urged to attend the site visit that will be scheduled by Base Contracting prior to the bid opening.
10. SINGLE, PRIME CONTRACT:
The work will be constructed under a single, prime contract.
11. PERFORMANCE PERIODS & NOTICE(S) TO PROCEED:
The performance period for the construction portion of each individual task order will be provided in the task order SOW. At the beginning of the construction performance window, and if all necessary submittals have been approved by the Contracting Officer, the Contracting Officer shall initiate Notice to Proceed to allow actual demolition and construction work to begin.
12. CODES & STANDARDS:
12.1 All construction must be in compliance with the International Building Code (IBC) latest Edition, Department of Defense Unified Facilities Criteria Standards (UFC), all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), and Johnson County, State of Missouri, and Federal standards, codes, and laws or other higher authority documents as applicable. Any discrepancies between code or standards provisions and the contract documents shall immediately be brought to the Contracting Officer’s attention, and the more stringent requirements shall apply unless otherwise directed.
12.2 Contractors shall be responsible for obtaining copies of all items referenced in this document.
Department of Defense criteria can be retrieved at: http://cbbs.spk.usace.army.mil.
13. WORKING HOURS:
Standard working hours are from 7:00 a.m. to 4:00 p.m. Monday through Friday excluding Federal Holidays and the day after Thanksgiving. Contractor requested deviations to this schedule will be considered if it is in the best interest of the government as determined by the Contracting Officer. If the Contractor desires on working hours other than 7:00 am to 4:00 pm, Monday through Friday, he must submit to the Contracting Officer a work schedule at least five working days prior. The schedule shall note the activities planned, the planned hours of work, and the reason for the additional hours so that the construction inspectors can plan their work schedule
14. AIR FORCE BASE ENTRY, REGULATIONS, & RESTRICTIONS
14.1 Conformance with Regulations/Directives: The Contractor shall conform to base regulations and directives pertaining to security, safety, traffic, fire and personnel clearances, insofar as they pertain to the Contractor's activities as directed by the Contracting Officer. Contractor employees and visitors are subject to the same restrictions as government personnel. Some of these are noted in the following paragraphs.
14.2 Smoking: Smoking is permitted in designated, outside smoking areas only. No smoking will be allowed within any base facility. Please see attached Designated Tobacco Policy Letter.
Attachment 1 7
14.3 Seatbelts: The use of seatbelts by all vehicle operators and passengers is mandatory on Whiteman AFB and in the state of Missouri. On Whiteman AFB, vehicle operators and passengers not wearing their seatbelt will be issued a traffic citation and may lose on-base driving privileges. Please see attached Installation Traffic Code Policy letter.
14.4 Firearms/Illegal Drugs: No firearms or illegal drugs are allowed to be brought onto Whiteman AFB. By accepting a vehicle pass, each person gives their consent to a search of their vehicle while it is entering, while on, or while leaving Whiteman AFB. Please see attached Drug Free Workplace policy letter.
14.5 Speed Limit: Unless otherwise posted, the speed limit on base is 25 MPH and in base housing areas and flightline it is 15 MPH. Please see attached Installation Traffic Code Policy letter.
14.6 Cell Phones: Use of hands-free cell phones while driving on an AF installation is required.
Please see attached Installation Traffic Code Policy letter.
14.7 Parking: Contractor vehicles and equipment will be parked in common parking areas or as otherwise approved in writing by the Contracting Officer.
14.8 Foreign National Access: Foreign nationals sponosred onto Whiteman AFB must be vetted and approved pursuant to the attached Policy Regarding Foreign National Access to WAFB memorandum prior to being granted base access.
14.9 Enhanced Security Measures: During elevated force protection levels there may be increased security and more restricted access to Whiteman AFB.
14.10 Additional Information: The following procedures and requirements for construction contractors requiring access, if followed, will assist in reducing delays in gaining access to work areas.
At Whiteman AFB, all commercial vehicles and vehicles larger than half ton pickup trucks will be required to access the base through the LEMAY gate only.
Upon arrival at a gate, all vehicle occupants will be required to show identification. A pictured identification such as a driver’s license will be required. The person will be required to identify himself/herself and the firm he/she works for and the information will be verified against the Entry Authority List (EAL) and may then proceed to obtain their long term pass.
Personnel cannot show up at the gate without prior notification for access and expect to gain access.
Verbal access cannot be provided.
Each employee and their vehicle may be subjected to search before entry. Each employee will be expected to comply with all directions provided by security personnel at the access gates. Failure to fully comply with directions provided by security personnel will result in access being denied. Before attempting access, ensure there are no weapons or other prohibited items in the vehicle as they will be confiscated if found. Further, no practical jokes or wise remarks will be tolerated. Security of Whiteman AFB is treated as serious business and full cooperation is required.
Once access to the base has been granted, each contractor employee will be expected to proceed to the work site and not go to other facilities except in the performance of their work. Access to the flightline can only be allowed through additional authorization.
Attachment 1 8
Expect some delays in gaining access to the base especially between the hours of 6:30 AM to 8:00 AM due to heavy traffic.
Gate Hours: Gate hours are subject to change by the Government at any time due to military activities.
Contractor shall be responsible for coordinating with the Contracting Officer for base access.
14.11 Unauthorized Activity: The contractor shall inform all personnel working under his/her jurisdiction (including subcontractor and supplier personnel) that access to areas outside of the immediate work area (excluding cafeterias and restrooms near the work site, direct haul and access routes, Contracting and Civil Engineering offices, and points of supply and storage) is prohibited.
Circulation of said personnel will be limited to official business only. Persons engaged in unauthorized reconnaissance of other contractor or government activity will be referred to the Contracting Officer for disposition. Infractions involving possible compromise of national security will be turned over to the FBI for disposition.
14.12 FAA Notification: Contractor will submit the required FAA Form 7460-1 to the FAA via https://oeaaa.faa.gov/oeaaa/external/portal.jsp for all new construction, work on the exterior of existing facilities, and all crane usage. Contractor will follow any and all requirements dictated by the FAA or Whiteman AFB Airfield Operations personnel in response to the FAA Form 7460-1 submittal.
15. AIRFIELD CONTROLLED AREA RESTRICTIONS:
The airfield controlled area is defined as all the areas on and adjacent to airfield features, within a flightline perimeter fence, the flightline side of facilities, or as otherwise defined in specific project documents.
16. CONTROLLED AREA ESCORTS:
The Contractor shall coordinate escorts with appropriate security clearance & badges required for work in controlled areas with the 509 CES Escort Pool at Whiteman AFB. The Contractor & Subcontractor employees shall be accompanied by their escort at all times in the controlled area jobsites.
Contractor/escort MUST have a flightline license to operate a vehicle on the airfield . Radio contact with the Airfield Control Tower will be made before entry, monitored while in the controlled area and contacted at departure from the controlled area.
Aircraft and emergency fire department vehicles always have the right of way. Construction personnel, vehicles and equipment must yield to taxiing aircraft at all taxiway crossing points.
The Contractor must only use designated taxiway crossing points, unless otherwise directed.
Runways must be cleared of equipment and personnel and be operationally ready within five minutes in the case of In-Flight Emergencies (IFEs), unless the runway is physically unable to accept aircraft. No contractor vehicles, equipment, or personnel shall be on or crossing any active runway, except during construction period closures as outlined above or when clearance is requested from and granted by the control tower.
Attachment 1 9
The Contractor will be issued a hand held radio by the government in order to be able to communicate with the airfield control tower. The on-site project manager shall be expected to continuously monitor the airfield frequency.
Unless authorized by the Contracting Officer, no contractor vehicles, equipment or personnel shall cross the painted red security lines located at various locations on the Airfield. Security Police are authorized to use deadly force in such breaches of security.
Other airfield contracts may be underway at the same time as this contract, and therefore the contractors may have to share haul routes, and work in the proximity of one another.
The Contractor may be required to cease project operations on the airfield during In Flight Emergencies (IFEs) or as directed by the Installation Commander. These delays typically are for one to two hours at a time. Every effort will be made by Base Operations, Civil Engineering, and the Contracting Office to minimize all potential delays and to inform the Contractor as early as possible of such delays so that critical work can be effectively scheduled around such events. For bidding purposes, assume work stoppages will occur minimally.
17. COORDINATING AND SCHEDULING
17.1 Work Coordination: In order for the work to progress smoothly and cause minimal difficulties, it will be necessary for the contractor, construction inspector, project engineer, and Contracting Officer to maintain close and active coordination. At all times, the Contractor shall keep the Government informed of when and what work will be accomplished. All work schedules will be coordinated with the appropriate representatives of the Contracting and Technical offices.
All work shall be accomplished in such a manner with upmost regard to Whiteman’s ongoing missions and cause minimum disruption to those missions.
At least two (2) calendar days prior to testing or closing hidden work, the Contractor shall identify such work and notify the Contracting Officer and Technical Representative when it will be accomplished. If proper inspections are not accomplished as a result of such lack of notification, the Contractor bears the risk of possibly removing completed work and reaccomplishing such uninspected work at no cost to the government.
17.2 Progress Schedule: The schedule shall be accomplished on and in accordance with the instructions pertaining to AF Form 3064 (AF3064), Contract Progress Schedule, as specified herein and directed by the Contracting Officer.
Work percentages shall be plotted weekly, from Sunday through Saturday, beginning with the date of receipt of the Notice to Proceed (NTP) through the contract completion date. Once approved, schedules will not be changed without Contracting Officer direction and/or approval.
The Work Elements, column B on the AF3064. Each element shall be identified by the applicable, major element of work (e.g., Site Work, Concrete, Electrical, etc.).
Attachment 1 10
The percentage of each listed work element of the job shall be shown opposite each major work element in Column C of the Contract Progress Schedule and may be expressed in whole numbers or may be carried out to two (2) decimals.
In order to assist in evaluating the AF3064, as well as the progress of construction, the contractor shall supplement the AF3064 with a Schedule of Values worksheet which will identify each sub-element of work along with its dollar and percentage values of the project work. A "network analysis system" may be used to supplement the proposed progress schedule.
17.3 Progress Reports: The report shall be accomplished on and in accordance with the instructions pertaining to AF Form 3065 (AF3065), Contract Progress Report, and as specified herein.
Progress Reports shall be submitted weekly by close of business on the Monday following completion of the previous work period.
Whenever the cumulative percentage of the work is 5% or more below the scheduled percentage, the Progress Report shall be accompanied by a letter of explanation for the delay and a plan detailing how the contractor intends to get back on schedule.
Each AF3065 shall be reviewed by the project inspector and CO for accuracy. Payment shall be authorized based on the Contracting Officer’s determination of percentage complete as reflected on the approved AF3065.
18. SUBMITTALS
18.1 AF Form 66 (AF66), Schedule of Material Submittals:
If an AF66 listing required submittal items was included with the project documents: Within 10 calendar days after receipt of the Notice to Proceed (NTP) with construction, the Contractor shall identify a not later than “required submission date” for each item specified on this form. Contractor shall ensure the specified dates provide adequate time to process the requirement and allows sufficient order/receipt time prior to the projected installation date.
If an AF66 is required to be developed with the design documents for the project: The contractor shall develop and provide the AF66 within the timeframes specified. Required submission of the material items listed shall be identified as NTP + XX calendar days. Contractor shall ensure the specified dates provide adequate time to process the requirement and allows sufficient order/receipt time prior to the projected installation date.
18.2 AF Form 3000 (AF3000), Material Approval Submittal:
Each submittal shall be transmitted under an AF3000 and shall be prepared in accordance with the Instructions on the reverse of the form and in Section 013300, Submittals and Substitutions.
Attachment 1 11
Variance from contract requirements: Whenever materials or drawings are required to be submitted by the Contractor for approval, and the material or drawings submitted are at variance with the specifications or Government drawings, but are approved by the Contracting Officer inadvertently and without consciousness of the variance, then the approval shall not be final unless the Contractor expressly noted on the submittal that "This material or drawing varies from specifications in the following aspects."
19. HAUL ROUTE
19.1 Specified Haul Route: The Contractor shall follow specified haul routes for this project, unless otherwise directed. The Contractor may make changes to the route only with the prior approval of the Contracting Officer at no additional cost to the Government. The Contractor shall restore the area to its original condition at the end of the contract period unless specific, written approval has been granted by the Contracting Officer.
19.2 Haul Route Cleanup: In an effort to minimize Foreign Object Damage (FOD) potential to aircraft, all mud, dirt, debris, foreign objects, or spills of any kind from the Contractor's operations (including subcontractors and suppliers) on taxiways, runways, parking aprons, hard surfaces, streets, and parking lots used as access to the work or staging areas, shall be cleaned immediately after use.
Cleanup shall be performed to the satisfaction of the Contracting Officer and the Airfield Manager.
Contractor may be held responsible for FOD to aircraft, if the FOD is attributable to his negligence or failure to comply with contract requirements.
20. MATERIAL STORAGE
20.1 Storage Area: Unless otherwise indicated, no on-base storage facilities are available for contractor owned supplies, tools, materials or equipment. Buildings and structures which are part of the contract may be used for storage provided the space is not required for government occupancy and the contractor accepts full responsibility for the material stored therein. The Contractor shall be responsible for protecting all construction materials from weather damage.
20.2 Storage Site: the Contracting Officer shall designate a storage site for contractor-owned supplies, tools, materials, and/or equipment in close proximity to the jobsite. All job equipment and material not in use, but to be installed in or used on the project by the Contractor may only be stored in this area. Security for the equipment and material storage shall be provided by the Contractor at his risk.
21. UTILITIES SERVICES
21.1 Water and Electricity: All reasonable amounts of domestic water and electricity will be made available to the Contractor by the Government from existing system outlets and supplies. Normal quantities of electricity and water necessary to make final tests of completely installed systems will be furnished by the Government. With prior coordination with the Contracting Officer, the Contractor shall be given access to water hydrants to obtain water for construction activities. The Contractor shall
Attachment 1 12 provide and install a double back flow preventer with meter to all water hydrants made available to them for project use.
21.2 Telephone: Commercial telephone lines are not available to the contractor. Separate communication arrangements must be made by the Contractor as necessary.
21.3 Temporary Utility Connections: The Contractor shall, at his own expense, make all temporary connections and install distribution lines. The Contractor shall furnish to the Contracting Officer a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. All temporary lines shall be maintained by the Contractor in a workmanlike manner satisfactory to the Contracting Officer and shall be removed and the area restored to its original (or better) condition by the Contractor prior to final acceptance of the construction. The point of connection shall be coordinated with the Government technical representative prior to connection. If additional outlets are needed, they will be provided at the Contractor's expense.
21.3.1 UTILITY SERVICE INTERRUPTIONS: If any utility will require interruption in service the following would apply:
Advance Notification: The Contractor shall submit written notification not less than 28 calendar days in advance of each interruption of each utility and/or communication service to or within existing buildings and facilities being used by others.
Duration: No single outage will exceed four (4) hours at a time or more than once in any two week period unless approved in writing by the Civil Engineering Customer Service Department. The time and duration of all outages will be coordinated with the Using Agency by Customer Service. Utility outages required shall be scheduled so as to provide the minimum interference to the government. Outages shall occur on weekends and/or during non-standard work hours depending on facilities affected and Using Agency operations.
Clearance: No outage may begin until the Contractor has applied for and obtained an Air Force Form 103, Base Civil Engineering Work Clearance Request. The Contractor shall apply for the clearance on Whiteman at Bldg 709, Civil Engineer Customer Service. Permit application shall be submitted a minimum of four (4) weeks prior to any outage as the Air Force portion of the permit typically takes four (4) weeks to complete.
22. SECURITY:
22.1 Physical Security: The Contractor shall provide physical security for the materials and work under his control, and shall immediately notify the Contracting Officer when equipment, material or work area is damaged.
Attachment 1 13
22.2 Communications: In accordance with Air Force Instruction 33-211, all communications with DoD organizations are subject to communications security (COMSEC) review. Contractor personnel will be aware telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations.
Therefore, civilian contractor personnel are advised any time they place a call to, or receive a call from, a USAF organization, they are subject to COMSEC procedures. The contractor will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees.
23. SAFETY AND ACCIDENT PREVENTION
23.1 General: Compliance with the current U.S. Army Corps of Engineers "Safety and Health Requirements Manual", EM 385-1-1; Occupational Safety and Health Act (OSHA) Public Law 1910 and 1926;
Air Force Occupational Safety and Health (AFOSH) standards, and current Whiteman AFB safety regulations is mandatory. The prime Contractor shall be held responsible to insure that his/her workforce and any subcontractor or supplier workforce comply with the above safety requirements.
23.2 Personnel Safety: Adequate protection of all persons shall be provided at all times. Work shall proceed in a manner to prevent hazard.
23.3 Temporary Barriers: Contractor shall install and maintain temporary barriers around construction work areas to prevent unauthorized personnel from area.
23.4 Road Closures/Lane Restrictions: The Contractor shall be responsible for submitting a closure/lane restriction plan to Contracting for approval at least 30 days in advance of any anticipated closure/restriction. All road closures and/or lane restrictions need to be properly advertised to base personnel and retirees which requires three weeks’ notice to be placed in the necessary publications.
The Contractor shall be responsible for providing and placing all barricades, lighting, closure markers and safety devices during any road work.
23.5 Safety Briefings: Contractors operating on base will be responsible to brief and ensure their employees, subcontractors, and suppliers comply with all traffic rules and regulations, as well as entry procedures.
23.6 Security Police: All instructions given by Security Police personnel will be complied with immediately. All on-base traffic rules are contained in Air Force Instruction (AFI) 31-204, Motor Vehicle Traffic Supervision.
23.7 Equipment and Tools: Equipment to be used on the project shall be safe and in good operating condition. The Contracting Officer reserves the right to inspect any on-base equipment and reject such equipment if he considers it unsafe, in poor operating condition, or inappropriate for work.
23.8 Explosive Operated Hand Tools: The Contractor shall comply with OSHA (Occupational Safety and Health Act) Standard 1910.215(c) when utilizing explosive operated hand tools. Storage of explosive cartridges on the installation will be in metal containers and limited to one day’s supply. The
Attachment 1 14 contractor will provide adequate controls to prevent loss/theft of cartridges used and stored on the installation.
23.9 Use of Radioactive Devices on Government Property: Under no circumstances will an unlicensed radioactive device be used on Whiteman Air Force Base
24. FIRE PREVENTION AND PROTECTION
24.1 Whiteman AFB Fire Regulations: The Contractor shall comply strictly with the Base fire regulations and become thoroughly familiar with and brief employees and subcontractors on the fire safety requirements applicable to this contract.
24.2 Welding Permit: No welding, cutting or open flame will be permitted without obtaining a Welding/Cutting/Burning Permit issued by the Base Fire Department. This permit shall be requested by the Contractor a minimum of one workday prior to required need. A permit must be obtained each time any welding, cutting, or open flame is required.
24.3 Clean-Up: The Contractor shall at all times maintain good housekeeping practices to reduce the risk of fire damage. All scrap materials, rubbish, and trash shall be removed daily from, in, and about the site. No debris shall be permitted to be scattered on adjacent property.
24.4 Fire Extinguishers: The Contractor shall provide fire extinguishers in accordance with the recommendations of the base fire regulations. Proper type fire extinguisher shall be available at each location where cutting and welding is being performed. Where electric or gas welding or cutting is done, interposed shields of incombustible material shall be used to protect against fire damage due to sparks and hot metal.
25. ENVIRONMENT PROTECTION:
25.1 Regulations and Permits: All work and Contractor operations shall comply with the requirements imposed by all applicable Federal, State, local, and base regulations and permits concerning environmental protection. Contractor shall pay for and obtain all Federal, State, local, and Whiteman AFB permits required for the successful execution of the project. The time required to process and receive such permits is included in the performance period. The project schedule shall reflect time required to acquire permits prior to commencing work on any affected work.
25.2 Hazardous Materials
25.2.1 Definitions: Any material defined as hazardous under the latest version of Federal Standard No. 313, or any item or class of items covered in the Emergency Planning and Community Right-to-Know Act (EPCRA) tracking requirements, OSHA HAZCOM Standard, and all Class I, and Class II Ozone Depleting Substances (ODS). The following items are a few examples of type of products that may be required to be tracked in the Air Force Environmental Management Information System (AF-EMIS):
Attachment 1 15
Items with the flash-point of 141 degrees or below.
All paints, Lacquer, Enamels, and Thinners (water-based, non-lead, non-polyurethane Latex paints are exempt from HAZMART tracking, however, MSDS is still required).
Adhesive, Sealants, Glues, some types of caulking.
Some Cleaning Supplies: Bleach, some types of glass cleaner, Drain cleaners, some floor waxes and stripers and others.
Pesticides, Insecticides, Herbicides, Fungicides. Usages of these products are to be used only if explicitly specified in the contract, otherwise usage of these materials is not permitted on Whiteman AFB
Compressed gases.
Any type of material with a PH of 2 and below or 10.5 and above.
25.2.2 Material Safety Data Sheets (MSDS): Prior to use, the Contractor shall submit MSDS for chemical or hazardous materials as a submittal item. Each MSDS shall be submitted in 3 copies, and the Contractor shall retain a copy for on-site use. All hazardous materials must be authorized before being used or brought on to the job site.
25.2.3 Hazardous Materials Authorization Procedures for Contractors: The Contractor is responsible for the proper handling and management of all hazardous waste generated from his/her work. The contractor will be held fully liable for any contractor activity/non-activity that results in a Notice of Violation (NOV) or any other regulatory penalty. Contractors using hazardous material (HAZMAT) on WAFB must comply with the authorizations procedures described below and in conformance with AFI 32-7086, 2.5.5.
Contractors must provide to the WAFB Contracting office, as a submittal item, a list of proposed HAZMAT, including MSDS that it plans to use on the installation during the performance of the contract. The Contracting officer/administrator will then forward this information to the Quality Assurance (QA) evaluator or Inspector.
This information will be forwarded to the HAZMART office by the Inspector. HAZMART office will review the information and determine which contractor-identified materials need to be tracked.
For each contractor-identified HAZMAT that does not meet the Air Force definition of a HAZMAT, these requirements do not apply.
For each contractor-identified HAZMAT that does meet the Air Force definition of a HAZMAT, the HAZMART office will notify the Inspector of the material requiring authorization and tracking. An Enterprise Environmental, Safety, and Occupational Health Management Information System (EESOH-MIS) worksheet will be completed and submitted as a submittal item to the Contracting Officer. The following information is required to be provided for each hazardous material used on WAFB: material name, manufacturer, unit of issue, and the amount used. If requested, the HAZMART office can assist the Contractor in completing the EESOH-MIS worksheet.
Attachment 1 16
The HAZMART office will enter the contractor supplied information into the HAZMAT tracking system to generate an AF Form 3952.
The Contractor will be issued tracking labels (barcodes) to assist in tracking and reporting the material used during the performance of the contract. It is encouraged that the labels be affixed to the material.
A Form 3952 will also be issued for the Contractors files. Copies of the AF Form 3952 must be kept on-site for the duration of the project. The contractor will be added to the authorized users list (AUL) by the HAZMART office.
Contractor will be required to report to the inspector on a monthly basis (by the 5th of the month) and within 10 working days after the completion of the project, the material used (see Contractor’s Monthly HAZMAT Usage Report).
Inspector will forward this information to the HAZMART by the 10th of every month.
HAZMART office will assist the QA, Inspector, and Contractor in any way possible and to answer any questions.
Material brought on the installation that was not originally identified by the contractor must be authorized. MSDS and other related information, provided by the contractor, must be given to the HAZMART office.
25.3 Asbestos and Lead Based Paint:
Prior to the commencement of any project demolition or renovation operation, Contractor shall thoroughly inspect the affected facility or part of the facility (regardless of the date of construction) where the demolition or renovation operation will occur, for the presence of asbestos and LBP.
Ten (10) days prior to the removal of any asbestos from any government facility, the Contractor shall obtain and submit an approved copy of the asbestos demolition permit to the Contracting Officer. This also applies to renovation operation when a facility has at least 260 linear feet, 160 square feet or 35 cubic feet of regulated asbestos containing material (RACM). When applicable, Contractor shall also submit a copy of the Notification to the County to the Contracting Officer. Also, ten (10) days prior to start work, the licensed Abatement Contractor shall submit an abatement work plan including copies of workers’ certifications to the Contracting Officer for 509 CES review (Environmental and Operations Offices).
The Contractor shall not install any asbestos containing material (ACM) or apply LBP materials. If such material is detected, the Contractor shall remove it and replace it with acceptable material at no additional cost to the government.
The Contractor shall immediately notify the Contracting Officer or COR when encountering any material which has not been previously identified is suspected of containing asbestos or lead-based paint. The Contractor shall cease operation in the affected part of the facility until suspected materials are verified and abated.
Attachment 1 17
If required by the project, the Contractor shall remove all friable ACM and Category I and Category II nonfriable ACM including 1% or less ACM prior to the commencement of demolition or renovation.
The asbestos removal shall be conducted by a licensed abatement contractor.
The Contractor shall prepare waste manifest for proper disposal and shipment of waste to a permitted facility. The manifest shall be signed by base-authorized personnel only as the waste generator
25.4 Trackout: The Contractor shall employ methods to prevent trackout from the construction/storage/laydown site(s). Mud or dirt shall not be allowed to be tracked out onto a paved road where such mud or dirt extends fifty (50) feet or more in cumulative length from the point of origin or allow any trackout to accumulate to a depth greater than 0.25 inch. Notwithstanding the preceding, all accumulations of mud or dirt on curbs, gutters, sidewalks or paved roads including trackout less than fifty (50) feet in length and 0.25 inch in depth, shall be cleaned and maintained to eliminate emissions of Fugitive Dust. At a minimum all trackout must be cleaned up by the end of the workday or evening shift, as applicable.
25.5 Storm Water Construction Permit (Soil Erosion): The Contractor shall provide protective barriers to prevent soil erosion on all required excavations. The Contractor shall provide environmental protection to prevent sediment drainage of silts into storm drains. Contractor shall minimize disturbed area, stockpile excavated soils, and protect excavated soils from wind and water erosion. If one (1) acre or more of total area is disturbed, including equipment lay down area, Contractor shall obtain a Missouri Storm Water Construction Permit, And prepare a Storm Water Pollution Prevention Plan (SWPPP).
Contractor shall coordinate the submittal with the Whiteman Storm Water Manager through the Contracting Officer on an AF 3000.
25.6 Protection of Water Resources: The Contractor shall not pollute any streams, rivers, or waterways through direct discharge or by storm water runoff. The Contractor shall comply with all applicable Federal, State and local laws.
25.7 Waste and Disposal:
There are no waste or disposal areas available on the base property. The Contractor shall make arrangements at an off-base location in accordance with local and state codes for disposal of waste generated from the site. All hazardous and non-hazardous waste materials (whether solid, liquid, or gaseous) generated by any work under the contract shall be handled, transported, stored, and disposed of by the contractor and by his subcontractors at all times in accordance with all applicable Federal, state, or local laws, ordinances, regulations, court orders, or other types of rulings having the effect of the law, including, but not limited to the following:
Executive Orders 12088 as amended by E.O. 13143, 12580, 11988, and 11990;
Clean Air Act, (42 U.S.C. 7401-7671);
Clean Water Act (33 U.S.C. 1251-1387);
Endangered Species Act (16 U.S.C. Sec 1531-1544);
Toxic Substances Control Act (15 U.S.C. Sec 2601-2671);
National Historic Resources Protection Act (16 U.S.C. Sec 740-470w-6);
Solid Waste Disposal Act (42 U.S.C. 6901-6991);
Attachment 1 18
Archaeological Resources Protection Act (16 U.S.C. 470aa-470-11);
Safe Drinking Water Act (42 U.S.C. 300f - 300j);
Federal Insecticide, Fungicide, and Rodenticide Act (7 U.S.C. 136-136y);
Sikes Act Administration Regulations (29 CFR 1910);
Environmental Protection Agency regulations (40 CFR 50-87, 110, 112, 122, 136, 141-13, 162, 165, 166, 171, 240-246, 260-271, 280, 300, 302, 355, 370, 372, 403, 405-471, and 761);
Department of Transportation regulations (49 CFR 171-177);
Resource Conservation and Recovery Act (RCRA) (40 CFR 260 – 271) Contact the Hazardous Waste Program Manager (HWPM) prior to shipment of hazardous waste off site. The HWPM (or designee) will verify waste profile sheets and manifests. The waste must have supporting documentations (e.g. MSDS) with the correct manufacturer analytical or laboratory analytical.
25.8 Recycling Requirements: Contractors shall participate in Whiteman AFB's Qualified Recycling Program (QRP).
At least three weeks prior to the start of the contract, contractors shall include an estimation of potential quantities of material that can be reused and recycled plus the amount disposed to a landfill for the project.
Contractor shall provide a monthly report including the following information:
Type of material (i.e. construction debris, plastics, gravel, etc) Amount generated (tons) Amount reused (tons) Amount recycled (tons) Diversion rate (see Executive Order 13514 below) Location of landfill All dump receipts
Executive Order (EO) 13514, Federal Leadership in Environmental, Energy, and Economic Performance mandates diversion of at least 50% of construction and demolition materials and debris by the end of fiscal year 2015. Use the following formula to determine the diversion rate for any reporting period: [(Amount reused (tons)) + (Amount recycled (tons))]/ (Amount generated (tons))
25.9 Spills:
Should any hazardous substance or oil spills occur on this project, in addition to containing and removing such spill, the Contractor shall:
During normal working hours, immediately report all spills in quantities of five (5) gallons.
Forward a written, completed spill report to the Contracting Officer within three (3) working days after the occurrence.
Attachment 1 19
All contaminated material shall be removed, transported and disposed of in accordance with all applicable laws, regulations and policies. The contractor shall also submit a copy of all permits and disposal certificates to the Contracting Officer as a submittal item for review. All costs incurred for the disposal of contaminated soils, as a result of Contractor negligence or error will be the Contractor’s responsibility.
25.10 Historical/Archaeological Artifacts: The Integrated Cultural Resources Management Plan (2007, page V) provides guidance on the discovery of historical or archaeological artifacts. If artifacts, features, or structural remains are discovered during, but not exclusive to, mission actions, personnel should implement the following:
Activities at the location should immediately cease and efforts should be taken to ensure protection until arrival of the Cultural Resources Manager;
The site shall be marked to provide efficient relocation, while also taking efforts to minimize the types of signs that would attract personnel, thereby placing the location in additional danger;
It is illegal to collect or disturb archaeological materials under the Archaeological Protection Act; thus, artifacts shall be left in place;
The Cultural Resources Manager shall be notified within 24 hours of discovery.
Contractor personnel should make efforts to be available to assist in identifying the location.
25.11…