This document is a Solicitation Amendment for a federal contract opportunity. The amendment corrects the fiscal year details in the Option Line Item descriptions, updates an attachment to reflect RFI responses, adds a new RFI responses attachment, establishes an RFI submission deadline, and extends the proposal due date by 7 calendar days to 16 August 2024.
The contract opportunity is for the regrading of Missile Alert Facilities and Missile Launch Facilities, including access roads, ditch grading, placement of gravel and stone, culvert work, and other related services. The estimated contract value is between $1,000,000 and $5,000,000. The government intends to award on a best value trade-off basis, with price approximately equal to the work performance plan and past performance. The contract will have yearly option periods from FY24 through FY28. Site access requirements and proposal submission instructions are also provided.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section A - Solicitation/Contract Form
The following changes have been made:
INFORMATION FROM TO
Contract Description
1) Magnitude: is Between $1,000,000.00 and $5,000,000.00.
2) Wage Rates for Heavy Construction ND20240043, ND20240047, and ND20240041 in the following counties:
Bottineau, Ward, Mountrail, Burke, McHenry, McClean, Sheridan, and Renville.
NOTE 1: The US Government intends to evaluate proposals and award a contract on best value trade-off decision with price being weighed approximately equal to work performance plan and past performance when combined. Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint.
NOTE 2: The offeror must request and obtain an acknowledgement of receipt for electronic submission.
NOTE 3: Please review ALL ATTACHMENTS. Please refer to the document titles rather than attachment identifiers.
NOTE 4: Site Visit was held at 09:00 AM on July 17th 2024.
Amendment 1: Sections L and M have been changed. The Past Performance Information Form has been attached. All attachments have been properly labeled.
The proposal due has been extended by 7 calendar days. Proposals are due no later than 1400 CDT, 9 August 2024.
1) Magnitude: is Between $1,000,000.00 and $5,000,000.00.
2) Wage Rates for Heavy Construction ND20240043, ND20240047, and ND20240041 in the following counties: Bottineau, Ward, Mountrail, Burke, McHenry, McClean, Sheridan, and Renville.
NOTE 1: The US Government intends to evaluate proposals and award a contract on best value trade-off decision with price being weighed approximately equal to work performance plan and past performance when combined. Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint.
NOTE 2: The offeror must request and obtain an acknowledgement of receipt for electronic submission.
NOTE 3: Please review ALL ATTACHMENTS. Please refer to the document titles rather than attachment identifiers.
NOTE 4: Site Visit was held at 09:00 AM on July 17th 2024.
Amendment 1: Sections L and M have been changed. The Past Performance Information Form has been attached. All attachments have been properly labeled. The proposal due date has been extended by 7 calendar days. Proposals are due no later than 1400 CDT, 9 August 2024.
Amendment 2: The FY in the description of the Option CLINs under Section B has been corrected. "Attachment 1 - Specifications" dated 6 August 2024, containing 122 pages has been corrected to reflect RFI responses under Section J. "Attachment 10 - Responses to RFIs" dated 6 August 2024, containing 2 pages has been added to Section J of the solicitation. A RFI submission deadline of 1600 CDT, 6 August 24 has been established. The proposal due date is extended by 7 calendar days, proposals are due no later than 1400 CDT, 16 August 2024.
Response Due Date
09 Aug 2024 16 Aug 2024
Section B - Supplies or Services & Prices or Costs
The following CLIN(s) / SLIN(s) / ELIN(s) were modified:
Option Line Item 1001
INFORMATION FROM TO CHANGED
BY
FY24 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and
FY25 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and
FA452824R00080002
Description materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
Option Line Item 2001
INFORMATION FROM TO CHANGED
BY
Description
FY24 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
FY26 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
Option Line Item 3001
INFORMATION FROM TO CHANGED
BY
Description
FY24 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
FY27 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
Option Line Item 4001
INFORMATION FROM TO CHANGED
BY
Description
FY24 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
FY28 F18SD FM9 REPAIR MAF & LF
CONTOURS 5 CES
The contractor shall provide all plant, labor, equipment, supervision, services, fuel, and materials necessary to the regrading of the Missile Alert Facilities (MAFs) and Missile Launch Facilities (LFs), including access roads, ditch grading (on/off site), placement of gravel and stone, clean SP-104 trench and/or pit, clean culverts, culvert replacement, install culvert end sections, install culvert markers, install clay barrier layer, seeding, topsoil, and geotextile fabric as identified in yearly delivery orders.
Contractor shall ensure proper drainage of MAF /LF site, access road, ditch areas, and culverts.
Section J - List of Attachments
The following attachments were added:
Attachment 1 - Specifications - Amendment 2 Attachment 10 - RFI Responses - Amendment 2
The following attachments were deleted:
Attachment 1 - Specifications
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0002 |
| EffDate: 07 Aug 2024 |
| ReqNo: |
| ProjNo: N/A |
| IssCode: FA4528 |
| AdmCode: |
| IssuedBy: FA4528 5 CONS LGCP |
165 MISSILE AVE, CP 701 723 2889
MINOT AFB, ND 58705
UNITED STATES
DAPHNE ROUSEY, Email: daphne.rousey.1@us.af.mil Telephone: 453-4674 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA452824R0008 |
| SolDate: 29 Jul 2024 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: The purpose of this amendment is to: |
1. Correct the FY in the description of the Option CLINs under Section B
2. Update "Attachment 1 - Specifications" dated 6 August 2024, containing 122 pages to reflect RFI responses
3. Add "Attachment 10 - Responses to RFIs" dated 6 August 2024, containing 2 pages to Section J of the solicitation
4. Establish a RFI submission deadline of 1600 CDT, 6 August 24.
5. Extend the proposal due date by 7 calendar days, proposals are due no later than 1400 CDT, 16 August 2024.
| ContNameTitle: |
| CoNameTitle: Charles Kendall |
| ContDate: |
| CODate: 06 Aug 2024 |
File details come from the government source that posted it. Updated .