Attachment 4 Updated Statement of Objectives 29 August 2024.pdf

PDF 1 MB Posted

Attached to
10 Channel UHF Repeater Federal contract opportunity
Solicitation number
FA461324Q1059
Issued by
Department of the Air Force Global Strike Command

About this file

This document is a Combined Synopsis/Solicitation for a 10 Channel UHF Repeater Enterprise Land Mobile Radio (ELMR) upgrade project at F.E. Warren AFB, Wyoming. The U.S. Air Force is seeking a "turnkey" solution that includes new antennas, radio equipment, and installation of a 90-foot self-supporting tower and uninterruptible power supply. Required services include system engineering, site preparation, equipment installation and optimization, acceptance testing, training, and warranty.

The solicitation is set aside for small businesses under NAICS code 517111 with a 1,500 employee size standard. Quotes are due by 2pm MT on September 3, 2024. The anticipated period of performance is 210 calendar days, with 180 days or less lead time for materials and 30 days to complete the project. Quotes must include a detailed price breakdown and address compliance with the attached Statement of Objectives. Award will be made to the lowest priced, technically acceptable offer.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 4 - Statement of Objectives

FA461324Q1059

Statement of Objectives

F.E. Warren AFB, WY

Enterprise Land Mobile Radio (ELMR) 10

Channel UHF Upgrade

29 August 2024

Table of Contents

1. Scope

2. Background

3. Technical Requirements

3.1 Trunking System

3.1.1 Radio Subsystem

3.1.2 Shelter

3.1.3 Antennas

3.1.4 Fiber/Communications Path

3.1.5 Power

3.2 System Requirements

3.2.1 Coverage

3.2.2 Demarcation Points

3.2.3 Advanced Encryption Standard (AES) Encryption

3.3 Applicable Standards

3.3.1 APCO P25 Standards

3.3.2 Site Preparation Standards

4. Site Preparation Guidelines

4.1 General Guidelines

4.2 Grounding Guidelines

4.3 Lighting Protection Guidelines

4.4 Environmental Controls

4.4.1 Notification of Environmental Spills

4.4.2 Hazardous Material (HM)

4.4.3 Green Procurement Program

4.5 Anti-Terrorism……………………………………………………………………………….8

4.6 Physical Security……………………………………………………………………………8

4.7 Notification

4.8 Operation Security (OPSEC)…………………………………………………………………..8

5. Implementation Services

5.1 Schedule

5.1.1 Hours of Operation/Scheduled Events

5.2 Program Management

5.3 System Engineering

5.4 Project Status Review (PSR) Meetings

5.5 Transportation of System Equipment

5.6 Site Access Information and Visitor Control Requirements

5.7 Optimization

5.8 System Cutover

5.9 Quality Assurance (QA), Testing, and Burn-In

5.9.1 Quality Assurance

5.9.2 Factory Acceptance Test (FAT)

5.9.3 System Acceptance Test

5.9.4 RF Coverage Test

5.9.5 System Burn-in

5.9.5.1 System Burn-in Tracking Reports Support

5.10 As-Built Documentation

5.11 System Acceptance

5.12 Information Assurance

5.13 Unique Identification (UID)

5.14 Services Summary

6. Logistic Requirements

6.1 Spares

6.2 Warranty

7. Deliverable Requirements ANNEX A (Site Preparation Standards)

APPENDIX A QUESTIONS AND ANSWERS………………………………………………………………. 15

1. SCOPE

The United States Air Force (USAF) requires a "turnkey" Project 25 compliant Enterprise Land Mobile Radio (ELMR) upgrade from Motorola 5 TDMA capable VHF channels to a Motorola 10 TDMA UHF capable channels at F.E. Warren AFB, Wyoming. The upgrade is required to improve channel balancing, support coverage at the new Weapons Storage Facility area, and facilitate a relocation due to Remodel of the building housing the existing system. This project will nominally include antennas, new radio equipment and the installation of a self-supporting 90’ tower, and an uninterruptable power supply (UPS).

The contractor shall provide all personnel, equipment, installation, configuration management, labor, material, documentation, and services in support of this project. Services include systems engineering services in support of the design, system staging, site preparation/development, equipment installation and optimization, acceptance testing, training, and warranty. The contractor shall perform all necessary efforts in the completion of this project to receive site acceptance.

2. BACKGROUND

The following information is provided to assist the contractor in preparing responses to this solicitation and is for reference only. A site visit will be held on 22 Aug 2024 @ 1000 Mountain Time. The location of the site visit is 834 Parade Rd, F. E. Warren AFB, Cheyenne, Wyoming, 82005. The contractor is responsible for verifying information during the site visit.

F.E. Warren AFB is located Northwest of Cheyenne, WY. The proposed ELMR system location is at building 834. 90 CS will provide LAT/LON information to support coverage design along with the UHF frequencies authorized for the upgraded system.

3. TECHNICAL REQUIREMENTS

3.1 Trunking System:

This system shall be fully compatible with the existing Motorola trunking core and subscriber base. The system shall meet Association of Public Communications Officials (APCO) Project 25 (P25) 12.5 KHz digital narrowband radio system standard. The system shall be capable of supporting P25 Phase II (two channel TDMA) with only software or license updates. The ELMR system is running software version 2022HS. Contractor shall also provide the Cisco routing switch to integrate this expansion into the EMLR network, to include configuration of said switch.

3.1.1 Radio Subsystem:

The radio subsystem shall be designed to provide 10 channels (9 voice and 1 control). The subsystem shall be provisioned to act as defined in P25-Phase II (Two channel TDMA). The existing radio subsystem is a one rack 4 channel TDMA ELMR configuration.

3.1.2 Shelter:

Building 834 at FE Warren AFB, WY does not require a new shelter.

3.1.3 Antennas:

There is no existing tower next to Building 834 and will require the installation of a Tower (90’ Self Supporting Tower). The tower will require UHF transmit and receive antennas. The antennas will be mounted high enough to give a clear line of sight to all areas of responsibility for FE Warren AFB emergency services and mission operations personnel.

3.1.4 Fiber/Communications Path:

The contractor shall install RF cable between the ELMR equipment in Building 834 and the Tower. Cable support from Building 834 and to the Tower will be provided via cable bridge (i.e., Ice Bridge). Use this information in preparing offers. Contractor shall route/patch fiber between the existing communication network switch in Building 834 Communications Room and the new ELMR rack equipment.

3.1.5 Power:

90th Civil Engineer Squadron (CES) is responsible for providing power hookup at the proposed location of the LMR equipment and Tower location. Contractor is responsible for wiring from this demark to the building and tower.

The Contractor shall provide all electrical work required to provide electricity to ensure power connections are provided at locations where there is no power source to support the proposed equipment installation.

The 90 CS Plans and Programs Office (90 CS/SCX) will coordinate a Civil Engineer Work Request (AF Form 332) to ensure appropriate Government oversight of the Contractor’s installation. Any power work cannot be started until 90 CES approval.

3.2 System Requirements:

3.2.1 Coverage:

RF coverage testing is required since this is a new UHF system install with new antennas mounted to a new ELMR tower.

3.2.2 Demarcation Points:

The contractor shall furnish the required cable and equipment to connect to the Government’s designated circuit demarcation point. The contractor shall identify by location all demarcation points and responsibilities for both contractor and base (90 CS).

a) 90 CES Support Requirements Identify the support requirements to be provided by the host civil engineering activity and those provided by the contractor. Such as, but not limited to generators, UPS, transfer switches, load centers, HVAC (Heating Ventilation and Air Conditioning) work, and any identified GFE equipment.

Power demarcation Circuit breaker/Outlet reservation Required power by rack location.

Modifications to or relocation of existing equipment New equipment installation (space and rack reservation) Soil analysis of proposed tower location

b) Communications-Computer Systems Support Requirements Identify support requirements to be provided by the host communications-computer systems activity and those provided by the contractor. Such as, but not limited to fiber and copper demarcation and count, network support, and any GFE equipment identified for reuse.

Fiber demarcation, count, and termination type Copper demarcation and count Rack location Cable ladder and cable management

3.2.3 Advanced Encryption Standard (AES) Encryption:

All AES Encryption hardware and software/firmware shall be certified, in accordance with current NIST and NSA requirements.

3.3 Applicable Standards:

The system shall comply with the following standards: In the event the standard has been updated, the contractor shall comply with the most current version of the published standards.

3.3.1 APCO P25 Standards:

The radio system shall comply with the TIA/EIA guidance given in EIA/TIA 102 Land Mobile Communications Radio Land Mobile Communications Radio Standards (APCO Project 25): The latest version of this document may be obtained from http://www.tiaonline.org.

3.3.2 Site Preparation Standards:

Site preparation is anticipated to be required in support of this system. All civil work shall be performed in accordance with the following documents and standards given in ANNEX A (Site Preparation Standards). Note: Specific vendor installation criteria are given as reference.

All site preparation/development and equipment installation will be conducted in accordance with R-56, industry standards, local, state, and federal/country codes. Work sites will be neat and maintained daily to prevent unsafe or hazardous conditions from developing.

Components that are no longer needed, or superseded, due to system upgrades will be removed and relocated to an on-site storage facility as determined by the 90 CS PM. All associated cables/connectors will also be removed from cable racks and system trays.

The contractor shall provide rack diagrams, rack labeling, cable labeling, and floor plan layouts, and document any changes to the planned system installation and any issues that occur, along with their resolution (CDRL A001) (CDRL A003). The contractor shall update any drawings, diagrams, and floor plans of provided GFE that is altered due to equipment installation.

4. SITE PREPARATION GUIDELINES

Unless otherwise identified in Demarcation, the contractor shall be responsible for all necessary site preparation/development. Site preparation includes all site work, building modifications, electrical wiring, AC Power, and grounding systems.

4.1 General Guidelines:

The contractor shall meet the following minimum Government guidelines:

Connect the new equipment to the existing AC electrical service without disconnecting existing loads. If sufficient spare capacity is not available, the contractor shall install sufficient AC electrical receptacles and circuits from an existing electrical panel to support the ELMR equipment.

4.2 Grounding Guidelines:

If required by the proposed technical solution, the contractor shall meet the following minimum Government guidelines: In the event of a conflict between the following and National/State code, National/State code shall supersede.

The contractor shall ensure that all equipment is electrically bonded, grounded, and protected in accordance with the National Electric Code.

The contractor shall provide all grounding and lightning protection equipment, including surge arrestors, to comply with the requirements of all equipment being installed and connected as part of the system.

A single point ground system shall be used, whenever possible, and approved by the site manager, on all equipment installed as part of the system. The single point ground system installed within equipment shelters or buildings shall be connected to the exterior building/tower ground system.

The antenna support structure/tower must be bonded to the external ground system using an exothermic weld, if permitted by the tower manufacturer.

All grounding conductors that compose the external ground system shall be connected using exothermic welding and cable size to ground rods and interconnection between rods shall be a minimum of 1/0.

Transmission lines shall be grounded with proper sized ground kits connected to the tower ground and building entry bus.

New grounding systems shall be installed in accordance with the National Electrical Code and applicable best industry practices and standards. All external ground rings, copper ground rods, chemical ground rods, and interconnecting copper conductors must be buried to a minimum depth of 30 inches, or 6 inches below the freeze line for the area, whichever is greater.

4.3 Lightning Protection Guidelines:

If required by the proposed technical solution, the contractor shall meet the following minimum Government guidelines:

Lightning protection shall be provided for the building, tower and all significant metallic structures IAW the NFPA 780 Standard for Installation of Lightning Protection Devices.

4.4 Environmental Controls:

The contractor shall be knowledgeable of and comply with all applicable Interstate, federal, state, and local laws, regulations, and requirements regarding environmental protection, to include Section 01 57 19.05 32, Environmental Protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost because of the change, the contractor shall inform the CO pursuant to notice requirements and negotiate a modification to the contract.

4.4.2 Notification of Environmental Spills

If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to the F.E. Warren AFB Fire Dept at 911 (landline) or 307-773-2931 (cell phone). The liability for the spill or release of such substance(s) rests solely with the contractor and its agent.

4.4.3 Hazardous Material (HM): If hazardous materials will be used in the execution of this contract, the contractor shall comply with all federal, state and local regulations concerning the use, storage, and reporting of HM in accordance with AFMAN 32-7002, Environmental Compliance and Pollution Prevention. The contractor shall be required to obtain authorization per the Installation Hazardous Materials Management Program before ordering or purchasing any hazardous product and may not bring a HM onto F.E. Warren AFB property, nor use a HM, until the contractor receives all required authorizations. This authorization process may take up to three weeks. . The contractor shall provide the information listed in Attachment 1 of Section 01 57 19.05 32 to request authorization for all hazardous materials proposed for use on FE Warren AFB or the missile field.

4.4.4 Green Procurement Program: In performance of this contract, contractors shall use Environmental Protection Agency (EPA) designated recycled content products, Information Technology (IT) Energy Star products/appliances, Federal Energy Management Program (FEMP) Designated Energy Efficient Low Stand By Power products/appliances, U.S.

Department of Agriculture (USDA) Bio based/Bio preferred products, Environmentally preferable products, Electronic Product Environmental Assessment Tool (EPEAT) registered products, Water Sense or other water efficient products, non- or Low Ozone depleting substances under the Significant New Alternatives Policy (SNAP), non or Low toxic or hazardous constituents (e.g. non-VOC paint) and any other environmentally sustainable product/method, to the greatest extent possible.

4.5 Anti‐Terrorism:

If the Contractor (contract employees/subcontractors) identify any suspicious activity, they shall immediately contact the Base Defense Operations Center (BDOC) at 307-773-3501 (on-installation)/Missile Security Control (MSC) at 307-773-2701 (off-installation) and notify the CO and 90 CS/PM that they contacted the BDOC and/or MSC.

4.6 Physical Security:

The Contractor shall be responsible for all contractor property on Government property. At the close of each work period, Government facilities, Contractor property, and Contractor materials shall be secured.

The Government shall not be held responsible for any loss experience by the contractor resulting from theft or vandalism.

4.7 Notification:

If the Contractor (contract employees/subcontractors) identify any suspicious activity, they shall contact the Base Defense Operations Center (BDOC) at 307-773-3501 (On-installation)/Missile Security Control (MSC) at 307-773-2701 (Off-installation) and notify the CO and COR (if appointed) that they contacted the BDOC and/or MSC.

4.8 Operational Security (OPSEC).

The contractor shall adhere to the following minimum requirements in support of this requirement:

4.8.1 Contractor personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Official Business, controlled unclassified information (CUI) may only be transmitted as directed in the PWS.

4.8.2 The Contractor shall not post to company websites, publications, newsletters or other media any images, data or information that reveal sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, company press releases related to this contract should be coordinated through the Project Manager or Contracting Officer, as applicable.

4.8.3 Because observation of events, operations, physical changes, etc. may reveal National Security information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. (Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC § 793.) Therefore, contractor personnel shall not disclose to unauthorized third parties, post to unofficial sites (including Social Networking sites) any images, data or information, or observed events that reveal sensitive government operations, personnel, equipment, including, but not limited to:

4.8.3.1 Tactics, techniques and procedures, production or work schedules, any visible or concealed modifications, upgrades, additions to vessels, aircraft, or weapons or equipment;

increases, change, or decreases in work/deployment frequency or government personnel, vehicle, vessel or aircraft movements; specialized equipment orders, deliveries, shipments, etc., Unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract shall be reported immediately to the 90 CS/PM and/or CO, as applicable.

4.8.3.2 Government issued badges, identification shall be removed and/or concealed from plain sight when off base and shall not be left in vehicles or unprotected. Badges and passes may not be duplicated, copied or loaned to others. Lost or stolen identification badges, vehicle passes etc.

shall be immediately reported to the Project Manager, Contracting Officer, and/or installation Security Office.

4.8.4 Network Infrastructure (Manhole Duct System (MHDS), Manhole/Hand Hole (MH/HH) locations, fiber paths, etc.) is on the 90 CS Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “Controlled Unclassified Information (CUI),” and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the contractor shall develop an OPSEC plan, and present to 90 CS/PM within ten (10) working days before start of project to ensure the protection of Controlled Unclassified Information (CUI) data either furnished by the government or produced by the contractor.

5. IMPLEMENTATION SERVICES

5.1 Schedule:

The offeror shall provide a detailed working schedule for accomplishing the requirements of this SOO which includes all Government activities, e.g., IA activities and network connectivity. The schedule shall identify all critical milestones and deliverables for the final design, integration, installation, and testing of the system. The milestones and schedule shall be described with reference to days after receipt of award.

(CDRL A002)

5.1.1 Hours of Operation/Scheduled Events:

The Contractor shall perform the services required under this contract during normal duty hours of the facility where work is being performed. At F. E. Warren AFB, WY normal duty hours are Monday-Friday, 0700 – 1600 MST. Any other work schedule outside of normal duty hours requires 90 CS/SCX and Contracting Officer (CO) approval. The Contractor shall not perform work under this contract on federal Holidays or site-unique down-days unless expressly authorized by the CO.

Part or all of the facility may be occupied during this effort. Contractor shall accomplish the installation with minimum disruption of daily office activities. If performance of work outside normal duty hours will be required to meet the scheduled dates stated above, include desired working hours in the Proposal.

5.2 Program Management:

Program Management shall be provided throughout the design and implementation of the system.

5.3 System Engineering:

Systems engineering services shall be provided from the preliminary system design through the completion of system implementation, security evaluation, and functional testing. As a minimum, system engineering services shall include the following:

System design System architecture development Frequency analysis and planning Coverage analysis Fleet map/talk group development and Database Entry Console programming Implementation support (design synthesis) Acceptance testing, to include coverage testing.

All IA activities as identified in this document.

Final (as-built) system documentation

5.4 Project Status Review (PSR) Meetings:

The contractor shall participate in weekly (or as decided by the integrated product team (IPT)) PSR meetings. The contractor shall include any existing action items for both the Government and contractor.

(CDRL A004)

5.5 Transportation of System Equipment:

The Government will provide a “Ship-to” address and temporary storage/staging area. The contractor shall be responsible for inventory and reconciliation of all shipments, which will be coordinated with and verified by a Government representative. The contractor shall transport all equipment from the temporary storage area to the final destination.

5.6 Site Access Information and Visitor Control Requirements:

The contractor shall coordinate all site visits through the 90 CS POC. The contractor shall provide all necessary site visit information at least 10 business days prior to any site visit by any contractor or subcontractor. The contractor shall coordinate all deliveries with the 90 CS POC at least 10 Business days prior to delivery and provide any site visit information required for the delivery. This will ensure visit clearances can be obtained from the local Security/Visitor Control Office.

5.7 Optimization:

The contractor shall optimize all RF equipment after system installation is completed to ensure optimal performance and reliability.

5.8 System Cutover:

The contractor shall develop a cutover plan in coordination with 90 CS POC and AFGSC ELMR Program Manager. The plan shall provide for an orderly, cost-effective transition of all ELMR users to the new system with minimal disruptions to operations and end users. Soft cutover means that the existing system shall be operational until the new ELMR system is completely cutover. Complete talk groups shall be moved intact into the new system. (CDRL A006)

5.9 Quality Assurance (QA), Testing, and Burn‐In:

5.9.1 Quality Assurance:

The contractor shall provide a Quality Assurance Evaluator (QAE) for the entire life of the project. The QAE shall assist the government representative in performing random spot checks and in performing the system acceptance tests. The QAE shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A Status Report will be submitted, indicating project progress/statuses and listings any deficiencies/discrepancies found and actions to correct them. (CDRL A003)

5.9.2 Factory Acceptance Test (FAT):

A Factory Acceptance Test will be required as this is a new system install with a UHF frequency range.

5.9.3 System Acceptance Test:

The Contractor shall provide the Acceptance Test Plan for the system. (CDRL A006)

System Acceptance Test shall include:

Operational testing of the features and functions described in this document.

System alarming, monitoring, and fault management as it pertains to the ability to diagnose, monitor, and maintain the system.

All equipment installed by the prime contractor or its sub-contractors.

Load test of battery sufficient to demonstrate that the facility will operate for a minimum of two days without power.

Failover testing of generator (if provided)

The contractor shall have 15 Business days after completion of the System Acceptance Testing to research, develop, and document the resolution of all discrepancies. The contractor shall provide in writing a detailed explanation to the Government engineer/ELMR Project Leader/QA representative of how the discrepancy will be resolved including any changes to the radio programming or the system data bases. (CDRL A003). Upon direction of the LMR Project Leader, the contractor shall implement the proposed resolution and perform the portion of the System Acceptance Test that previously failed.

5.9.4 RF Coverage Test:

The contractor shall conduct RF coverage testing since the new system and new antennas will be installed at a new location (Building 834).

5.9.5 System Burn‐in:

The Government reserves the right to refuse start of 30-day burn-in until all discrepancies have been resolved to the satisfaction of the Government. The Government will review all test results and prepare the official list of discrepancies, if any. The contractor shall support this effort by submitting his/her own list of discrepancies based on discrepancies detected/identified during testing and/or inspections conducted by either the contractor or the Government QA representative.

The contractor shall perform a 30-day Operational Test of the system. The 30-day equipment burn-in will not start until the system has successfully passed all of the tests in the system Acceptance Testing Process, all QA discrepancies have been resolved, the IA effort is complete, and Government approval has been provided from the 90 CS POC. If any major failure occurs during the 30-day burn-in, the test shall be terminated, corrective action shall be taken and approved, and the entire 30 days shall be restarted. If any minor failure occurs during the 30-day test period, the testing period may resume after resolution of the problem. The contractor shall document in detail any discrepancies that occur during testing. (CDRL A005)

5.9.5.1 System Burn‐in Tracking Reports Support:

The contractor shall support the site in tracking any problems during the System Burn-in. As a minimum, the contractor’s responsibilities shall include, answering called-in trouble calls, creating trouble tickets and logs, providing tracking reports for active and closed tickets, answering questions, and correcting any system deficiencies that are identified. The 90 CS POC will prioritize the trouble calls.

5.10 As‐Built Documentation:

The Contractor shall provide full documentation on the installed system within 30 business Days after Project Completion. This documentation shall contain user and maintainer documentation for newly installed equipment. (CDRL A001)

5.11 System Acceptance:

Formal system acceptance shall be granted after completion of the acceptance test and a successful 30-day equipment burn-in period. Final acceptance shall require at a minimum:

Completion of all facility work, system, component, hardware and software delivery, installation, testing, optimization, phased integration, and as built documentation.

Acceptance of system facilities, individual systems, and equipment by Communications Squadron ELMR and management personnel. Correction of any operational, performance, or workmanship defects shall be at the sole expense of the contractor.

Successful completion of System Acceptance Testing. Failure of any tests during the system acceptance test will delay the start of the 30-day burn-in period until all tests have passed.

Successful completion of the RF Coverage testing. Failure of the new ELMR system to provide the required coverage will delay the start of the 30-day burn-in period until any RF coverage issues are resolved to the satisfaction of the Government.

Successful completion of the IA certification.

Successful completion of the 30-day burn-in period.

5.12 Information Assurance:

The RF System is an extension to the IA certification of AFGSC ELMR. The vendor shall work with appointed representatives to ensure the system is fully documented and compliant with IA controls.

The Contractor shall develop and process necessary Assessment and Authorization packages IAW AFI 17- 101, Risk Management Framework (RMF) for Air Force Information Technology (IT), Air Force Certification and Accreditation Process (AFCAP), DoDI 8500.01 Cybersecurity, 8510.01 Risk Management Framework (RMF) for DoD Information Technology (IT). The result of this action should result in the issuance of an ATO by the IS appointed Authorizing Official (AO). Firmware shall be current and approved IAW AF EPL. The IS shall meet all required Information Assurance Controls.

5.13 Unique Identification (UID):

The Office of the Under Secretary of Defense for Acquisition Technology and Logistics developed a Defense Procurement and Acquisition Policy for unique identification (UID). The requirement affects all delivered items for which the Government’s unit acquisition cost is $5,000 or more.

The contractor shall apply physical unique item identifiers (UII) in the format specified in referenced DFARS clause. The required information includes, but is not limited to:

(1) Concatenated UII or DoD recognized unique identification equivalent.

(2) UII type

(3) Issuing agency code

(4) Enterprise identifier

(5) Original part number

(6) Lot or batch number

(7) Current part number

(8) Current part number effective date

(9) Serial number

(10) Unit of measure

(11) Description

The contractor shall apply physical UIIs to all equipment with a unit acquisition cost of $5,000 or more that is procured through this requirement. Contractors shall also register the UIIs in the item unique identification (IUID) Registry. The vendor shall provide a detailed description of how the requirement of DFARS policy and clause 252.211-7003 will be accomplished with work schedule, including a description of how the vendor will provide verification that the reporting requirement has been met.

5.14 Services Summary:

The contractor service delivery requirements are summarized into performance objectives that relate directly to standards of performance required to meet mission essential needs. For the Performance Objectives to be met, service delivery must be in substantial compliance with applicable performance standards. The Performance Threshold describes the minimum overall levels of service delivery required for acceptable quality control. Failure to meet these Performance Thresholds means that contractor Quality Control is unacceptable. The following is a list of the key performance objectives that shall be verified as contractually compliant by Government personnel; however, inspection of any contract requirement is authorized.

Performance Objective

PWS

Para.

Performance Threshold Method of

Surveillance

Turnkey Proposal

1.

Provide a proposal with all items considered.

100% review

Tower Installation 3.1.3 Proposal for tower install with description of intended procedures 100% review

RF Coverage 5.9.4 RF Coverage Test 100% review

6 LOGISTICS REQUIREMENTS

6.1 Spares:

The contractor shall propose as separate line-items, all necessary spares for their system.

6.2 Warranty:

The contractor shall provide a one-year warranty or manufacturer’s standard commercial warranty, whichever is longer. The warranty shall commence at the date of final system acceptance.

7 DELIVERABLE REQUIREMENTS

All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables:

CDRL Data Item Title Due Date Due to

A001 As-Built Documentation At Project Completion / Acceptance

COR/90CS SCXP

A002 Work Schedule Submitted with proposal COR/90CS SCXP A003 Status Report Bi-weekly COR/90CS SCXP

A004 Meeting Minutes After Meetings COR/90CS SCXP

A005 Installation Test Report 10 business days after Acceptance Test Plan (ATP) Completion

COR/90CS SCXP

A006 Test Plan/Report 2 weeks prior to installation completion

COR/90CS SCXP

ANNEX A (Site Preparation Standards)

American National Standards Institute (ANSI/EIA/TIA-222-H), Structural Standards for Steel Antenna Towers & Antenna Supporting Structures, June 2018

National Fire Protection Association (NFPA) 780, Standard for Installation of Lightning Protection Devices, 2023

NFPA 70 National Electrical Code (NEC) 2023 FAA Advisory Circular 70/7460-1M, Obstruction Marking and Lighting, 16 November 2020 FAA Advisory Circular150/5345-43F, Specification for Obstruction Lighting Equipment, 11 March 2019 Motorola R56 Standard rev 2005, “Standards and Guidelines for Communications Sites”

APPENDIX A

Questions and Answers

29 August 2024

1. What is the tower distance from the building?

a. 50’

2. Type of tower to be used?

a. Composite Pole with internal grounding and Transmission Line feeds.

3. Is there tower lighting?

a. No

4. We doing anything for access road like laying gravel?

a. Not required for this project.

5. What are the testing requirements?

a. Optimize all RF equipment after system installation to ensure optimal performance and reliability. Time and synchronize the network among the dispatch consoles, the management terminals, and the RF site to ensure maximum system reliability.

6. Are installing a fence – what size?

a. Fence is not required for Composite Pole.

7. Soil/Ground Remediation?

a. Not sure if there is a contaminated soil concern or just to spread topsoil and replant with native grasses. If the latter, attached is our seed mix (See Attachment 7).

8. Spoils – Spread on site or removed?

a. Depending on quantity/type but they might be able to slope to grade and spread on site.

9. Frequency pairs?

a. Provided upon contract award

10. Who is responsible for soil testing?

11. Environmental study? – Who is responsible?