Attachment 2 - Performance Work Statement.pdf
PDF 172 KB Posted
- Attached to
- Paxton Locks Federal contract opportunity
- Solicitation number
- FA460825QS032
About this file
This Performance Work Statement (PWS) details the installation of a Paxton Access Control System for the 2nd Security Forces Squadron at Barksdale Air Force Base. The project requires installing 15 Paxton Access Control Units (ACUs) and Net2 Plus POE keypads at various door locations in Building 6000, including electric strikes and associated hardware. Key requirements include using a Paxton certified installer with minimum 3 years of experience, providing 3 references from similar completed jobs, and ensuring all parts are new and compatible with the existing Paxton system.
The installation involves mounting ACUs, keypads, and wiring to specified triggers and locations as determined by the facility manager. The contractor must complete the work within 30 days after the award date, following normal duty hours (0700-1630 M-F), with potential for adjusted hours if approved. The total materials list includes 1 US Net2 Pro Software package, 15 units each of cabling, Net2 Plus with POE, and Proximity Keypads, along with 15 electric strikes and 2 PoE injectors. The project is set aside for 100% small businesses, with a size standard of $25.0M, under solicitation number FA460825QS032.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 04 - FA460825QS0032 - Paxton Locks.pdf | ||
| Combined Synopsis.pdf | ||
| Amendment 03 - FA460825QS0032 - Paxton Locks.pdf | ||
| Amendment 01 - FA460825QS032 - Paxton Locks.pdf | ||
| Combined Synopsis.pdf | ||
| Amendment 02 - FA460825QS032 - Paxton Locks.pdf | ||
| Amendment 01 - FA460825QS0032 - Paxton Locks.pdf | ||
| Attachment 1 - Provisions and Clauses.pdf | ||
| Attachment 3 - Wage Determination.pdf | ||
| Combined Synopsis.pdf | ||
| Attachment 2 - Performance Work Statement.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA460825QS032
Attachment 2
Performance Work Statement 23 June 2025
Install Paxton Access Control in Security Forces Building (Bldg. 6000)
OBJECTIVE: Install turn-key Paxton Access Control System throughout Bldg. 6000 as outlined below.
All parts shall be new, used or refurbished strictly prohibited. Parts and pieces must be compatible with existing Paxton system.
QUALIFICATIONS:
1. Paxton certified installer with minimum 3 years of experience.
2. Provide (3) references from recently completed similar jobs.
SCOPE OF WORK:
1. Install (15) Paxton Access Control Units (ACU’s) and Net2 Plus POE keypads at door locations where Facility Manager deems necessary
2. Install Electric Strikes where needed
3. Proposed ACU locations will be discussed with the facility manager prior to doing any installations.
4. The Contractor shall be responsible for all painting required following the installation of equipment.
MATERIALS
1. Parts to be used:
Nomenclature/Part# UI Qty US Net2 Pro Software (To be turned over to 2 SFS) EA 1 Cabling and Misc Hardware EA 15 US Net2 Plus with POE EA 15 US Proximity Keypad KP75 EA 15 Electric Strike HES 9600 EA 9 Electric Strike HES 9600 EA 6 Black Box Network Services - supplies plug-and-play PoE injectors to power wireless access points for door systems without network reconfiguration LPJ016A-T-R2
EA 2
2. Submittals required on all parts and pieces.
3. An area will be provided on or near work site as required to store contractors LOM.
SPECIFICS:
1. Install ACU, keypad and wire to MLR trigger provided by customer at the Facility Manager’s requested locations.
2. Install ACU, keypad and wire to ET provided by customer at Facility Manager’s requested locations.
3. Cut-in electric door strikes (ES’) and install ACU, keypad and applicable wiring harness at Facility
Manager’s requested locations.
4. There’s no old equipment to be removed from new ACU install locations.
5. Facility ceilings are suspended type.
6. No computers required.
7. No UPS’s required.
8. No CAD design required.
FA460825QS032
Attachment 2
INSTALLATION
1. Each ACU installation location shall be discussed and approved by the facility manager prior to install.
2. Installation will be done in a neat and professional manner, to include but not limited to the use of mounting hardware and cable management.
3. Any damage to the facility caused by the contractor will be repaired by the contractor in conjunction with 2 CES.
INSPECTION, TESTING and CERTIFICATION:
1. Each install location will be tested by 2 SFS facility manager to verify 100 percent serviceability.
WORKSITE LOCATION:
1. 1200 Chappie James Rd
(B6000) Barksdale AFB, LA 71110
2. Contractor Working Days/Hours:
a. Normal duty time M-F, 0700-1630
b. Days and hours can be adjusted as required with prior approval from 2 CONS and 2
SFS 48 hrs prior to a proposed change.
2 SFS Shall:
1. Coordinate contractor base access as required to complete project.
PERMITS:
1. No permits required for this project.
PERIOD OF PERFORMANCE:
1. Completed NLT thirty {30) days after period start date.
2. 2 CONS and contractor will determine award date when funding becomes available
ACRONYMS
1. POE Power over Ethernet
2. ES Electrified Strike
3. EL Electrified Lock
4. ET Electrified Trim
5. MLR Motorized Latch Retraction
| QUALIFICATIONS: |
| SCOPE OF WORK: |
| MATERIALS |
| SPECIFICS: |
| INSTALLATION |
| INSPECTION, TESTING and CERTIFICATION: |
| WORKSITE LOCATION: |
| 2 SFS Shall: |
| PERMITS: |
| PERIOD OF PERFORMANCE: |
| ACRONYMS |