Exh A CDRL List Rev 1 Mar 2012.doc

DOC document 54 KB Posted

Attached to
FA4600-11-R-0012 NIDS III A011
Solicitation number
FA4600-11-R-0012
Issued by

About this file

NIDS III Exhibit A CDRL List

View the file

Other files

File Type Posted
A016.doc DOC document
A015.doc DOC document
Atch_14 _Pricing_Model_Rev5_14Mar13.xlsm XLSM spreadsheet
Atch_14_Pricing_Model_Rev3_A013_12Mar2013.xlsm XLSM spreadsheet
A013.doc DOC document
Atch_14 _Pricing_Model_Rev2_A012.xlsm XLSM spreadsheet
A012.doc DOC document
A011.doc DOC document
Amend_A010.doc DOC document
CDRL A013 Rev1.docx DOCX document
A009.doc DOC document
A008.doc DOC document
A007.doc DOC document
A007 Q A.docx DOCX document
FA4600-11-R-0012-0006.doc DOC document
FA4600-11-R-0012-0006 Conformed.doc DOC document
Atch 1 PWS Rev 2.doc DOC document
A005.doc DOC document
Atch 14 Pricing Model Rev1 A004.xls XLS spreadsheet
Atch 17 Representative SCRs Worksheet Rev 1.xlsx.xls XLS spreadsheet
Atch 3 DD 254 Rev1.doc DOC document
A004.doc DOC document
Atch 1 PWS - 10 May 12.doc DOC document
Atch 5 Incentive Fee Plan Rev 10 May 12.doc DOC document
11-R-0012 0003.doc DOC document
11-R-0012-A002.doc DOC document
Atch 17 Representative SCRs Worksheet 3Feb12.xlsx XLSX spreadsheet
Atch 19 Priced Option SCR Worksheet.xlsx XLSX spreadsheet
11-R-0012-0001 23April12.doc DOC document
Atch 14 Pricing Model Rev1 A001.xls XLS spreadsheet
Atch 15 DOL OFCCP EEOC clearance.doc DOC document
Exh B CDRLS-DD Fm 1423 —
Atch 17 Representative SCRs Worksheet 3Feb12.xlsx XLSX spreadsheet
Exh C CDRL Matrix.docx DOCX document
Atch 16 SOO Task Order V2.docx DOCX document
Atch 4 AP2 BMOA.doc DOC document
Atch 11 PP Tracking Record.docx DOCX document
Atch 1 PWS - 9Apr12.doc DOC document
Atch 10 PP Questionnaire.docx DOCX document
Atch 9 PPQ cover ltr.docx DOCX document
FINAL RFP 9APR12.doc DOC document
Atch 3 DD 254.doc DOC document
Atch 12 Subcontracting Teaming Partner Consent Ltr.docx DOCX document
Atch 14 Pricing model.xls XLS spreadsheet
Atch 5 Incentive Fee Plan Revised 13Mar12.doc DOC document
Atch 8 PP Information Doc.docx DOCX document
Atch 7 PPQ Cross Ref Matrix.docx DOCX document
Atch 2 GFE LIST.docx DOCX document
Atch 6 NCIC Data Letter.doc DOC document
Atch 13 Client Authorization Ltr.docx DOCX document
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSED

Contract:

EXHIBIT A – Contract Data Requirements List (CDRL)

CDRL#
TITLE
PURPOSE
FREQUENCY
USER
A001
Program Management Plan (PMP)
Defines program goals and objectives, specifies how they will be achieved, resource allocation, and associates budget and timelines for completion. Includes the processes for risk management, configuration management, information assurance and quality assurance.
Initial Delivery = 60 days after contract Award – updates When revised
PM

A002

Integrated Master Schedule (IMS)
Contains the networked, detailed tasks necessary to ensure successful program execution. Contains the contract milestones, accomplishments, and discrete tasks/activities from contract award to completion of the contract.
Initial Delivery = 60 days after contract Award – updates When revised
PM
A003
Software Development Plan (SDP)
Describes plans for conducting software development efforts.
Initial Delivery = 60 days after contract Start – updates When revised
PM
A004
Data Accession List (DAL)
Provides a medium for identifying contractor internal data which has been generated by the contractor in compliance with the work effort described in the PWS or TO. The DAL is an index of the generated data that is made available upon request.
As required by Government.
PM
A005
Software Requirements Specification (SRS)
Specifies the requirements and the methods to be used to ensure each requirement has been met. Provides the basis for design and qualification testing.
End of Government Test and Evaluation (GDT&E) – Subsequent submission = When system or subsystem baseline is changed and delivered and at the start of Contractor Development Test and Evaluation (CDT&E). A complete and comprehensive SRS is required 30 days prior to the end of the contract.
PM
A006
Software Test Plan (STP) / Software Test Description (STD)
Describes the overall plan, test preparations, test cases, and test procedures to be used to perform qualification testing.
Concurrent with beginning of Contractor Development Test and Evaluation (CDT&E). – Based on the magnitude of the change, the Government shall determine if a new document must be issued or if the current version can be updated.

PM

A007
User Manuals

· Software User Manual (SUM)

· Mission Analysis Software (MAS) User Manual

Mission Analysis and Validation Simulation (MAVS) User Manual Provides functionality for users on-line and in hardcopy

When baseline changed
PM
A008
Software Test Report (STR)
Records contractor testing results.
Initial delivery – 30 days after Contractor Developmental Test & Evaluation (CDT&E), concurrently 30 days after CDT&E completion. Based on the magnitude of the change, the Government shall determine if a new document must be issued or if the current version can be updated.
PM

A009

Software Version Description (SVD) includes:

· Software Change Request (SCR) List

Software Change Request (SCR) List and/or SCR Analysis Report

Provides a full identification of the system and description of all changes for each version delivery.
When baseline changed and delivered at the end of GDT&E

Additional SCR List and/or SCR Analysis Report: When requested

PM

A010
Training Materials
Provides formal and informal training on the use of the application. Materials include course outlines, lesson plans, training guides, handouts, and other support material.
Initial delivery – Due 60 days after start of contract.

Then concurrent with completion of CDT&E (when revised)

PM

A011
Program Management Review (PMR) Package

· PMRs

· TIMs

· ITRs

· PDRs

· CDRs

· Others as requested

Provides meetings and reviews agendas, minutes, and action items.
Agendas are due 10 working days prior to each event; minutes and action items 10 working days after the event
PM

A012

Monthly Activity and Progress Report
Provides monthly report of contractor activities, deliveries, upcoming events, Software Change Requests, and risk management.
12th Working Day Of Each Month (As Of EOM)
PM
A013
Contract Performance Report (CPR)
Provides timely, reliable summary-level data with which to assess current and projected contract cost and schedule performance.
Initial delivery – 60 days after start of contract – Subsequent deliveries - Monthly
PM
A014
Socio-Economic Report
Provide subcontracting socio-economic reports
12th Working Day After Each Reporting Period (1 Apr – 30 September and 1 October – 31 March)
55 CONS
A015
Software Design Document (SDD)
Describes the design of the software to include architectural design, detailed design for implementation and the interfaces.
When Design Changes –

Complete and comprehensive SDD is required 30 days prior to the end of the contract

PM

A016
Reliability and Maintainability (R&M)
Describes the Contractor’s organization, functions, duties, responsibilities, and

reporting requirements to ensure that a system or equipment contributes to the achievement of the maximum LCAC reliability and operational availability at the lowest possible Total Ownership Cost.

Yearly and 30 days after requested
PM
A017
Information Assurance (IA) Deliverables
Provides the IA items required for certification of the system.
For each major delivery at TRR
PM
A018
Computer Software Product End Items (CSPEI)
Contractor shall make a delivery of the application to coincide with semi-annual maintenance. Deliveries shall consist of raw source code for reference and recompilation as well as working executables.
In conjunction with each software delivery (end of GDT&E) and if requested by the government.

PM

A019
Technical Report – Study/Service
Provides technical reports, studies or services as requested by the Government.
When requested
PM

Exhibit A – page 2