SF 1442 Solicitation.pdf

PDF 157 KB Posted

Attached to
Hangar Floor Epoxy Coating
Solicitation number
FA4625-12-R-0015
Issued by

About this file

SF1442 Solicitation

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Epoxy Floor Application

1. Only one site visit shall be held and is scheduled for 29 August 2012 at 9:00 a.m. CST. The site visit is MANDATORY. Any proposal received from a company that did not have representation at the site visit shall be rejected. Attendance of the site visit w ill be documented by the contract administrator. The Entry Authorization List (EAL) must be submitted in accordance w ith Section L, Site Visit provision.

2. A Notice To Proceed (NTP) w ill be issued upon receipt of bonds after contract aw ard. See Blocks 12A. and 12B. below .

3. This requirement is being solicited as a Total Small Business set-aside.

4. The Designated NAICS code is 238190.

5. Block 14, Add company CAGE code, Taxpayer Identif ication Number (TIN), and DUNS number.

6. See Section L of the solicitation for the Instruction to Offers.

7. See Section M of the solicitation for the basis of contract aw ard.

//////////////////////////////LAST ITEM////////////////////////////////

ANDREW S. GAST 660-687-5431

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

13-Aug-2012

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________13 Sep 2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

509 CONS/LGCB - FA4625

727 SECOND ST, STE 124A

WHITEMAN AFB MO 65305-5344

FA4625

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

(660) 687-5462FAX:TEL: (660) 687-5466 TEL: FAX:

FA4625-12-R-0015 44

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

FA4625-12-R-0015

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot Building 52 - Epoxy Floors

FFP

Contractor shall provide labor, materials, and all equipment required to prepare and install Aircraft Hanger Epoxy Floor Coating System in building 52.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Lot Building 27 - Epoxy Floors

FFP

Contractor shall provide labor, materials, and all equipment required to prepare and install Aircraft Hanger Epoxy Floor Coating System in building 27.

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

STATEMENT OF WORK

EPOXY FLOOR COATING

WHITEMAN AFB, MO 65305

1. SCOPE. Contractor shall provide labor, materials, and all equipment required to prepare and install

Aircraft Hanger Epoxy Floor Coating System in designated areas.

2. APPLICABLE DOCUMENTS.

2.1 Attachment 1. Facility drawings.

3. REQUIREMENTS.

3.1 General.

3.1.1 The contractor shall have free and unencumbered access to floor area and facility 24 hours a day during project.

3.1.2 The contractor shall complete project within 180 days from receiving the Notice To Proceed.

3.1.3 The Government will attempt to maintain building climate in according to contractor requested temperature.

3.1.4 Contractor is responsible for their own refuse and disposal of generated waste IAW Missouri State, and all Federal Laws. Contractor shall manage, handle, transport, and dispose of any and all hazardous materials and scrap waste at their own expense. The Government accepts no liability for the disposal of the Contractors hazardous waste or refuse.

3.1.5 Contractor shall install all warning, work, and cautions signage and barriers protecting the flooring projects.

3.1.6 Building 27 floor size is approximately 20,190 square feet.

3.1.7 Building 52 floor size is approximately 13,360 square feet.

3.2 Surface preparation.

3.2.1 The contractor shall prepare existing floor and joints by grinding, cutting, shot blasting with recovery system, or by approved abrading methods in accordance with manufacturer recommendations.

3.2.2 The contractor shall remove existing floor coating in hanger area to bare concrete.

3.2.3 The contractor shall cut out, clean and rout all joints and install new compatible roding and expandable joint material in accordance with manufacturer recommendations.

3.2.3.1 Building 27. Floor joints are approximately .25 inches wide by 468 feet in length.

3.2.3.2 Building 52. Floor joints are approximately .25 inches wide by 650 feet in length.

3.2.4 Building 52. The contractor shall clean and rout all cracks to an acceptable width and depth and fill with compatible roding and expandable joint material in accordance with epoxy floor coating manufacturer recommendations. Floor cracks in need of repair are approximately 40 linear feet.

3.2.5 The contractor shall remove all damaged or loose substrate and replace with rapid strength epoxy repair mortar, polymer concrete or other system compatible repair material. Contractor shall fill all floor imperfections prior to applying coatings with a compound in accordance with manufacturer recommendations.

3.3 Installation.

3.3.1 The contractor shall conduct moisture testing on floor substrate prior to application in accordance with the manufacturer recommendations.

3.3.2 Directional Lines. The contractor shall apply all “painted” directional lines on floor and clear coat with applicable materials.

3.3.2.1 Building 27. Total allowance for lineage is 6 inches x 716 linear feet. The color shall be yellow except for one set of yellow/black alternating angled pinch points along hanger door 5 feet deep by 25 feet long.

3.3.2.2 Building 52. Total allowance for lineage is 4” x 900 linear feet. The color shall be yellow except for one set of yellow/black alternating angled pinch points along hanger door 5 feet deep by 25 feet long; 1 each single yellow line 4 inches by 120 feet indicating fire lane; 15 yellow wheel boxes 4” w x 3’ x 3’.

3.3.3 RESERVED

3.3.4 Drainage angle iron.

3.3.4.1 Building 27. The contractor shall paint all drainage angle iron with black enamel paint, not to include grating. The angle iron that supports grating is approximately 1-1/2” x 880 feet.

3.3.4.2 Building 52. The contractor shall paint all drainage angle iron with black enamel paint, not to include grating. The angle iron that supports grating is approximately 1-1/4” x 650 feet.

3.4 Material Requirements.

3.4.1 Epoxy coating system shall be Sherman Williams Hanger Coating System.

3.4.2 Contractor shall install three coat epoxy flooring system.

3.4.2.1 100% solids epoxy primer material @ 10 MILS.

3.4.2.2 Intermediate coat of 100% solids epoxy resin @ 15 MILS.

3.4.2.3 Final coat of aliphatic, chemical, abrasion and UV resistant urethane 5 MILS with abrasives for slip resistance. Color shall be 1263 Pewter Gray (71) high gloss finish.

3.4.3 Slip resistant finish.

3.4.3.1 Building 27. Anti slip will be equivalent to industry grade “medium”.

3.4.3.2 Building 52. Anti slip will be equivalent to industry grade “sugar sand 480”.

3.4.4 Contractor shall perform any preparation between coats in accordance with manufacture’s recommendation.

3.5 Warranty. The contractor shall provide one year warranty on materials and labor.

3.6 Safety. Contractor shall perform project requirements in accordance with the applicable OSHA standards for their craft.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

0001 180 dys. ADC 1 509 CES - F4E3ZA

660 10TH STREET SUITE 211

WHITEMAN AFB MO 65305

F4E3ZA

0002 180 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

F4E3ZA

Section G - Contract Administration Data

CLAUSES INCORPORATED BY FULL TEXT

WIDE AREA WORKFLOW-RECEIPT AND ACCEPTANCE (WAWF-RA) (CONSTRUCTION)

1. In accordance with DFARS Clause 252.232-7003, Electronic Submission of Payment Request, the contractor shall submit payment requests using WAWF-RA. Information regarding WAWF-RA is available on the internet at https://wawf.eb.mil.

2. The contractor shall create a CONSTRUCTION PAYMENT invoice.

3. The contractor shall use the following Department of Defense Activity Address Codes (DODAAC).

ISSUE DODAAC: FA4625

ADMIN DODAAC: FA4625

INSPECT DODAAC (BPN): FA4625

CONTRACTING OFFICER DODAAC (BPN): FA4625

PAY DODAAC: F67100

NOTE: Vendor must include the following email address where the program prompts for additional emails:

wawf509conslgca@whiteman.af.mil

(End of clause)

Section H - Special Contract Requirements

SPECIAL CONTRACT REQUIREMENTS

H-1 BASE ACCESS

Occasionally it is necessary to require either early release of Whiteman AFB personnel, late reporting, or even total base closure when weather conditions make normal travel unsafe. When weather conditions cause one of the above situations, contractor personnel will be denied access to the base unless they have been notified that their contract service has been determined essential. For base closure or late reporting during inclement weather, listen to radio stations KOKO (1450 AM), DVEQ (104.0 FM), KPRS (103.3 FM), KDRO (1490 AM), KXKX (105.7 FM), KSIS (1050 AM), KLRQ (96.1 FM) KDKD (1280 AM/95.3 FM), and / or watch television stations KMBC (Channel 9) and WAFC Cable (channel 41).

H-2 REQUIRED INSURANCE (IAW FAR 28.306(b))

Reference FAR clause entitled "Insurance . . ." the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.

a. Workmen's Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.

b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.

c. Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.

Before commencing work under this contract, the Contractor shall certify to the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribed or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.

H-3 BONDS

a. Performance and Payment Bonds. The contractor will be required to furnish a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25-A), each with good and sufficient surety or sureties, acceptable to the Government for each purchase order exceeding $150,000.00 within 14 calendar days after award. The contractor may use alternate payment protection for the delivery orders between $2,000.00 and $150,000.00.

Note: A Notice To Proceed will not be issued and no work shall begin until good and sufficient surety has been received and accepted by the Contracting Officer.

NOTE: INDIVIDUAL SURETY CLAUSE: In order for the Contracting Officer to determine the acceptability of individuals proposed as sureties, all offerors providing bonds which are executed by individual sureties are required to submit the following information in support of Standard Form 28, "Affidavit of Individual Surety:"

a. A complete description of property offered, supported by title or deed, and appraisal or tax assessment.

b. A current list of all other bonds on which the individual is a surety and bonds for which the individual is requesting to be a surety.

c. Independent certification of net value of property offered.

d. Independent certification of liens or other encumbrances which exist against all property listed.

e. CPA - certified balance sheet(s) and income statement(s) with a signed opinion for each individual surety.

H-4 TAXES

The Missouri Department of Revenue agrees that contractors, subcontractors and material suppliers may claim an exemption from Missouri sales and use tax with respect to tangible personal property and materials purchased or used for the purpose of constructing, repairing or remodeling facilities for the United States of America, its agencies and instrumentalities ("the United States"). Therefore, the Contracting Officer shall provide a project exemption certificate to the successful contractor awarded this project. The contractor shall further provide the project exemption to all subcontractors purchasing construction materials for this project.

NOTE: THE PROJECT EXEMPTION CERTIFICATE DOES NOT ALLOW CONTRACTORS TO PURCHASE

MACHINERY, EQUIPMENT, OR TOOLS USED IN FULFILLING THIS CONTRACT, TAX EXEMPT.

H-5 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS

1. Security Training. The on-base contractor senior representative ensures all contractor employees receive initial and recurring security education training from the sponsoring agency’s security manager. Training must be conducted IAW DOD 5200.1-R, Information Security Program Regulation, and AFI 31-401, Information Security Program Management. Contractor personnel who work in Air Force controlled/restricted areas must be trained IAW AFI 31-209, The Air Force Resource Protection Program, and AFI 31-101, The Air Force Physical Security Program.

2. Listing Of Employees. The on-base contractor senior representative shall maintain a current listing of employees. The list shall include the employee's name, social security number and level of security clearance if contract work involves unescorted entry to Air Force restricted areas or other sensitive areas designated by the installation commander. The list shall be provided to the Contracting Officer and sponsoring agency’s security manager. An updated listing shall be provided when an employee's status or information changes.

3. Weapons, Firearms, and Ammunition. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor-owned or privately owned vehicle while on Whiteman

AFB.

4. Physical Security. The contractor shall be responsible for safeguarding all government property and controlled forms provided for contractor use. At the end of each work period, all government facilities, equipment, and materials shall be secured.

H-6 PREPARATION OF PROGRESS SCHEDULES AND REPORTS

The reports contemplated by the clause 52.236-15 entitled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. The AF Form 3064 shall be provided to the Contracting Officer not later than 15 calendar days after issuance of the Notice to Proceed. (Mandatory when performance is 60 or more days)

H-7 MATERIAL APPROVAL SUBMITTAL FORM (AF FORM 3000)

All material and articles requiring approval, as contemplated by the Materials and Workmanship Clause (FAR 52.236-5), shall be submitted by the contractor using AF Form 3000. These submittals are divided into three classes. Class “A” submittals shall be brought to the pre-construction conference. Class “B” submittals are due as specified either on the ENG Form 4288 or as directed by the Contracting Officer (usually within ten days after receipt of the Notice to Proceed). Class “C” submittals are submitted on an “as required” basis. In addition, the contractor is reminded that the certification on the AF Form 3000 must be signed by an individual within the company who has authority to make the certification.

H-8 UTILITY SERVICES

The Contracting Officer has determined that Government-operated utilities are adequate and will be furnished to the contractor without charge where existing outlets are available. The contractor is responsible for installing temporary service outlets, as necessary, and charges will be made in accordance with the clause entitled “Availability and Use of Utility Services” (Contract Clause FAR52.236-14)

Damage to Utilities

(a) In the event of a contractor caused utility failure/disruption, the Contractor will first make the area safe, then immediately contact the Base Civil Engineer Call Desk and Contracting Officer.

(b) Repairs to contractor-damaged utilities will be performed in a timely manner and at no additional cost to the Government.

H-9 ON SITE OFFICE TRAILERS AND STORAGE TRAILERS/FACILITIES

Unless otherwise indicated, no on-base storage facilities are available for contractor owned materials. Buildings and structures which are part of the contract may be used for storage providing the space is not required for occupancy and contractor accepts full responsibility for the material stored therein. The Contracting Officer will designate areas where above-mentioned equipment shall be parked.

H-10 AS-BUILT DRAWINGS

The contractor shall maintain one set of drawings at the work site and record all changes and any hidden or subsurface data discovered during construction. The contractor shall provide a marked by blueline copy with all changes, which transpired during the contract. This will be given to the Contracting Officer prior to the final inspection.

H-11 ENVIRONMENTAL REQUIREMENTS

Environmental Impact

All waste materials generated by the contractor or any work under the contract performed on a government installation shall be handled, transported, stored, and disposed of by the contractor and by his/her subcontractors at any time in accordance with all applicable Federal, state, or local laws, ordinances, regulations, court orders, or other types of rules or rulings having the effect of law, including but not limited to Executive Order 12088, 13 October 1978; the Federal Water Pollution Control Act, as amended (33 USC Sec 1251 ET SEQ); the Clean Air Act, as amended (42 USC SEC 1857 ET SEQ); the Endangered Species Act, as amended (16 USC Sec 1531, ET SEQ); the Toxic Substance control Act, as amended (15 USC Sec 2601 ET SEQ); the National Historic Preservation Act, as amended (16 USC Sec 470, ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 USC Sec 460, ET SEQ); the Estimate of and Percentage of Recovered Material Content for EPA Designated (Products) [Aug 2000]; and the Waste Reduction Program [Aug 2000] as required by the Resources Conservation and Recover Act of 1976, as amended (42 USC 6926 (I)(2)(C)).

1. Environmental References:

The contractor is responsible for strict adherence to any local, state, or Federal environmental regulations relating to this contract. 509 CES/CEV is the base point of contact for environmental compliance / non-compliance issues and if applicable, will provide the contractor a briefing of environmental requirements at the pre-performance conference for this contract. Additionally, the contractor shall contact the Contracting Officer whenever interpretations of environmental regulations are required.

2. Hazardous Material Submittal Requirements:

(a) Submittals shall be required for all hazardous materials (most materials contain hazardous constituents). For the purposes of this contract, hazardous material shall be defined as any material or mixture of materials, which may present a danger to the public health, occupational safety, or the environment and includes:

(1) Materials containing chemicals defined under Section 1910.122 (c) of Title 29 of the code of Federal Regulations (CFR), any extremely hazardous substance listed in 40 CFR part 355, and any pesticide for which a registration has been canceled or suspended under the provisions of the Missouri Pesticide Registration Act, Section

281.210 through Section 281.310 of the Revised Statutes of Missouri (RSMO) and 2 Code of State Regulations (C.S.R.) 70-25.010 et seg. Or under the Federal Environmental Pesticide Control provisions of the 7 United States Code (U.S.C.) Section 136, et sect., and;

(2) Materials containing any element, compound, mixture, solution, or substance as designated pursuant to sections 101(14) and 102 of the Comprehensive Environmental Response, Compensation, and Liabilities Act of 1980 (CERCLA), codified at 42 U.S.C. Sections 9601 (14) and 9602, or requiring notice pursuant to Section 304 of the Emergency Planning and Community Right-to-Know- Act of 1986, codified at 42 U.S.C. Section 11004, and;

(3) Any hazardous material, or group or class or material, designated as hazardous by the United States Secretary of Transportation under 49 U.S.C. Section 5130.

(b) Prior to contractor transporting any hazardous material onto Whiteman Air Force Base, the contractor must provide a current copy of the manufacturer’s Material Safety Data Sheet (MSDS) to the Contracting Officer for certification. The contractor must ensure the MSDS contains at minimum, the following information and additional documentation from the manufacturer defining the values of items not directly addressed by the MSDS:

(1) Manufacturer’s Name

(2) List 100% hazardous components

(3) Chemical Abstract Number (CAS Number) for each chemical component

(4) Specific Gravity / Unit Volume and or Unit Weight

(5) pH (Acidity or Alkalinity) if applicable

(6) Flash Point / Ignitability

(7) Exact Weight in pounds / ounces of the material initially brought on base

(c) No hazardous materials for this contract shall be allowed on base until the contractor has received written approval of the submittal for the material in question from the Contracting Officer. If the contractor’s intent is to bring more of the product (same manufacturer) on base property after the product has received approval, only a weight submittal will be required. If it is a different manufacturer from that originally submitted, then a new MSDS submittal will be required.

(d) All material tracking shall be done on the Hazardous Material Tracking List which must be; (1) submitted initially, (2) whenever new hazardous materials are added to the contract (minimum of 60 days between update), and (3) a final update when leftover materials are removed upon completion of the contract. Prior to final acceptance of this contract, the contractor must submit a listing of all hazardous materials relating to this contract.

The Hazardous Material Tracking List will include the product name, manufacturer, and exact weight of material remaining.

(e) When special haul routes are required to deliver or remove hazardous materials for this contract, it shall be addressed by the Contracting Officer during review and approval of each hazardous material submittal.

3. Hazardous Wastes Disposal Requirements:

(a) All hazardous wastes generated by this contract shall be handled in the manner required by the State of Missouri and Federal regulations (RSMO 10 CSR, 40 CFR, and 49 CFR). For this contract, hazardous waste shall be defined as any solid wastes satisfying the criteria listed in 40 CFR 261:3.

(b) The contractor shall ensure wastes generated by this contract that have been chemically altered during this contract are sampled and analyzed to establish levels of all possible Resource Conservation Recovery Act contaminates.

(c) Contractor shall perform all required training and notifications concerning hazardous waste or materials related to contractor’s activities and maintain an on-site listing of employees so trained.

(d) The contractor shall be responsible for proper labeling, containerization, handling, and storage of hazardous wastes created from this contract.

(e) As required by 40 CFR, Whiteman Air Force Base is the “generator” of all hazardous wastes originating within the confines of the installation, and as such is required to certify all hazardous waste is properly prepared and shipped by signing the manifest for off-site transport. All hazardous waste shipments shall be initiated by completion of a “Hazardous Waste Manifest” EPA Form 8700-22 (Rev. 9-94) MDNR-HWG 10, obtainable from the Missouri Department of Natural Resources. The contractor shall be responsible for obtaining all necessary manifest forms and for proper completion of each required by this contract.

(1) The contractor shall obtain all manifest numbers from 509 CES/CEV.

(2) Each manifest line item must have the quantity listed on the manifest in pounds except Polychlorinated Biphenyls (PCBS) which shall have the quantity listed in kilograms.

(3) Each manifest line item must have supporting documentation to allow proper chemical characterization of the hazards as defined in 40 CFR and MO 10 CSR. Sampling and analysis will be required on all wastes, which have been contaminated or altered during the course of this contract.

(4) The contractor shall insure all hazardous wastes are moved off base only by properly licensed hazardous waste transporters and are sent to properly licensed disposal facilities.

(5) 509 CES/CEV shall be the only authorized agency to sign each manifest for wastes being transported off Whiteman Air Force Base. Each shipment must be evaluated by 509 CES/CEV for compliance with applicable environmental regulations prior to signing the manifest. The contractor shall retain the responsibility for correction of all discrepancies noted during the pre- transport evaluation. (Note: CEV personnel are present only during 7:30 a.m. to 4:30 p.m. on normal working days, Monday through Friday.)

4. Inspection Liability:

(a) The contractor must understand that any operations on Whiteman Air Force Base property are fully inspectable (on a no-notice basis) by the Department of Defense, the Department of the Air Force, Missouri Department of Natural Resources (MDNR), Environmental Protection Agency (EPA), Occupational Health and Safety Agency (OSHA), and other federal regulatory agencies. Compliance with all environmental requirements pertaining to this contract is mandatory.

(b) The contractor is subject to no-notice inspections of all activities related to the project by 509 CES/CEV (Base Environmental Flight). Issues of non-compliance will be addressed directly to the Contracting Officer or his/her representative to ensure rapid correction of unsatisfactory features.

(c) The contractor is liable to the Air Force for any fines, penalties, or environmental assessments levied against the Air Force by any environmental regulatory agency that arise from, or relate to, the contractor’s performance of this contract, or the contractor’s failure to perform as specified by the contract. Any such liability may result in an equitable adjustment to the contract price, establishment of a contract debt, or recovery by the government under any other judicial, administrative, or contractual remedy as may be available to the Government.

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.202-1 Definitions JAN 2012 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees APR 1984 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures OCT 2010 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

JAN 1997

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity JAN 1997 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

OCT 2010

52.203-13 Contractor Code of Business Ethics and Conduct APR 2010 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber

Content Paper

MAY 2011

52.204-7 Central Contractor Registration FEB 2012 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

FEB 2012

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

DEC 2010

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

FEB 2012

52.211-13 Time Extensions SEP 2000 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.219-8 Utilization of Small Business Concerns JAN 2011 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards Act - Overtime

Compensation

JUL 2005

52.222-6 Davis Bacon Act JUL 2005 52.222-7 Withholding of Funds FEB 1988 52.222-8 Payrolls and Basic Records JUN 2010 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) JUL 2005 52.222-12 Contract Termination-Debarment FEB 1988 52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility FEB 1988 52.222-21 Prohibition Of Segregated Facilities FEB 1999 52.222-26 Equal Opportunity MAR 2007 52.222-27 Affirmative Action Compliance Requirements for

Construction

FEB 1999

52.222-30 Davis-Bacon Act--Price Adjustment (None or Separately Specified Method)

DEC 2001

52.222-35 Equal Opportunity for Veterans SEP 2010 52.222-36 Affirmative Action For Workers With Disabilities OCT 2010 52.222-37 Employment Reports on Veterans SEP 2010

52.222-40 Notification of Employee Rights Under the National Labor Relations Act

DEC 2010

52.222-50 Combating Trafficking in Persons FEB 2009 52.222-54 Employment Eligibility Verification JAN 2009 52.223-6 Drug-Free Workplace MAY 2001 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

AUG 2011

52.225-12 Notice of Buy American Act Requirement - Construction Materials Under Trade Agreements

FEB 2009

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright

Infringement

DEC 2007

52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds OCT 1995 52.228-14 Irrevocable Letter of Credit DEC 1999 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes APR 2003 52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002 52.232-17 Interest OCT 2010 52.232-23 Assignment Of Claims JAN 1986 52.232-27 Prompt Payment for Construction Contracts OCT 2008 52.232-33 Payment by Electronic Funds Transfer--Central Contractor

Registration

OCT 2003

52.233-1 Disputes JUL 2002 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -

Alternate I

APR 1984

52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-6 Change Order Accounting APR 1984 52.244-6 Subcontracts for Commercial Items DEC 2010 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994

52.249-2 Alt I Termination for Convenience of the Government (Fixed- Price) (Apr 2012) - Alternate I

SEP 1996

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies

DEC 2008

252.203-7002 Requirement to Inform Employees of Whistleblower Rights JAN 2009 252.203-7003 Agency Office of the Inspector General APR 2012 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A Central Contractor Registration Alternate A SEP 2007 252.204-7008 Export-Controlled Items APR 2010 252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7001 Disclosure of Ownership or Control by the Government of a

Terrorist Country

JAN 2009

252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country

DEC 2006

252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage And Disposal Of Toxic And

Hazardous Materials

APR 2012

252.225-7012 Preference For Certain Domestic Commodities JUN 2012 252.225-7031 Secondary Arab Boycott Of Israel JUN 2005 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

JUN 2012

252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment MAR 1998 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for

Military Operations

OCT 2010

52.203-14 DISPLAY OF HOTLINE POSTER(S) (DEC 2007)

(a) Definition.

United States, as used in this clause, means the 50 States, the District of Columbia, and outlying areas.

(b) Display of fraud hotline poster(s). Except as provided in paragraph (c)--

(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites--

(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and

(ii) Any DHS fraud hotline poster subsequently identified by the Contracting Officer.

(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.

(3) Any required posters may be obtained as follows:

Poster(s) Obtain from http://www.dodig.mil/hotline/hotline_posters.htm

(i) Appropriate agency name(s) and/or title of applicable Department of Homeland Security fraud hotline poster);

and

(ii) The website(s) or other contact information for obtaining the poster(s).)

(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph (b) of this clause, other than any required DHS posters.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts that exceed $5,000,000, except when the subcontract--

(1) Is for the acquisition of a commercial item; or

(2) Is performed entirely outside the United States.

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use as prescribed in section A. The time stated for completion shall include final cleanup of the premises.

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (APR 2012)

(a) Definitions. As used in this clause--

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts--

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 238190- assigned to contract number .

(Contractor to sign and date and insert authorized signer's name and title).

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

10.0% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Whiteman AFB, Missouri.

(End of provision)

52.232-16 PROGRESS PAYMENTS (APR 2012)

The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:

(a) Computation of amounts. (1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the Contractor's total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The Contracting Officer will consider cost of money that would be allowable under FAR 31.205-10 as an incurred cost for progress payment purposes.

(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due and will be paid to subcontractors--

(i) In accordance with the terms and conditions of a subcontract or invoice; and

(ii) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government.

(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless--

(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's total costs for progress payments until paid).

(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)(1) of this clause:

(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.

(ii) Costs incurred by subcontractors or suppliers.

(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.

(iv) Payments made or amounts payable to subcontractors or suppliers, except for --

(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and

(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.

(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor

(ii) the value, for…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .