Attachment_9_-_Questions_and_Answers.docx
DOCX document 20 KB Posted
- Attached to
- Minot AFB SABER IDIQ Federal contract opportunity
- Solicitation number
- FA4528-18-R-0010
About this file
Attachment 9 - Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1_-_SABER_IDIQ_SOW_Revised.pdf | ||
| SF_30.pdf | ||
| Attachment_2_-_SABER_Master_Specifications.pdf | ||
| Attachment_1_-_SABER_IDIQ_Statement_of_Work.pdf | ||
| Attachment_5-_Past_Performance_Information_Form.docx | DOCX document | |
| Attachment_6_-SOW_12April18_ANNEX.pdf | ||
| Attachment_4_-_Financial_Responsibility.docx | DOCX document | |
| Attachment_7_-_Drawings.pdf | ||
| Attachment_3_-_Wage_Determinations.pdf | ||
| FA4528-18-R-0010.pdf | ||
| Attachment_8_-_Construction_Cost_Breakdown.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 9 Pre-Proposal Offeror Questions and Government Responses
SABER IDIQ
FA4528-18-R-0010
7 June 2018
1. Will the seed project be an awarded task order?
A) The seed project will be awarded with the SABER IDIQ.
2. Are the only two options E4Clicks and WinEst for estimating programs?
A) Yes, these are the only programs allowed on Government computers.
3. Is RS Means on-line an acceptable estimating program?
A) No, see response to question 2.
4. What level of design is required for design/build task orders? i.e. 35%, 100%, etc. and do they need to be stamped by a licensed architect and or engineer?
A) The SABER task order require minimum design effort which is up to 35%. If 100% design or stamped drawings are required this will be noted in the project Statement of Objectives.
5. Does the SABER contractor need an office location within a 2 hour distance from the base to respond to emergency response warranty calls? No office requirement, but still requires response to the site within 2 hours if an emergency warranty call is made.
A) See revised SOW paragraphs 1.1 and 6.1.
6. Are design costs to be included in the contractors coefficient?
A) Minimum design and drawings are to be included in the coefficient, any specialized design that needs a stamp is not.
**Note – This attachment does not become part of the resultant contract**