Attch 1 ABW Historian Statue repair PWS v2.docx

DOCX document 9 MB Posted

Attached to
THOMAS B. MCGUIRE. JR. STATUE RESTORATION Federal contract opportunity
Solicitation number
FA448424Q0052
Issued by
Department of the Air Force Air Mobility Command

About this file

This document is a Statement of Work (SOW) for the repair, renovation, and relocation of the Thomas B. McGuire, Jr. bronze statue located outside building 3011 on the Joint Base McGuire-Dix-Lakehurst (JB MDL). The vendor shall inspect the statue, remove it from the current location, make necessary repairs and renovations to maintain the original design, and then relocate the statue to the Joint Base Heritage Park adjacent to building 3011. The SOW outlines the general requirements, including that the vendor must provide all materials and equipment for the movement, repair, renovation, and relocation of the statue. Coordination with the Joint Base Historian is required for the final placement location.

The related federal contract opportunity is a solicitation (FA448424Q0052) for the complete repair and restoration of the existing bronze statue. The scope includes repairing all visible stress cracks, fixing any incomplete prior repairs, blending all repairs to remove signs of deterioration, sandblasting the entire statue to remove oxidation, painting with a graphite spray to achieve a statuary appearance, and applying a protective coating in either a satin or high gloss finish. The contracting agency is the Department of the Air Force, Air Mobility Command.

View the file

Other files for this federal contract opportunity

Other files attached to THOMAS B. MCGUIRE. JR. STATUE RESTORATION, newest first.
File Type Posted
Response to Questions FA448424Q0052.docx DOCX document
Attch 6 Medical Statement.docx DOCX document
Attch 2 SFS Appendix - CONTRACTOR APPENDIX Sep 23.pdf PDF
Attch 7 SOW_PWS AT Statement APR 24.pdf PDF
Attch 5 Combo Synopsis-Solicitation ABW Historian statue repair.docx DOCX document
Attch 1 ABW Historian Statue repair PWS.docx DOCX document
Attch 3 JB MDL Antiterrorism Awareness for Contractors Trifold.pdf PDF
Attch 4 JB MDL AT Awareness Guide for Contractors 22APR24.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Thomas B. McGuire, Jr Statue Renovation and Relocation The scope of work is as follows in the Statement of Work. The vendor shall furnish and assemble all material outlined below to construct a modular building. No alteration, additions or deletions shall be made to the contract unless prior approval is given in writing by the Contracting Officer (CO). The Thomas B. McGuire, Jr. bronzed statue located outside building 3011 needs to be removed for the purpose of renovation and repair. Once these renovations and repairs are completed, the statue will be relocated to the Joint Base Heritage Park adjacent to building 3011. This location will be coordinated through the Joint Base Historian prior to the statues return once repairs are completed.

Vendor must provide the following specifications for the removal, repair, renovation, and relocation of the Thomas B. McGuire, Jr. statue:

1. GENERAL REQUIREMENTS

a. Contractor would need to inspect and prepare the statue for removal from building 3011 prior to being moved to the location where repairs and renovations will take place.

· The contractor will need to come to our location to conduct the repairs.

· The entire statue will be relocated approximately 50-75 feet to the east of the building adjacent to the parking lot.

· Coordinate with the base historian for exact location and orientation.

b. Make repairs and renovations that will maintain its original look as designed and created by the original sculptor, Mr. Masood Ali-Wilbert Warren.

· The statue is 8-feet and it sits on a square base that is 3 feet 5 inches by 3 feet five inches.

c. Return statue to the Joint Base Heritage Park on JB MDL located adjacent to building 3011.

d. Provide all materials and equipment for the movement, repair, renovation, and relocation of the statue.

2. Miscellaneous

a. Coordination for final placement location will be conducted with the Joint Base Historian. A map showing this location will be provided.

b. Pictures below:

image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.jpeg image11.jpeg image12.jpeg image1.png image2.jpeg