About this file

Q&A #3

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bldg 90 FA4418-19-R-0004 – Q & A #3 Follow up questions to Q&A #1 below

1. Will any hazardous material found to be in the May 18, 2015 survey by our “person licensed as a building inspector” be a change condition or part of the bid price?

Change.

2. Who currently manages the Fire Alarm System, and will their cost of integration be part of the bid price?

JB Charleston. No cost for integration.

3. Who currently manages the DDC Energy Management System, and will their cost of integration be a part of the bid price?

JCI or Trane. Yes, their cost of integration shall be a part of the bid price.

4. Are the “existing windows” rated as emergency egress windows?

RESPONSE: Existing windows are not emergency egress windows.

5. Define “maintained” for the Kitchen Equipment, Bunk Furniture, and Washer/Dryer, and is that cost to be part of the bid price?

Secured in a safe place until re-installed. Yes, that cost shall be incurred by the contractor.

6. Please define “industry standard” in regards to the existing substrate preparation for the new flooring.

RESPONSE: Follow manufacturer's instruction for existing floor preparation.

7. Please define the extent of work not shown, for the removal and replacement of the fencing, golf ball netting and unknown utilities in conflict with the new water line.

RESPONSE: Remove and reinstall existing items as required to install new utilities.

File details come from the government source that posted it.