This is a Statement of Work (SOW) for water slide removal and installation services at Barksdale Air Force Base, updated April 16, 2026, under contract number FA460826QS026.
The contractor is responsible for removing existing water slides from the Main Base Pool (located at 2938 Daedalus Avenue, Barksdale AFB, LA) and installing four new Flum brand slides with an attached climbing structure. The new slides include: a 72-foot yellow spiral slide starting at 18 feet high, an 18-foot green curved slide, a 16-foot red curved slide, and a 12-foot blue curved slide. The new slides must be installed to meet OSHA standards. Installation must occur during the off-season between Labor Day and Memorial Day. The contractor must provide all personnel, equipment, tools, supervision, and services necessary for completion, including removal and disposal of existing slides, inspection and replacement of existing hardware as needed, and maintenance of a clean and organized work area with proper hazardous waste disposal procedures.
Security and conduct requirements include obtaining visitor passes through 2SFS/SFA Form 74, complying with base traffic regulations, prohibiting weapons and firearms, safeguarding government property, managing records per Air Force Instruction 33-322, 33-363, and 33-364, implementing an OSHA-compliant safety plan with mandatory personal protective equipment, and reporting all accidents and incidents to the Main Base Pool Point of Contact and Department of Labor as applicable. The contractor must retrieve all identification media from departing employees and cooperate fully with government accident investigations if required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
MAIN BASE POOL WATER SLIDE REMOVAL & INSTALLATION
updated April 16, 2026
FA460826QS026
Attachment 1
Description of work:
Scope of Work. Contractor will remove the existing water slides from the pool and then install new waterslides in their place.
Place of Performance. At the Barksdale Air Force Base Main Base Pool: 2938 Daedalus Avenue, Barksdale AFB, LA.
Background: Barksdale AFB is completing a renovation to update the existing pool facilities to update the safety and appearance of the existing pool.
Discussion: Contractor will be removing the current water slides from the pool deck and installing new waterslides in their place to ensure the installation meets OSHA standards.
Removal of Existing Slides: Contractor will be responsible for the removal and disposal of the existing slides.
Installation of New Slides: The new slides will be installed into the existing hardware on the pool deck. Contractor will be responsible for ensuring the existing hardware is in good condition and replacing any hardware needed.
Equipment and Supplies: The contractor shall provide all personnel, equipment, tools, supervision, and other items and/or services necessary for water slide removal and installation.
Slide Replacement: Contractor will provide and install a new 4 Flum slide with an attached climbing structure.
Slide1 – Seventy-two feet (72’) long spiral slide starting at eighteen feet (18’) high,yellow
Slide 2- Eighteen feet (18’) high curved slide, green
Slide 3 – Sixteen feet (16’) high curved slide, red
Slide 4 - Twelve feet (12’) high curved slide, blue
Further details can be found in Attachment 3 – Salient Characteristics
Time Frame: Installation services will take place during the off season, between Labor Day and Memorial Day.
Work Area: Work area should be kept in an organized and clean manner.
Waste Disposal:
Follow proper procedures for waste disposal, including hazardous materials Security Requirements:
Visitor Passes: To receive a visitor, pass the contactor much complete a 2SFS/SFA Form
74, and fax that form to the Contract Administrator. This form will be sent to the successful offer or upon request. This information will be reviewed and forwarded to the passing office. If a pass is approved, the Commercial Visitor Control Center will issue a SFMIS AF Form 75 (Visitor Pass) to the contractor and his/her employees
FA460826QS026
Attachment 1 Page upon completion of screening process for the duration of the contract. The screening process takes time, and the contractor shall visit the Commercial Visitor Control Center prior to expecting base entry to receive the required forms and instruction on the application process (to include estimated time of receiving the visitor pass). Although contractors will not be issued vehicle passes, vehicles will be subject to search while on the installation.
Employees privately owned vehicles will not be allowed access to the restricted/controlled areas without a free zone being established. Company vehicles will be allowed access to restricted/controlled areas. All Contractor vehicles should have marking with the company name for quick identification of ownership and notification if they are involved in an incident.
Conduct Requirements: The contractor shall ensure that his/her employees comply with all base traffic regulations and properly conduct themselves while on the base.
Retrieving Identification Media: The Contractor shall be responsible for retrieving all identification media including vehicle passes from employees who depart for any reason before the contract expires (e.g., terminate for cause, retirement, etc.).
Traffic compliance: The contractor and contractor employees shall comply with base traffic regulations.
Weapons, Firearms, Ammunition: Contractor employees are prohibited from possessing weapons, firearms, and ammunition on themselves or within their contractor or privately owned vehicles while on base.
Safeguarding government property and materials: The Contractor shall be responsible for safeguarding all government property, and controlled forms provided for contractor use. At the end of each work period, Contractor shall secure all Government facilities, equipment, and materials.
Records Management: The Contractor shall manage all data created for Government use or legally controlled by the Government, in support of the functional activity or required by AF publication, IAW with the AF Records Management procedures in Air Force Instruction (AFI) 33-322, Air Force Manual (AFMAN) 33-363 and Air Force Instruction (AFI) 33-364 (or their subsequent replacements)
Safety: The Contractor shall have a safety plan for their employees that meets Occupational Safety and Health Administration Standards. The Contractor shall instruct each employee in the recognition and avoidance of unsafe conditions and regulations to his or her work environment to control or eliminate any hazards or other exposure to illness or injury. The Contractor shall provide their employees appropriate Personal Protective Equipment (PPE) and mandate proper wear.
Accident/Incident Reporting and Investigation. Contractor shall record and report to the Main Base Pool POC all available facts relating to each instance of accidental damage to Government property or injury to either Contractor or Government personnel. The contractor is responsible for contacting the Department of Labor regarding injuries and/or death of contract personnel. Check with 2 CONS for the precise wording for contract requirements. The Contractor shall secure the accident scene and wreckage until released by the accident investigative authority through the Main Base Pool POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
End of Statement of Work