JB_MDL_EOS_Logistics_Questions_20170803.pdf
PDF 17 KB Posted
- Attached to
- Expeditionary Operations School Logistics Support Services Federal contract opportunity
- Solicitation number
- FA448417R0018
About this file
Combined questions from the site visit and submitted questions via email.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| EOSLogistics_Amendment_2_20170822.pdf | ||
| EOSLogistics_PWSRev14_20170822.pdf | ||
| JB-MDL_EOSLogistics_PWS_20170815.pdf | ||
| SFS_Contractor_Appendix_2016.pdf | ||
| FA448417R00180001.pdf | ||
| JB_MDL_Antiterrorism_Awareness_for_Contractors_(Trifold).pdf | ||
| JB-MDL_EOSLogistics_QASP_20170321.docx | DOCX document | |
| JB-MDL_EOSLogistics_PWS_20170612.docx | DOCX document | |
| A2_QUESTIONNAIRE.docx | DOCX document | |
| A7_Antiterrorism_Awareness_Guide_for_Contractors,_MAR_16.pdf | ||
| Past_Performance_Cover_Sheet.pdf | ||
| Wage_Determinations_EOS_Logistics_Support.docx | DOCX document | |
| A5_JB-MDL_Security_Forces_Appendix_20150610.pdf | ||
| FA448417R0018_EOS_Logistics_Support_Solicitation.docx | DOCX document | |
| CGFP_Listing-_20170403.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Joint Base McGuire-Dix-Lakehurst
Solicitation No. FA4484-17-R-0018
EOS Logistics Support Services
Questions and Answers
1) Does the contractor provide all the MHE (material handling equipment)?
Yes, the contractor will provide all MHE.
2) Will all equipment be in one location?
Yes, the equipment will all be in one location in Hangar-1 (The Hindenburg Hangar) on the Lakehurst Annex of JB MDL.
3) Will the contractor have access to a computer or phone?
Yes, the contractor will have access to one terminal and one land line.
4) Will the Contractor be able to open the hangar door?
Yes, the contractor will be able to open one side of the hangar door.
5) Is Contractor in charge of lawn cutting and latrine waste disposal?
The contractor will have a single point of contact for these items. The contractor can call a week in advance and the custodian will take care of these items.
6) Does the contractor have to work with the mock village on site?
No; the the mock village shall be left as is.
7) What about the water buffalo?
The water buffalo is government provided. It is the contractor’s job to test, fill, and clean the buffalo.
8) Temp requirements for sleeping?
If it gets too hot, there will be two more generators will be provided, making four total.
The maximum temperature inside the tents is 78 degrees.
9) Is tick spraying coordinated?
The contractor is responsible for the coordination of tick spraying.
10) All electrical is above ground?
Yes, all the wires are above ground.
11) What about the cots inside the tents?
Cots are not the contractors responsibility. If they break, the site manager must be notified for replacement.
12) What do the briefings consist of?
Briefings are instructions on how to set up and tear down the site. The contractor is required to give a maximum of one briefing per course.
13) Security clearance. They need a NACI clearance can take up to 120 days, but EAL’s are required in 3 days post award. How do we rectify this?
The PWS has been updated to reflect that only the site manager needs NACI access. The NACI access is required to access the network terminal, not for base access.
14) Attachment 1 Appendix 4, is that the final version? That isn’t the long term pass for the contractors?
The final version, 1 Jul 16, has been added as an attachment to the solicitation
15) Is there a better photo of Lakehurst?
The current photo in the PWS is the only photo that will be provided.
16) What is the contract number?
The contract number will be created when the contract is awarded.
17) What is the Standard Industrial Classification Code?
The SIC is no longer used. This requirement is solicited under NAICS code 541614.
18) Does the map identify all training sites?
There is a back-up training site approximately 2.5 miles away from Hangar-1.
19) Is the forklift for contractor use?
No, the contractor shall provide all of their own equipment.
20) What size are the spill containment berms?
They are 8ft by 8ft.