Atch 1 - Bid Schedule (Base Option Year)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 2_Davis Bacon Wage Determination_Effective 23May08.doc | DOC document | |
| Attachment 6_Project Wage Determination_Roofer.doc | DOC document | |
| A-15_FA4528-08-R-0013 Amendment 0001.doc | DOC document | |
| Attachment 4_Responsibility.doc | DOC document | |
| Attachment 3_07-0213 | — | |
| Attachment 2_Davis Bacon Wage Determination.doc | DOC document | |
| A-15_RFP Solicitation.doc | DOC document | |
| Attachment 5_Technical Acceptance Criteria.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BASE YEAR
| Roofing Maintenance Contract Bid Schedule - QJVF 07-0213 | |||||
| B A S E Y E A R | |||||
| Item | Description | Unit | Base Year Estimated Quantity | Base Year Unit Price | Base Year Total Price for Estimated Quantity |
| 0001 | BASE-Investigative inspection-specified in Section 01010. | Roof | 6 | ||
| 2 | BASE-Security delay time for all contractor's activity entering or exiting a secure area. The Contractor will assume, at his risk, 30 minutes time for access entry for a crew up to 6. Contractor shall notify the Contracting Officer or inspector verbally immediately following delay. 1 hr. min. unit. | Crew Hour | 8 | ||
| 3 | BASE-Certified Asbestos and Lead Based Paint Inspector. Price per 1 Site Inspection. Min. 1 site inspection. | Per Inspec | 8 | ||
| 4 | BASE-Asbestos Analysis- single sample. Price per sample. Min. 2 samples per site. | EA | 30 | ||
| 5 | BASE-Lead Based Paint Analysis-single sample. Price per Sample. Min. 2 samples per site. | EA | 30 | ||
| 6 | BASE-Sample analysis Summary Letter with lab results. 1 site per Report. Price per Report, min. 1 report. | EA | 8 | ||
| 7 | BASE-Remove single layer of deteriorated BUR roof components (including felts, gravel surfacing and insulation); or standing seam metal roof system (including insulation and support system); or single-ply roof componets (including membrane, gravel surfacing and insulation); including repair preparation, to structural deck. 1 square min. unit. | SQ | 200 | ||
| 8 | BASE-Remove multiple layers of deteriorated BUR roof components (including felts, gravel surfacing and insulation); or standing seam metal roof system (including insulation and support system); or single-ply roof componets (including membrane, gravel surfacing and insulation); including repair preparation, to structural deck. 1 square min. unit. | SQ | 200 | ||
| 9 | BASE-Spud existing gravel surfacing. 1 Square foot minimum unit. | SF | 10000 | ||
| 10 | BASE-Mud and tape or caulk existing flashing joints, etc. 1 Lineal foot minimum unit. | LF | 1500 | ||
| 11 | BASE-Cut existing welds and remove existing steel curbs or supports. Minimum 1 foot length unit. | LF | 40 | ||
| 12 | BASE-Install and weld new steel angle iron supports, up to 4"X4"X1/4". Miniumun 2' length. | LF | 40 | ||
| 13 | BASE-Remove existing 1-1/2" Roof deck & replace with new. Minimum 1 square foot unit. | SF | 200 | ||
| 14 | BASE-Remove and replace existing plywood soffits with ADX plywood, prime & paint to match existing. | SF | 450 | ||
| 15 | BASE-Remove existing fascia/gravel stop and replace with new prefinished, galvanized steel fascia/ gravel stop and cleat. 1 square foot minimum unit. | SF | 2000 | ||
| 16 | BASE-Remove existing reglet and counterflashing and replace with new galvanized 24 gauge steel reglet and counterflashing. 1 square foot minimum unit. | SF | 450 | ||
| 17 | BASE-Remove existing counterflashing and replace with new galvanized or prefinished, galvanized counterflashing. 1 square foot minimum unit. | SF | 250 | ||
| 18 | BASE-Remove existing and furnish and install new wood blocking at roof perimeters, control joints, roof penetration curbs and other curb locations. 1 board foot minimum unit. | BF | 5200 | ||
| 19 | BASE-Remove existing vent flashing and replace with new lead vent flashing as shown on NRCA detail BUR-18 (01). | EA | 30 | ||
| 20 | BASE-Remove existing metal parapet/curb cap and replace with new prefinished galvanized steel. 1 square foot min. unit. | SF | 1000 | ||
| 21 | BASE-Remove existing siding and replace with new long span prefinished steel panels. | SF | 100 | ||
| 22 | BASE-Remove existing siding and replace with new 12" wide vertical prefinished steel panels with steel furring channels. | SF | 100 | ||
| 23 | BASE-Remove existing EFIS siding system and replace with new EFIS siding system. | SF | 100 | ||
| 24 | BASE-Install new warranty sign. One sign minimum unit. | EA | 8 | ||
| 25 | BASE-Remove existing roof drain sump. Replace with new. Reconnect to drain piping. See NRCA detail BUR-20 (01). | EA | 16 | ||
| 26 | BASE-Remove existing expansion joint and furnish and install new all metal expansion joint cover similar to NRCA detail SM-22 (01). 1 lineal foot minimum unit. | LF | 260 | ||
| 27 | BASE-Furnish and install new prefinished galvanized steel scupper. Minimum 12" wide X 6" out. | EA | 40 | ||
| 28 | BASE-Remove and replace existing continuous snow/ice gaurd. Minimum 5 L.F. | LF | 120 | ||
| 29 | BASE-Remove and replace existing fabricated, prefinished, galvanized steel, 6" raingutter system. Minimum 10 L.F. | LF | 120 | ||
| 30 | BASE-Remove and replace existing fabricated, prefinished, open faced, galvanized steel 6" downspouts. Min. 8 L.F. | LF | 80 | ||
| 31 | BASE-Remove and replace existing prefinished 4"X5" aluminum continuous raingutters. 10' minimum unit. | LF | 120 | ||
| 32 | BASE-Remove and replace existing prefinished 5"X6" aluminum continuous raingutters. 10' minimum unit. | LF | 80 | ||
| 33 | BASE-Remove and replace existing prefinished aluminum continuous 2"X3" downspouts. 10' minimum unit. | LF | 140 | ||
| 34 | BASE-Remove and replace existing prefinished aluminum continuous 3"X4" downspouts. 10' minimum unit. | LF | 40 | ||
| 35 | BASE-Furnish and install new precast concrete splashblock. Minimum one unit. | EA | 40 | ||
| 36 | BASE-Furnish and install specified vapor barrier. 1 square minimum unit. | SQ | 200 | ||
| 37 | BASE-Furnish and install specified underlayment. 1 square minimum unit. | SQ | 120 | ||
| 38 | BASE-Furnish and install specified polyisocyanurate insulation over prepared surface area. Thickness is per layer of insulation and is identified in specification. 1 board foot minimum unit. | BF | 265000 | ||
| 39 | BASE-Furnish and install specified tapered polyisocyanurate insulation over prepared surface area. Thickness is average layer of insulation. 1 board foot minimum unit. | BF | 20000 | ||
| 40 | BASE-Furnish and install specified 5/8" DensDeck roof board (Type X) over prepared surface area. Thickness is average layer of insulation. 1 board foot minimum unit. | SF | 50000 | ||
| 41 | BASE-Furnish and install specified 3/4 inch perlite insulation over prepared surface area. Thickness is per layer of insulation. 1 square foot minimum unit. | SF | 50000 | ||
| 42 | BASE-Furnish and install specified tapered edge strips. 1 lineal foot minimum unit. | LF | 800 | ||
| 43 | BASE-Furnish and install specified 4 inch x 4 inch cant strips. 1 lineal foot minimum unit. | LF | 1600 | ||
| 44 | BASE-Furnish and install asphalt system as specified, including membrane, bitumen and surfacing. 1 square minimum unit. | SQ | 360 | ||
| 45 | BASE-Furnish and install specified asphalt base flashing system as specified. | SF | 800 | ||
| 46 | BASE-20 year asphalt system warranty, less than 100 squares per roof. 1 roof minimum unit. | Roof | 5 | ||
| 47 | BASE-20 year asphalt system warranty, 100 squares or more per roof. 1 roof minimum unit. | SQ | 250 | ||
| 48 | BASE-Furnish and install SBS modified bitumen system as specified, including membrane, base sheet system and bitumen. 1 square minimum unit. | SQ | 50 | ||
| 49 | BASE-Furnish and install specified SBS modified bitumen base flashing system as specified. | SF | 240 | ||
| 50 | BASE-20 year SBS Modified Bitumen system warranty, less than 100 squares per roof. 1 roof minimum unit. | Roof | 1 | ||
| 51 | BASE-20 year SBS Modified Bitumen system warranty,100 squares or more per roof. 1 roof minimum unit. | SQ | 40 | ||
| 52 | BASE-Complete asphalt roof membrane sampling as specified. 1 each minimum unit. | EA | 2 | ||
| 53 | BASE-EPDM Membrane 60 mil fully adhered system. 1 square minimum unit. | SQ | 160 | ||
| 54 | BASE-EPDM Flashing. | SF | 240 | ||
| 55 | BASE-Rubber Walk Pad. Minimum 6.25 S.F. | SF | 50 | ||
| 56 | BASE-20 year EPDM Warranty less than 100 squares per roof. 1 roof minimum unit. | Roof | 2 | ||
| 57 | BASE-20 year EPDM Warranty 100 squares or more per roof. 1 roof minimum unit. | SQ | 100 | ||
| 58 | BASE-Furnish and install aluminum roof coating. | SF | 100 | ||
| 59 | BASE-RC 2000 Spray-On Coating | SF | 200 | ||
| 60 | BASE-Embed fiberglass mesh in coating(coating included) | SF | 200 | ||
| 61 | BASE-Remove and replace existing plywood roof sheathing to match existing. Min. 32 SF. | SF | 240 | ||
| 62 | BASE-Remove and replace existing shingles and felt underlayment. Minimum one square. | SQ | 22 | ||
| 63 | BASE-Modified asphalt underlayment, minimum 10 S.F. | SF | 300 | ||
| 64 | BASE-Remove & replace metal drip edge, minimum 10 L.F. | LF | 160 | ||
| 65 | BASE-Valley with modified asphalt underlayment and galvanized metal flashing, minimum 200 L.F. | LF | 40 | ||
| 66 | BASE-Remove and replace existing ridge cap, min. 10 L.F. | LF | 40 | ||
| 67 | BASE-Continuous Ridge Vent, minimum 10 L.F. | LF | 40 | ||
| TOTAL BASE YEAR | |||||
| Select tab at bottom for Option Year Bid Schedule |
&RFA4528-08-R-0013
Attachment 1 &LBid Schedule &C&P
&RQJVF 07-0213
OPTION YEAR
| Roofing Maintenance Contract Bid Schedule - QJVF 07-0213 | |||||
| O P T I O N Y E A R | |||||
| Item | Description | Unit | Option Year Estimated Quantity | Option Year Unit Price | Option Year Total Price for Estimated Quantity |
| 1001 | BASE-Investigative inspection-specified in Section 01010. | Roof | 6 | ||
| 1002 | BASE-Security delay time for all contractor's activity entering or exiting a secure area. The Contractor will assume, at his risk, 30 minutes time for access entry for a crew up to 6. Contractor shall notify the Contracting Officer or inspector verbally immediately following delay. 1 hr. min. unit. | Crew Hour | 8 | ||
| 1003 | BASE-Certified Asbestos and Lead Based Paint Inspector. Price per 1 Site Inspection. Min. 1 site inspection. | Per Inspec | 8 | ||
| 1004 | BASE-Asbestos Analysis- single sample. Price per sample. Min. 2 samples per site. | EA | 30 | ||
| 1005 | BASE-Lead Based Paint Analysis-single sample. Price per Sample. Min. 2 samples per site. | EA | 30 | ||
| 1006 | BASE-Sample analysis Summary Letter with lab results. 1 site per Report. Price per Report, min. 1 report. | EA | 8 | ||
| 1007 | BASE-Remove single layer of deteriorated BUR roof components (including felts, gravel surfacing and insulation); or standing seam metal roof system (including insulation and support system); or single-ply roof componets (including membrane, gravel surfacing and insulation); including repair preparation, to structural deck. 1 square min. unit. | SQ | 200 | ||
| 1008 | BASE-Remove multiple layers of deteriorated BUR roof components (including felts, gravel surfacing and insulation); or standing seam metal roof system (including insulation and support system); or single-ply roof componets (including membrane, gravel surfacing and insulation); including repair preparation, to structural deck. 1 square min. unit. | SQ | 200 | ||
| 1009 | BASE-Spud existing gravel surfacing. 1 Square foot minimum unit. | SF | 10000 | ||
| 1010 | BASE-Mud and tape or caulk existing flashing joints, etc. 1 Lineal foot minimum unit. | LF | 1500 | ||
| 1011 | BASE-Cut existing welds and remove existing steel curbs or supports. Minimum 1 foot length unit. | LF | 40 | ||
| 1012 | BASE-Install and weld new steel angle iron supports, up to 4"X4"X1/4". Miniumun 2' length. | LF | 40 | ||
| 1013 | BASE-Remove existing 1-1/2" Roof deck & replace with new. Minimum 1 square foot unit. | SF | 200 | ||
| 1014 | BASE-Remove and replace existing plywood soffits with ADX plywood, prime & paint to match existing. | SF | 450 | ||
| 1015 | BASE-Remove existing fascia/gravel stop and replace with new prefinished, galvanized steel fascia/ gravel stop and cleat. 1 square foot minimum unit. | SF | 2000 | ||
| 1016 | BASE-Remove existing reglet and counterflashing and replace with new galvanized 24 gauge steel reglet and counterflashing. 1 square foot minimum unit. | SF | 450 | ||
| 1017 | BASE-Remove existing counterflashing and replace with new galvanized or prefinished, galvanized counterflashing. 1 square foot minimum unit. | SF | 250 | ||
| 1018 | BASE-Remove existing and furnish and install new wood blocking at roof perimeters, control joints, roof penetration curbs and other curb locations. 1 board foot minimum unit. | BF | 5200 | ||
| 1019 | BASE-Remove existing vent flashing and replace with new lead vent flashing as shown on NRCA detail BUR-18 (01). | EA | 30 | ||
| 1020 | BASE-Remove existing metal parapet/curb cap and replace with new prefinished galvanized steel. 1 square foot min. unit. | SF | 1000 | ||
| 1021 | BASE-Remove existing siding and replace with new long span prefinished steel panels. | SF | 100 | ||
| 1022 | BASE-Remove existing siding and replace with new 12" wide vertical prefinished steel panels with steel furring channels. | SF | 100 | ||
| 1023 | BASE-Remove existing EFIS siding system and replace with new EFIS siding system. | SF | 100 | ||
| 1024 | BASE-Install new warranty sign. One sign minimum unit. | EA | 8 | ||
| 1025 | BASE-Remove existing roof drain sump. Replace with new. Reconnect to drain piping. See NRCA detail BUR-20 (01). | EA | 16 | ||
| 1026 | BASE-Remove existing expansion joint and furnish and install new all metal expansion joint cover similar to NRCA detail SM-22 (01). 1 lineal foot minimum unit. | LF | 260 | ||
| 1027 | BASE-Furnish and install new prefinished galvanized steel scupper. Minimum 12" wide X 6" out. | EA | 40 | ||
| 1028 | BASE-Remove and replace existing continuous snow/ice gaurd. Minimum 5 L.F. | LF | 120 | ||
| 1029 | BASE-Remove and replace existing fabricated, prefinished, galvanized steel, 6" raingutter system. Minimum 10 L.F. | LF | 120 | ||
| 1030 | BASE-Remove and replace existing fabricated, prefinished, open faced, galvanized steel 6" downspouts. Min. 8 L.F. | LF | 80 | ||
| 1031 | BASE-Remove and replace existing prefinished 4"X5" aluminum continuous raingutters. 10' minimum unit. | LF | 120 | ||
| 1032 | BASE-Remove and replace existing prefinished 5"X6" aluminum continuous raingutters. 10' minimum unit. | LF | 80 | ||
| 1033 | BASE-Remove and replace existing prefinished aluminum continuous 2"X3" downspouts. 10' minimum unit. | LF | 140 | ||
| 1034 | BASE-Remove and replace existing prefinished aluminum continuous 3"X4" downspouts. 10' minimum unit. | LF | 40 | ||
| 1035 | BASE-Furnish and install new precast concrete splashblock. Minimum one unit. | EA | 40 | ||
| 1036 | BASE-Furnish and install specified vapor barrier. 1 square minimum unit. | SQ | 200 | ||
| 1037 | BASE-Furnish and install specified underlayment. 1 square minimum unit. | SQ | 120 | ||
| 1038 | BASE-Furnish and install specified polyisocyanurate insulation over prepared surface area. Thickness is per layer of insulation and is identified in specification. 1 board foot minimum unit. | BF | 265000 | ||
| 1039 | BASE-Furnish and install specified tapered polyisocyanurate insulation over prepared surface area. Thickness is average layer of insulation. 1 board foot minimum unit. | BF | 20000 | ||
| 1040 | BASE-Furnish and install specified 5/8" DensDeck roof board (Type X) over prepared surface area. Thickness is average layer of insulation. 1 board foot minimum unit. | SF | 50000 | ||
| 1041 | BASE-Furnish and install specified 3/4 inch perlite insulation over prepared surface area. Thickness is per layer of insulation. 1 square foot minimum unit. | SF | 50000 | ||
| 1042 | BASE-Furnish and install specified tapered edge strips. 1 lineal foot minimum unit. | LF | 800 | ||
| 1043 | BASE-Furnish and install specified 4 inch x 4 inch cant strips. 1 lineal foot minimum unit. | LF | 1600 | ||
| 1044 | BASE-Furnish and install asphalt system as specified, including membrane, bitumen and surfacing. 1 square minimum unit. | SQ | 360 | ||
| 1045 | BASE-Furnish and install specified asphalt base flashing system as specified. | SF | 800 | ||
| 1046 | BASE-20 year asphalt system warranty, less than 100 squares per roof. 1 roof minimum unit. | Roof | 5 | ||
| 1047 | BASE-20 year asphalt system warranty, 100 squares or more per roof. 1 roof minimum unit. | SQ | 250 | ||
| 1048 | BASE-Furnish and install SBS modified bitumen system as specified, including membrane, base sheet system and bitumen. 1 square minimum unit. | SQ | 50 | ||
| 1049 | BASE-Furnish and install specified SBS modified bitumen base flashing system as specified. | SF | 240 | ||
| 1050 | BASE-20 year SBS Modified Bitumen system warranty, less than 100 squares per roof. 1 roof minimum unit. | Roof | 1 | ||
| 1051 | BASE-20 year SBS Modified Bitumen system warranty,100 squares or more per roof. 1 roof minimum unit. | SQ | 40 | ||
| 1052 | BASE-Complete asphalt roof membrane sampling as specified. 1 each minimum unit. | EA | 2 | ||
| 1053 | BASE-EPDM Membrane 60 mil fully adhered system. 1 square minimum unit. | SQ | 160 | ||
| 1054 | BASE-EPDM Flashing. | SF | 240 | ||
| 1055 | BASE-Rubber Walk Pad. Minimum 6.25 S.F. | SF | 50 | ||
| 1056 | BASE-20 year EPDM Warranty less than 100 squares per roof. 1 roof minimum unit. | Roof | 2 | ||
| 1057 | BASE-20 year EPDM Warranty 100 squares or more per roof. 1 roof minimum unit. | SQ | 100 | ||
| 1058 | BASE-Furnish and install aluminum roof coating. | SF | 100 | ||
| 1059 | BASE-RC 2000 Spray-On Coating | SF | 200 | ||
| 1060 | BASE-Embed fiberglass mesh in coating(coating included) | SF | 200 | ||
| 1061 | BASE-Remove and replace existing plywood roof sheathing to match existing. Min. 32 SF. | SF | 240 | ||
| 1062 | BASE-Remove and replace existing shingles and felt underlayment. Minimum one square. | SQ | 22 | ||
| 1063 | BASE-Modified asphalt underlayment, minimum 10 S.F. | SF | 300 | ||
| 1064 | BASE-Remove & replace metal drip edge, minimum 10 L.F. | LF | 160 | ||
| 1065 | BASE-Valley with modified asphalt underlayment and galvanized metal flashing, minimum 200 L.F. | LF | 40 | ||
| 1066 | BASE-Remove and replace existing ridge cap, min. 10 L.F. | LF | 40 | ||
| 1067 | BASE-Continuous Ridge Vent, minimum 10 L.F. | LF | 40 | ||
| TOTAL OPTION YEAR | |||||
| TOTAL BASE YEAR | |||||
| TOTAL |