amendment answering contractor questions. please acknowledge by signing and providing with offer.

View the file

Other files

File Type Posted
STATEMENT OF WORK 2 sep 09.docx DOCX document
amendment 2 as amendment 5.pdf PDF
Amendment 0002 QA.docx DOCX document
Amendment 0001 xtdend due date to 8sep09 09-R-A008.doc DOC document
RFQ 09RA008 carpet idiq solicitation.pdf PDF
presolicitation notice 09RA008.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1

QUESTIONS AND ANSWERS

8.7 Last sentence, and initial cleaning and sealing of material.

Q. Is there a Base standard for the finish?

A- No, comply with manufacturer directives.

Q. How many coats of finish shall be applied?

A- Comply with manufactures' directives.

Q. How many days extra will the Air Force give to provide this extra service?

A- None

8.8 Rubber flooring?

Q. Is there a Base Standard for the care of Rubber Flooring?

A- - No, comply with manufacturer directives.

Q. Are you currently waxing these floors?

A- No.

Q. are you going to extend the Bid Date Due to the Labor Day Holiday?

A- No

Q. Do you want a finish? If so what type?

A- Follow manufacturer’s directions

9.1 Installation

Q. Multiple questions on the certification of the foreman.

A- The installer's will be required to be certified. There will be no mandated direction to the contractors regarding foreman. Replace Paragraph 9.1 with the following:

9.1 Contractor Qualifications. All work will be performed by contractors/installers who are CFI Certified Floorcovering Installers (International Certified Floorcovering Installer Association) or manufacturer’s approved installers.