Atch_10_-_SWPPP,_Rpr_AVB_Post_4.pdf

PDF 9 MB Posted

Attached to
Repair Active Vehicle Barriers at JB Charleston - WS, SC
Solicitation number
FA4418-18-R-0022
Issued by

About this file

Sect J, SWPPP

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P 843 875 3637 F 843 875 4509

320-C Midland Parkway Summerville, SC 29485

STORMWATER POLLUTION PREVENTION PLAN

POST 4

JOINT BASE CHARLESTON (NAVAL WEAPONS STATION)

GOOSE CREEK, SC

JULY 2017

TABLE OF CONTENTS

NARRATIVE

PLANNED EROSION AND SEDIMENTATION CONTROL PRACTICES

MAINTENANCE PLAN

320-C Midland Parkway Summerville, SC 29485

SWPPP NARRATIVE:

The project site is located at Joint Base Charleston, entering the Naval Weapons Station in Goose Creek, South Carolina. The entry control facility area is along Perimeter Road, North of

Remount Road. The site consists of an existing vehicle processing area, to remain, with a new active vehicle barrier, overwatch structure, and associated supporting infrastructure.

Total area site disturbance is slightly under one acre. According to the USDA Soil Survey, the soils found at the site consist of Bonneau loamy sand as well as borrow pit material. Bonneau loamy sand conforms within hydrologic soil group “B” (moderately well drained), and borrow pit soils are assumed to be hydrologic soil group “D” (poorly drained).

The nearest receiving water body (RWB) for storm water discharge is Filbin Creek, which ultimately reaches the Cooper River. The Filbin Creek tributary is approximately 3878’ South of the project site. Storm water is then conveyed approximately 6000’ downstream to the Cooper

River, a coastal receiving Water (CRW) which is classified as Freshwater (FW) per SCDHEC.

Best Management Practices for Sediment and Erosion Control are in place for this project to protect existing conditions, and the construction will not contribute to any impairments. To limit the sediment discharge from the site, temporary silt fence will be installed along the edges of earthwork, demolition, and construction disturbance. A construction staging area, enclosed with silt fence with gravel construction entrances, shall prevent construction vehicle tracking.

Once construction has been completed, all disturbed areas shall be sodded or seeded with grass in accordance with the plans, specifications, and following direction. Upon stabilization of grassed area, sediment control measures shall be removed and all sediment and debris must be removed from the area of work.

The proposed site disturbance requires consideration of the Energy Independence and

Security Act of 2007 (EISA) provision requirements to the greatest extent technically feasible.

The attached NOI package for Automatic Coverage should be completed/signed by the prime contractor (serving as "project Owner/Operator”) & submitted to JB CHS MS4 Office (JB

CHS 628 CES/CEIE; C Wannamaker. For additional information, refer to the design drawings, Erosion & Sedimentation Control Practices and Maintenance Plans within this package.

REFERENCES:

SCDHEC Stormwater Management Best Management Practices Handbook Energy Independence and Security Act (EISA) 2007: Section 438

320-C Midland Parkway

PLANNED EROSION AND SEDIMENTATION CONTROL PRACTICES

1. SEDIMENT (SILT) FENCE –

Silt fence will be provided along specified edges of the project site as shown in the drawings. The silt fence will limit the amount of eroded material leaving the site until a vegetative cover is established.

2. TEMPORARY GRAVEL CONSTRUCTION ENTRANCE/EXITS –

Gravel entrance pads, as detailed, will be installed as shown on the plans to provide a buffer to cut down on material leaving the construction staging area where vehicles leave the work area. The contractor will be responsible for cleaning and adding stone if an excessive amount of mud or debris accumulates.

3. LAND GRADING

The grading plan has been developed with consideration of what areas need to be graded, when the work will start and stop, the degree and length of finished slopes, where borrow will be needed and where excess material will be wasted. The contractor will coordinate grading operations while utilizing the erosion and sedimentation control measures set forth in the plans.

4. CONCRETE TRUCK WASHOUT

Temporary concrete washout facilities should be located a minimum of 50 feet from storm drain inlets, open drainage facilities, and watercourses, unless determined infeasible by the

Engineer. Each facility should be located away from construction traffic or access areas to prevent disturbance or tracking. Install a sign adjacent to each washout facility to inform concrete equipment operators to utilize the proper facilities.

MAINTENANCE PLAN

SCDHEC Standard Notes:

1. Stabilization measures shall be initiated as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased, but in no case more fourteen (14) days after work has ceased, except as stated below.

• Where stabilization by the 14th day is precluded by snow cover or frozen ground conditions stabilization measures must be initiated as soon as practicable.

• Where construction activity on a portion of the site is temporarily ceased, and earth-disturbing activities will be resumed within 14 days, temporary stabilization measures do not have to be initiated on that portion of the site.

2. All sediment and erosion control devices shall be inspected once every calendar week. If periodic inspection or other information indicates that a bmp has been inappropriately, or incorrectly, the permittee must address the necessary replacement or modification required to correct the bmp within 48 hours of identification.

3. Provide silt fence and/or other control devices, as may be required, to control soil erosion during utility construction. All disturbed areas shall be cleaned, graded and stabilized with grassing immediately after the utility installation. Fill, cover, and temporary seeding at the end of each day are recommended. If water is encountered while trenching, the water should be filtered to remove any sediments. Do not pump the filtered water into waters of the state.

4. All erosion control devices shall be properly maintained during all phases of construction until the completion of all construction activities and all disturbed areas have been stabilized. Additional control devices may be required during construction in order to control erosion and/or offsite sedimentation. All temporary control devices shall be removed once construction is complete and the site is stabilized.

5. The contractor must take necessary action to minimize the tracking of mud onto paved roadway(s) from construction areas and the generation of dust. The contractor shall daily remove mud/soil from pavement, as may be required.

6. Litter, construction debris, oils, fuels and building products with significant potential for impact (such as stockpiles of freshly treated lumber) and construction chemicals that could be exposed to storm water must be prevented from becoming a pollutant source in storm water discharges.

7. A copy of the SWPPP, inspections records, and rainfall data must be retained at the construction site or a nearby location easily accessible during normal business hours, from the date of commencement of construction activities to the date that final stabilization is reached.

8. Initiate stabilization measures on any exposed steep slope (3H:1V or greater) where land-disturbing activities have permanently or temporarily ceased, and will not resume for a period of 7 calendar days.

9. Minimize soil compaction and, unless infeasible, preserve topsoil.

10. Minimize the discharge of pollutants from equipment and vehicle washing, wheel wash water, and other wash waters. Wash waters must be treated in a sediment basin or alternative control that provides equivalent or better treatment prior to discharge;

11. Minimize the discharge of pollutants from dewatering of trenches and excavated areas.

These discharges are to be routed through appropriate BMPs (sediment basin, filter bag, etc.).

12. The following discharges from sites are prohibited:

• Wastewater from washout of concrete, unless managed by an appropriate control;

• Wastewater from washout and cleanout of stucco, paint, form release oils, curing

• Compounds and other construction materials;

• Fuels, oils, or other pollutants used in vehicle and equipment operation and maintenance;

• Soaps or solvents used in vehicle and equipment washing.

13. After construction activities begin, inspections must be conducted at a minimum of at least once every calendar week and must be conducted until final stabilization is reached on all areas of the construction site.

14. If existing BMPs need to be modified or if additional BMPs are necessary to comply with the requirements of this permit and/or SC’s water quality standards, implementation must be completed before the next storm event whenever practicable. If implementation before the next storm event is impracticable, the situation must be documented in the

SWPPP and alternative BMPs must be implemented as soon as reasonably possible.

15. A pre-construction conference must be held for each construction site with an approved on-site SWPPP prior to the implementation of construction activities.

320-C Midland Parkway

Additional Erosion Control Maintenance Notes:

1. Install permanent vegetative cover and the long-term erosion protection measures or structures as soon as practical in the development process.

2. Provide for handling the increased runoff caused by changed soil and surface conditions. Use effective means to conserve existing on-site soil including the use of diversion ditches, grassed waterways and storm sewers.

3. Place silt fence barriers at locations shown on plan. Silt barriers shall be maintained in place and in good condition until ground cover is established.

4. All disturbed areas not paved shall be grassed. Use temporary plant cover, mulching, and/or structures to control runoff and protect areas subject to erosion during construction.

5. Contractor shall provide dumpster of sufficient size and number to contain the solid waste generated by the project.

6. Contractor shall frequently remove garbage to maintain a clean construction site and minimize the exposure of waste to storm water.

Project Name

Project Location

Map Prepared By

Date

Applicant

Map Reference

SCALE

Not to scale

PROJECT SITE AREA

JBC, Goose Creek, South Carolina Remount / Perimeter Road

Google Maps 2017

April, 2017 JBC Post 4 AVB

320-C Midland Parkway, Summerville, South Carolina, 29485 843.875.3637

ENGINEERING | ARCHITECTURE

Joint Base Charleston / CEMS

Aerial, Location, and RWB Map

REMOUNT RD.

PE

R

IM

ET

ER

R

D

AutoCAD SHX Text N

Map Prepared By

Date

Applicant

Map Reference

SCALE

Not to scale

JBC, Goose Creek, South Carolina Remount / Perimeter Road

NRCS Database

April, 2017 JBC Post 4 AVB

320-C Midland Parkway, Summerville, South Carolina, 29485 843.875.3637

ENGINEERING | ARCHITECTURE

Joint Base Charleston / CEMS

Soils Map

PROJECT SITE AREA

AutoCAD SHX Text NOTE: SITE AREA IS COMPRISED OF BoB SOILS, CONFORMING TO HYDROLOGIC SOIL GROUP B, AND BORROW PIT SOILS, CONFORMING TO HYDROLOGIC SOIL GROUP D.

Map Prepared By

Date

Applicant

Map Reference

SCALE

Not to scale

JBC, Goose Creek, South Carolina Remount / Perimeter Road

Quad / Topo Mapping

April, 2017 JBC Post 4 AVB

320-C Midland Parkway, Summerville, South Carolina, 29485 843.875.3637

ENGINEERING | ARCHITECTURE

Joint Base Charleston / CEMS

PROJECT SITE

AREA

B O

L L A

R D

S C

O S

C O

X

SWMU 62SWMU 62

SWMU 62

X

X

X

X

X

X

H

H

H

H

H

H

A B C

D S

G

B

Y

D R

W

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

S

T A

T I O

N

S

O U

H

C

A R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

V

R E

P A

I R

T

I V

E

V

E H

I C

L E

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

N

SCALE: NOT TO SCALE

OVERALL CIVIL GRADING, DRAINAGE, SEDIMENT & EROSION CONTROL PLAN

E M

E M

J R

C

R W

P

R W

P

O V

E R

A L

L

C

I V

A

D I N

G

D

R A

I N

A G

E

S E

D I M

E N

O

S I O

N

C

O N

T R

O

P

A

N

CG101

NO WORK IN THIS AREA

SHEET NOT INCLUDED

AutoCAD SHX Text A/C

AutoCAD SHX Text A/C

AutoCAD SHX Text

TP

AutoCAD SHX Text

TP

AutoCAD SHX Text

TP

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text H

AutoCAD SHX Text S

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 43.2x

AutoCAD SHX Text x

AutoCAD SHX Text 41.4

AutoCAD SHX Text x

AutoCAD SHX Text x

AutoCAD SHX Text 42.3

AutoCAD SHX Text x

AutoCAD SHX Text 42.3

AutoCAD SHX Text 42.8

AutoCAD SHX Text x

A/E SEAL

ELEC.

TRANSFORMER

SWMU 62SWMU 62

SWMU 62

M A

T C

H L

I N

E

A

R E

A

A

M A

T C

H L

I N

E

A

R E

A

B

M A

T C

H L

I N

E

A

R E

A

A

M A

T C

H L

I N

E

A

R E

A

B

INSTALLATION RESTORATION AREA:

"LANDFILL SITE AT 1ST STREET AND AVENUE A-B",

DESIGNATED SWMU 62 PER EXISTING RESOURCE

CONSERVATION AND RECOVERY ACT PERMIT.

SOIL AND GROUNDWATER CONTAMINATION EXIST

IN THIS AREA. REFER TO DRAWING C-501 FOR LAND

DISTURBANCE ENVIRONMENTAL REQUIREMENTS.

TOTAL PROJECT

DISTURBANCE LIMITS: 42,750 SF (0.98 AC.)

PLACE SOD ON SHOULDER FROM EDGE

OF PAVEMENT TO LIMIT OF WORK

(APPROX. 5000 SF) AS SHOWN,

SEE DETAIL DRAWING C-505

PLACE SOD ON SHOULDER FROM EDGE

OF PAVEMENT TO LIMIT OF WORK

(APPROX. 5000 SF) AS SHOWN,

SEE DETAIL DRAWING C-505

D S

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

R E

P A

T

I V

E

V

E H

I C

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

E M

E M

J R

C

R W

P

R W

P

CG102

CIVIL GRADING, DRAINAGE, SEDIMENT & EROSION CONTROL PLAN AREA A

SCALE: 1" = 30'

LEGEND:

EDGE OF ASPHALT

EDGE OF CONCRETE / STRUCTURE

CONTOUR

UNDERGROUND COMMUNICATION LINE

UNDERGROUND ELECTRICAL

STORM DRAIN LINE

TREE LINE

WATER VALVE

COMMUNICATION STRUCTURE

STORM DRAIN INLET

FENCE LINE

WATER LINE

X X X

BOLLARD

MONITORING WELL

SMWU

HANDHOLE

TELECOM STRUCTURE

LIGHT POLE

EXISTING

WETLANDS

NEW

C I V

A

D I N

G

D

R A

I N

A G

E

S

E D

I M

E N

T

E

R O

S I O

N

C

O N

T R

A

N

A

R E

A

A

SILT FENCE

DISTURBANCE LIMITS

1. THE CONTRACTOR SHALL ADHERE TO JBC INSTALLATION ACCESS, DIG

PERMIT, AND UTILITY FLAGGING COORDINATION PROCEDURES. PROVIDE

ADEQUATE NOTICE TO RELEVANT PARTIES PRIOR TO COMMENCEMENT

OF EXCAVATION OF DEMOLITION. OBTAIN COPY OF APPROVED EROSION

CONTROL PERMIT AND OTHER GRADING AND LAND DISTURBANCE

PERMITS REQUIRED BY JBCHS, NWS.

2. SEE C-501 FOR ALL ADDITIONAL ENVIRONMENTAL REQUIREMENTS FOR

JOINT BASE CHARLESTON WEAPONS (INCLUDING GROUNDWATER

MONITORING WELLS, INVESTIGATIVE-DERIVED WASTE, DEWATERING /

CONTAMINATED GROUNDWATER, AND CONTAMINATED SOIL AND

DISPOSAL).

3. ALL DEMOLITION DEBRIS SHALL BE HAULED OFFSITE AND DISPOSED OF

TO AN APPROVED FACILITY LICENSED AND PERMITTED TO ACCEPT LIKE

MATERIALS, AND FACILITY TO HAVE A STATE APPROVED EROSION

CONTROL PLAN IN PLACE.

4. CONTRACTOR TO VERIFY EXISTING UTILITIES, MATERIALS, SIZES AND

LOCATIONS, 1,000 LF IN ADVANCE, AND NOTIFY THE ENGINEER OF

RECORD OF ANY DISCREPANCIES BEFORE ORDERING MATERIALS.

5. CONTRACTOR TO COORDINATE LOCATION/MARKING OF EXISTING SITE

UTILITIES IN AREAS WHERE WORK IS CONDUCTED. THE CONTRACTOR

SHALL ADJUST THE GRADE OF PIPE WORK UP OR DOWN, OR SIDE TO SIDE

TO MISS EXISTING UTILITIES AT NO COST TO THE GOVERNMENT AS

DIRECTED BY THE FIELD ENGINEER.

6. CONTRACTOR SHALL FIELD ADJUST MANHOLE RIMS, FIRE HYDRANTS,

VALVES AND APPURTENANCES TO MATCH FINISHED GROUND

ELEVATIONS.

7. CONTRACTOR SHALL TAKE PRECAUTIONS TO AVOID DAMAGE TO TREES

AND THEIR ROOT SYSTEMS.

8. REFER TO DRAWING C-501 FOR STANDARD SEDIMENT AND EROSION

CONTROL ORDER OF OPERATIONS AND ADDITIONAL INFORMATION. ALL

DISTURBED AREAS TO BE GRASS SEEDED PER INSTALLATION

REQUIREMENTS AFTER ACTIVITY HAS BEEN COMPLETED. UPON

COMPLETION OF WORK, RESTORE AREA TO MATCH EXISTING

CONDITIONS.

9. THE CONTRACTOR WILL BE HELD RESPONSIBLE FOR THE WORKMANLIKE

REPAIR OF ANY DAMAGE DONE TO ANY NEW AND EXISTING SITE ITEMS IN

THE EXECUTION OF HIS WORK UNDER THIS SECTION.

GENERAL NOTES:

N

GRAPHIC SCALE

0 30' 60'

SCALE: 1" = 30'

30'

PAVEMENT (SEE CIVIL SITE PLANS)

SOD

AutoCAD SHX Text

TX

AutoCAD SHX Text M

AutoCAD SHX Text

TX

AutoCAD SHX Text M

AutoCAD SHX Text M

AutoCAD SHX Text C

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 43.2x

AutoCAD SHX Text x

AutoCAD SHX Text 41.4

AutoCAD SHX Text x

AutoCAD SHX Text x

AutoCAD SHX Text 42.3

AutoCAD SHX Text x

AutoCAD SHX Text 42.3

AutoCAD SHX Text 42.8

AutoCAD SHX Text x

AutoCAD SHX Text

A/E SEAL

AutoCAD SHX Text W

AutoCAD SHX Text C

AutoCAD SHX Text M

AutoCAD SHX Text H

AutoCAD SHX Text

TX

S C

O S

C O

X

X

X

X

X

X

X

X

X

X

DROP INLET

RIM: 34.28'

INV OUT: 30.73'

BUILDING

BUILDING 3209

BUILDING 3206

ELEC.

TRANSFORMER

ELEC. METER

PANEL

BACK FLOW PREVENTER

X

X

X

X

M A

T C

H L

I N

E

A

R E

A

A

M A

T C

H L

I N

E

A

R E

A

B

M A

T C

H L

I N

E

A

R E

A

A

M A

T C

H L

I N

E

A

R E

A

B

M A

T C

H L

I N

E

A

R E

A

B

M A

T C

H L

I N

E

A

R E

A

C

M A

T C

H L

I N

E

A

R E

A

B

M A

T C

H L

I N

E

A

R E

A

C

PLACE 25' OF SDR 21 (8") PVC

OUTLET DRAIN AT MINIMUM 2%

SLOPE. REFER TO DETAIL

DRAWINGS C-503 AND C-505.

TOTAL PROJECT

DISTURBANCE LIMITS: 42,750 SF (0.98 AC.)

D S

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

R E

P A

T

I V

E

V

E H

I C

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

E M

E M

J R

C

R W

P

R W

P

CG103

C I V

A

D I N

G

D

R A

I N

A G

E

S

E D

I M

E N

T

E

R O

S I O

N

C

O N

T R

A

N

A

R E

A

B

CIVIL GRADING, DRAINAGE, SEDIMENT & EROSION CONTROL PLAN AREA B

SCALE: 1" = 30'

SILT FENCE

LEGEND:

EDGE OF ASPHALT

EDGE OF CONCRETE / STRUCTURE

CONTOUR

UNDERGROUND COMMUNICATION LINE

UNDERGROUND ELECTRICAL

STORM DRAIN LINE

TREE LINE

WATER VALVE

COMMUNICATION STRUCTURE

STORM DRAIN INLET

FENCE LINE

WATER LINE

X X X

BOLLARD

MONITORING WELL

HANDHOLE

TELECOM STRUCTURE

LIGHT POLE

EXISTING NEW

DISTURBANCE LIMITS

SEWER LINE

1. THE CONTRACTOR SHALL ADHERE TO JBC INSTALLATION ACCESS, DIG

PERMIT, AND UTILITY FLAGGING COORDINATION PROCEDURES. PROVIDE

ADEQUATE NOTICE TO RELEVANT PARTIES PRIOR TO COMMENCEMENT

OF EXCAVATION OF DEMOLITION. OBTAIN COPY OF APPROVED EROSION

CONTROL PERMIT AND OTHER GRADING AND LAND DISTURBANCE

PERMITS REQUIRED BY JBCHS, NWS.

2. SEE C-501 FOR ALL ADDITIONAL ENVIRONMENTAL REQUIREMENTS FOR

JOINT BASE CHARLESTON WEAPONS (INCLUDING GROUNDWATER

MONITORING WELLS, INVESTIGATIVE-DERIVED WASTE, DEWATERING /

CONTAMINATED GROUNDWATER, AND CONTAMINATED SOIL AND

DISPOSAL).

3. ALL DEMOLITION DEBRIS SHALL BE HAULED OFFSITE AND DISPOSED OF

TO AN APPROVED FACILITY LICENSED AND PERMITTED TO ACCEPT LIKE

MATERIALS, AND FACILITY TO HAVE A STATE APPROVED EROSION

CONTROL PLAN IN PLACE.

4. CONTRACTOR TO VERIFY EXISTING UTILITIES, MATERIALS, SIZES AND

LOCATIONS, AND NOTIFY THE ENGINEER OF RECORD OF ANY

DISCREPANCIES BEFORE ORDERING MATERIALS.

5. CONTRACTOR TO COORDINATE LOCATION/MARKING OF EXISTING SITE

UTILITIES IN AREAS WHERE WORK IS CONDUCTED. THE CONTRACTOR

SHALL ADJUST THE GRADE OF PIPE WORK UP OR DOWN, OR SIDE TO SIDE

TO MISS EXISTING UTILITIES AT NO COST TO THE GOVERNMENT AS

DIRECTED BY THE FIELD ENGINEER.

6. CONTRACTOR SHALL FIELD ADJUST MANHOLE RIMS, FIRE HYDRANTS,

VALVES AND APPURTENANCES TO MATCH FINISHED GROUND

ELEVATIONS.

7. CONTRACTOR SHALL TAKE PRECAUTIONS TO AVOID DAMAGE TO TREES

AND THEIR ROOT SYSTEMS.

8. REFER TO DRAWING C-501 FOR STANDARD SEDIMENT AND EROSION

CONTROL ORDER OF OPERATIONS AND ADDITIONAL INFORMATION. ALL

DISTURBED AREAS TO BE GRASSED PER INSTALLATION REQUIREMENTS

AFTER TRENCHING ACTIVITY HAS BEEN COMPLETED. UPON COMPLETION

OF WORK, RESTORE AREA TO MATCH EXISTING CONDITIONS.

9. THE CONTRACTOR WILL BE HELD RESPONSIBLE FOR THE WORKMANLIKE

REPAIR OF ANY DAMAGE DONE TO ANY NEW AND EXISTING SITE ITEMS IN

THE EXECUTION OF HIS WORK UNDER THIS SECTION.

N

GRAPHIC SCALE

0 30' 60'

SCALE: 1" = 30'

30'

GENERAL NOTES:

AutoCAD SHX Text A/C

AutoCAD SHX Text A/C

AutoCAD SHX Text

TP

AutoCAD SHX Text

TP

AutoCAD SHX Text

TP

AutoCAD SHX Text

EM

AutoCAD SHX Text

TX

AutoCAD SHX Text

TX

AutoCAD SHX Text H

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text C

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text H

AutoCAD SHX Text

WESTERN PARKING LOT

AutoCAD SHX Text

EASTERN PARKING LOT

AutoCAD SHX Text

A/E SEAL

AutoCAD SHX Text W

AutoCAD SHX Text C

AutoCAD SHX Text M

AutoCAD SHX Text H

TX

D

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

R E

P A

T

I V

E

V

E H

I C

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

N

E M

E M

J R

C

R W

P

R W

P

S T

A G

I N

G

A

R E

A

A

U

L

R

O U

T E

CG104

MATERIAL LAYDOWN, STAGING & WORK TRAILER LOCATION

DISTURBANCE LIMITS: 7,000 SF MAX

(APPROXIMATELY 175'x40', ENCLOSE WITH SILT FENCING)

RESTORE TO MATCH EXISTING CONDITIONS DURING

PROJECT CLOSEOUT

HAUL ROUTE, INBOUND AND OUTBOUND

CONSTRUCTION TRAFFIC

LEGEND:

NEW

SILT FENCE

DISTURBANCE LIMITS

PROVIDE DEDICATED ENTRY AND EXIT GRAVEL

CONSTRUCTION ENTRANCES, SEE DRAWING C-502

STAGING AREA AND HAUL ROUTE

SCALE: NOT TO SCALE

PROVIDE CONCRETE WASHOUT AREA,

SEE DRAWING C-501

1. STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS PRACTICABLE IN

PORTIONS OF THE SITE WHERE CONSTRUCTION ACTIVITIES HAVE TEMPORARILY OR

PERMANENTLY CEASED, BUT IN NO CASE MORE FOURTEEN (14) DAYS AFTER WORK

HAS CEASED, EXCEPT AS STATED BELOW.

· WHERE STABILIZATION BY THE 14TH DAY IS PRECLUDED BY SNOW COVER OR

FROZEN GROUND CONDITIONS STABILIZATION MEASURES MUST BE INITIATED AS

SOON AS PRACTICABLE.

· WHERE CONSTRUCTION ACTIVITY ON A PORTION OF THE SITE IS TEMPORARILY

CEASED, AND EARTH-DISTURBING ACTIVITIES WILL BE RESUMED WITHIN 14

DAYS, TEMPORARY STABILIZATION MEASURES DO NOT HAVE TO BE INITIATED ON

THAT PORTION OF THE SITE.

2. ALL SEDIMENT AND EROSION CONTROL DEVICES SHALL BE INSPECTED ONCE EVERY

CALENDAR WEEK. IF PERIODIC INSPECTION OR OTHER INFORMATION INDICATES THAT

A BMP HAS BEEN INAPPROPRIATELY, OR INCORRECTLY, THE PERMITTEE MUST

ADDRESS THE NECESSARY REPLACEMENT OR MODIFICATION REQUIRED TO CORRECT

THE BMP WITHIN 48 HOURS OF IDENTIFICATION.

3. PROVIDE SILT FENCE AND/OR OTHER CONTROL DEVICES, AS MAY BE REQUIRED, TO

CONTROL SOIL EROSION DURING UTILITY CONSTRUCTION. ALL DISTURBED AREAS

SHALL BE CLEANED, GRADED AND STABILIZED WITH GRASSING IMMEDIATELY AFTER

THE UTILITY INSTALLATION. FILL, COVER, AND TEMPORARY SEEDING AT THE END OF

EACH DAY ARE RECOMMENDED. IF WATER IS ENCOUNTERED WHILE TRENCHING, THE

WATER SHOULD BE FILTERED TO REMOVE ANY SEDIMENTS BEFORE BEING PUMPED

BACK INTO THE WATERS OF THE STATE.

4. ALL EROSION CONTROL DEVICES SHALL BE PROPERLY MAINTAINED DURING ALL

PHASES OF CONSTRUCTION UNTIL THE COMPLETION OF ALL CONSTRUCTION

ACTIVITIES AND ALL DISTURBED AREAS HAVE BEEN STABILIZED. ADDITIONAL

CONTROL DEVICES MAY BE REQUIRED DURING CONSTRUCTION IN ORDER TO

CONTROL EROSION AND/OR OFFSITE SEDIMENTATION. ALL TEMPORARY CONTROL

DEVICES SHALL BE REMOVED ONCE CONSTRUCTION IS COMPLETE AND THE SITE IS

STABILIZED.

5. THE CONTRACTOR MUST TAKE NECESSARY ACTION TO MINIMIZE THE TRACKING OF

MUD ONTO PAVED ROADWAY(S) FROM CONSTRUCTION AREAS AND THE GENERATION

OF DUST. THE CONTRACTOR SHALL DAILY REMOVE MUD/SOIL FROM PAVEMENT, AS

MAY BE REQUIRED.

6. LITTER, CONSTRUCTION DEBRIS, OILS, FUELS AND BUILDING PRODUCTS WITH

SIGNIFICANT POTENTIAL FOR IMPACT (SUCH AS STOCKPILES OF FRESHLY TREATED

LUMBER) AND CONSTRUCTION CHEMICALS THAT COULD BE EXPOSED TO STORM

WATER MUST BE PREVENTED FROM BECOMING A POLLUTANT SOURCE IN STORM

WATER DISCHARGES.

7. A COPY OF THE SWPPP, INSPECTIONS RECORDS, AND RAINFALL DATA MUST BE

RETAINED AT THE CONSTRUCTION SITE OR A NEARBY LOCATION EASILY ACCESSIBLE

DURING NORMAL BUSINESS HOURS, FROM THE DATE OF COMMENCEMENT OF

CONSTRUCTION ACTIVITIES TO THE DATE THAT FINAL STABILIZATION IS REACHED.

8. INITIATE STABILIZATION MEASURES ON ANY EXPOSED STEEP SLOPE (3H:1V OR

GREATER) WHERE LAND-DISTURBING ACTIVITIES HAVE PERMANENTLY OR

TEMPORARILY CEASED, AND WILL NOT RESUME FOR A PERIOD OF 7 CALENDAR DAYS.

9. MINIMIZE SOIL COMPACTION AND, UNLESS INFEASIBLE, PRESERVE TOPSOIL.

10. MINIMIZE THE DISCHARGE OF POLLUTANTS FROM EQUIPMENT AND VEHICLE WASHING,

WHEEL WASH WATER, AND OTHER WASH WATERS. WASH WATERS MUST BE TREATED

IN A SEDIMENT BASIN OR ALTERNATIVE CONTROL THAT PROVIDES EQUIVALENT OR

BETTER TREATMENT PRIOR TO DISCHARGE;

11. MINIMIZE THE DISCHARGE OF POLLUTANTS FROM DEWATERING OF TRENCHES AND

EXCAVATED AREAS. THESE DISCHARGES ARE TO BE ROUTED THROUGH APPROPRIATE

BMPS (SEDIMENT BASIN, FILTER BAG, ETC.).

12. THE FOLLOWING DISCHARGES FROM SITES ARE PROHIBITED:

· WASTEWATER FROM WASHOUT OF CONCRETE, UNLESS MANAGED BY AN

APPROPRIATE CONTROL;

· WASTEWATER FROM WASHOUT AND CLEANOUT OF STUCCO, PAINT, FORM

RELEASE OILS, CURING

· COMPOUNDS AND OTHER CONSTRUCTION MATERIALS;

· FUELS, OILS, OR OTHER POLLUTANTS USED IN VEHICLE AND EQUIPMENT

OPERATION AND

· MAINTENANCE; AND

· SOAPS OR SOLVENTS USED IN VEHICLE AND EQUIPMENT WASHING.

13. AFTER CONSTRUCTION ACTIVITIES BEGIN, INSPECTIONS MUST BE CONDUCTED AT A

MINIMUM OF AT LEAST ONCE EVERY CALENDAR WEEK AND MUST BE CONDUCTED

UNTIL FINAL STABILIZATION IS REACHED ON ALL AREAS OF THE CONSTRUCTION SITE.

14. IF EXISTING BMPS NEED TO BE MODIFIED OR IF ADDITIONAL BMPS ARE NECESSARY TO

COMPLY WITH THE REQUIREMENTS OF THIS PERMIT AND/OR SC’S WATER QUALITY

STANDARDS, IMPLEMENTATION MUST BE COMPLETED BEFORE THE NEXT STORM

EVENT WHENEVER PRACTICABLE. IF IMPLEMENTATION BEFORE THE NEXT STORM

EVENT IS IMPRACTICABLE, THE SITUATION MUST BE DOCUMENTED IN THE SWPPP AND

ALTERNATIVE BMPS MUST BE IMPLEMENTED AS SOON AS REASONABLY POSSIBLE.

15. A PRE-CONSTRUCTION CONFERENCE MUST BE HELD FOR EACH CONSTRUCTION SITE

WITH AN APPROVED ON-SITE SWPPP PRIOR TO THE IMPLEMENTATION OF

CONSTRUCTION ACTIVITIES. FOR NON-LINEAR PROJECTS THAT DISTURB 10 ACRES OR

MORE THIS CONFERENCE MUST BE HELD ON-SITE UNLESS THE DEPARTMENT HAS

APPROVED OTHERWISE.

SCDHEC STANDARD NOTES:

ENVIRONMENTAL REQUIREMENTS FOR JOINT BASE CHARLESTON:

1. GROUNDWATER MONITORING WELLS

SEVERAL MONITORING WELLS ARE LOCATED NEAR OR WITHIN THE PROPOSED PROJECT AREA AT JOINT BASE

CHARLESTON WEAPONS (JBCHS WEAPONS). EVERY EFFORT SHOULD BE MADE TO PROTECT THE INTEGRITY OF THESE

MONITORING WELLS, AS THEY ARE CURRENTLY BEING USED TO MONITOR THE EFFECTIVENESS OF REMEDIATION

EFFORTS. SEE SITE MAPS PROVIDED FOR WELL LOCATIONS.

ANY WELLS DAMAGED OR DESTROYED DURING THE PROJECT MUST BE REPAIRED OR REPLACED. COORDINATION FOR

PROPER ABANDONMENT AND RE-INSTALLATION SHOULD BE WITH THE RESTORATION PROGRAM MANAGER (RPM), MR.

HAYES PATTERSON AT 843-963-2708 (HAYES.PATTERSON@US.AF.MIL) AND SOUTH CAROLINA DEPARTMENT OF HEALTH

AND ENVIRONMENTAL (SCDHEC) BUREAU OF LAND AND WASTE MANAGEMENT, EITHER THE DIVISION OF WASTE

MANAGEMENT, DEPARTMENT OF DEFENSE CORRECTIVE ACTION OR THE UNDERGROUND STORAGE TANK MANAGEMENT

DIVISION, CORRECTIVE ACTION SECTION, DEPENDING ON THE TYPE OF WELL. NOTE THAT SUCH COORDINATION IS NOT

WITH THE SCDHEC BUREAU OF WATER. WELL REPAIR, ABANDONMENT AND REPLACEMENT ARE THE RESPONSIBILITY OF

THE CONTRACTOR.

IF A WELL IS ABANDONED AND RE-INSTALLED A REGISTERED LAND SURVEYOR MUST SURVEY THE GROUND SURFACE, TOP OF CASING, AND TOP OF CONCRETE WELL PAD, AND PROVIDE THIS INFORMATION TO THE JBCHS WEAPONS RPM.

VERTICAL ELEVATIONS NEED TO BE REFERENCED TO THE NORTH AMERICAN VERTICAL DATUM 1988 (NAVD 88), U.S.

SURVEY FEET AND HORIZONTAL LOCATIONS (NORTHINGS AND EASTINGS) SHOULD BE REFERENCED TO UNIVERSAL

TRANSVERSE MERCATOR COORDINATES ZONE 17 NORTH.

ADDITIONALLY, A SC-CERTIFIED WELL DRILLER MUST BE USED FOR ALL WELLS THAT ARE ABANDONED OR RE-INSTALLED, AND A SCDHEC FORM 1903 (WATER WELL RECORD FORM) MUST BE PREPARED BY THE WELL DRILLER AND SUBMITTED TO

THE PROPER SCDHEC SECTION ABOVE (I.E. NOT THE BUREAU OF WATER) AND A COPY TO THE JBCHS WEAPONS RPM. IF

NECESSARY, ANY RE-INSTALLED MONITORING WELL(S) MUST BE PROPERLY DEVELOPED BY PUMPING UNTIL

GROUNDWATER IS CLEAR OF VISIBLE SEDIMENTS AND FIELD PARAMETER MEASUREMENTS ARE STABILIZED (PH VARIES

TO WITHIN 0.1 STANDARD UNITS, SPECIFIC CONDUCTIVITY VARIES TO WITHIN 10%, AND TEMPERATURE IS CONSTANT FOR

AT LEAST THREE CONSECUTIVE MEASUREMENTS). ALL FIELD DOCUMENTATION, INCLUDING THE DEVELOPMENT LOGS

AND WATER WELL RECORD FORMS, MUST BE PROVIDED TO THE JBCHS WEAPONS RPM.

2. CONTAMINATED SOIL

SOIL AT THE PROPOSED SITE IS CONTAMINATED. THE QUANTITY OF SOIL TO BE REMOVED FROM THE SITE HAS YET TO BE

DETERMINED. ANY SOIL TO BE REMOVED FROM THE SITE SHOULD BE EXCAVATED, CONTAINED IN 55-GALLON DRUMS OR

PLASTIC-LINED ROLL-OFF BINS, COVERED, LABELED WITH HOLD PENDING ANALYSIS STICKERS, AND STORED ON BASE

UNTIL THE SOIL HAS BEEN SAMPLED AND CHARACTERIZED. A COMPOSITE SOIL SAMPLE SHOULD BE COLLECTED FROM

EVERY ROLL-OFF BIN (OR ONE COMPOSITE SAMPLE FROM EVERY FIVE 55-GALLON DRUMS) AND ANALYZED FOR VOCS BY

METHOD 8260B AND TCLP METALS. ONCE CHARACTERIZED, THE APPROPRIATE LABEL(S) SHOULD BE PLACED ON THE

STORAGE CONTAINERS. ANY SOIL EXCAVATED AT THE SITE SHOULD BE PROPERLY DISPOSED OFF-BASE AND MUST BE

COORDINATED THROUGH MR. TOMMY HARDIN AT 843-963-2727. AFTER THE DATA IS EVALUATED, THE WASTE HAS BEEN

CHARACTERIZED, AND A WASTE STREAM CHARACTERIZATION PROCESS DOCUMENT (WSCPD) FOR CONTRACTORS HAS

BEEN PREPARED, THE WSCPD FORM MUST BE SIGNED BY MR. HAYES PATTERSON AT 843-963-2708

(HAYES.PATTERSON@US.AF.MIL) AND ALL THE INFORMATION MUST BE PROVIDED TO MR. TOMMY HARDIN AT

843-963-2727), WELL IN ADVANCE OF SHIPMENT AND PRIOR TO DISPOSAL. MR. HARDIN OR MR. PATTERSON WILL PROVIDE

THE CONTRACTOR A WASTE STREAM CHARACTERIZATION PROCESS DOCUMENT FORM. MR. HARDIN MUST SIGN THE

WASTE MANIFEST PRIOR TO OFF-BASE TRANSPORTATION AND DISPOSAL. THE SAME DISPOSAL PROCEDURES AND

COORDINATION MUST BE ADHERED TO FOR CONTAMINATED GROUNDWATER AS FOR CONTAMINATED SOIL.

2. COASTAL SEEDING SPECIFICATIONS

3. EROSION CONTROL PLAN

1. GENERAL

A. INSTALL PERMANENT VEGETATIVE COVER AND THE LONG-TERM EROSION PROTECTION MEASURES OR

STRUCTURES AS SOON AS PRACTICAL IN THE DEVELOPMENT PROCESS.

B. PROVIDE FOR HANDLING THE INCREASED RUNOFF CAUSED BY CHANGED SOIL AND SURFACE

CONDITIONS. USE EFFECTIVE MEANS TO CONSERVE EXISTING ON-SITE SOIL INCLUDING THE USE OF

DIVERSION DITCHES, GRASSED WATERWAYS AND STORM SEWERS.

C. PLACE SILT FENCE BARRIERS AT LOCATIONS SHOWN ON PLAN. SILT BARRIERS SHALL BE MAINTAINED IN

PLACE AND IN GOOD CONDITION UNTIL GROUND COVER IS ESTABLISHED.

D. ALL DISTURBED AREAS NOT PAVED SHALL BE GRASSED. USE TEMPORARY PLANT COVER, MULCHING, AND/OR STRUCTURES TO CONTROL RUNOFF AND PROTECT AREAS SUBJECT TO EROSION DURING

CONSTRUCTION.

E. CONTRACTOR SHALL PROVIDE DUMPSTER OF SUFFICIENT SIZE AND NUMBER TO CONTAIN THE SOLID

WASTE GENERATED BY THE PROJECT.

F. CONTRACTOR SHALL FREQUENTLY REMOVE GARBAGE TO MAINTAIN A CLEAN CONSTRUCTION SITE AND

MINIMIZE THE EXPOSURE OF WASTE TO STORM WATER.

PERMANENT SEEDING:

“COOL SEASON”: PLANTED BETWEEN 1 SEPTEMBER AND FEBRUARY 28

SPECIES RATE

HULLED BERMUDA 44 LBS./AC.

UNHULLED BERMUDA 44 LBS./AC.

CENTIPEDE 22 LBS./AC.

“WARM SEASON”: PLANTED BETWEEN 1 MARCH AND 15 AUGUST

SPECIES RATE

SERICEA LESPEDEZA (CLAY SOILS) 44 LBS./AC.

WEEPING LOVE GRASS (SANDY SOILS) 44 LBS./AC.

CENTIPEDE 22 LBS./AC.

TEMPORARY SEEDING:

RECOMMENDED “COOL SEASON” ONLY: PLANTED BETWEEN 1 SEPTEMBER AND 3 MARCH

SPECIES RATE

RYE GRAIN 56 LBS./AC.

RYEGRASS 50 LBS./AC.

A. ALL AREAS WHICH ARE DISTURBED BY THE CONTRACTOR SHALL BE SEEDED.

B. WHEN THE PIPE TRENCH APPROACHES A STREAM, INSTALL A CHECK DAM OR DO NOT

COMPLETELY EXCAVATE THE TRENCH UNTIL PIPE INSTALLATION WILL IMMEDIATELY

FOLLOW TO PREVENT UNOBSTRUCTED FLOW FROM THE TRENCH TO THE STREAM.

C. PROVIDE A DOUBLE ROW OF SILT FENCE IN ALL AREAS WHERE A 50' BUFFER CAN'T BE

MAINTAINED BETWEEN THE DISTURBED AREA AND THE WETLANDS. A 10' BUFFER SHALL

BE LEFT WITH THE WETLANDS AND SILT FENCE.

SEDIMENT AND EROSION CONTROL NOTES

D S

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

R E

P A

T

I V

E

V

E H

I C

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

E M

E M

J R

C

R W

P

R W

P

C I V

T

A I L

S

C-501

1. CONCRETE TRUCKS SHOULD NOT TYPICALLY BE WASHED ON SITE. HOWEVER, IF THIS DOES NEED TO OCCUR THE

FOLLOWING BMPS SHOULD BE USED.

2. TEMPORARY CONCRETE WASHOUT FACILITIES SHOULD BE LOCATED A MINIMUM OF 50 FEET FROM STORM DRAIN

INLETS, OPEN DRAINAGE FACILITIES, AND WATERCOURSES, UNLESS DETERMINED INFEASIBLE BY THE ENGINEER OR

CRM. EACH FACILITY SHOULD BE LOCATED AWAY FROM CONSTRUCTION TRAFFIC OR ACCESS AREAS TO PREVENT

DISTURBANCE OR TRACKING.

3. INSTALL A SIGN ADJACENT TO EACH WASHOUT FACILITY TO INFORM CONCRETE EQUIPMENT OPERATORS TO UTILIZE

THE PROPER FACILITIES.

4. TEMPORARY CONCRETE WASHOUT FACILITIES SHOULD BE CONSTRUCTED ABOVE GRADE OR BELOW GRADE AT THE

OPTION OF THE CONTRACTOR. TEMPORARY CONCRETE WASHOUT FACILITIES SHOULD BE CONSTRUCTED AND

MAINTAINED IN SUFFICIENT QUANTITY AND SIZE TO CONTAIN ALL LIQUID AND CONCRETE WASTE GENERATED BY

WASHOUT OPERATIONS.

5. TEMPORARY WASHOUT FACILITIES SHOULD HAVE A TEMPORARY PIT OR BERMED AREAS OF SUFFICIENT VOLUME TO

COMPLETELY CONTAIN ALL LIQUID AND WASTE CONCRETE MATERIALS GENERATED DURING WASHOUT

PROCEDURES.

6. PERFORM WASHOUT OF CONCRETE MIXER TRUCKS IN DESIGNATED AREAS ONLY. WASHOUT MAY BE COLLECTED IN

AN IMPERMEABLE BAG FOR DISPOSAL. SEE ALSO CONCRETE TRUCK WASHOUT.

7. ONCE CONCRETE WASTES ARE WASHED INTO THE DESIGNATED AREA AND ALLOWED TO HARDEN, THE CONCRETE

SHOULD BE BROKEN UP, REMOVED, AND DISPOSED OF PER SOLID WASTE MANAGEMENT.

WASHOUT INSTALLATION NOTES:

1. THE ENGINEER OR CRM SHOULD MONITOR ON SITE CONCRETE WASTE STORAGE AND DISPOSAL PROCEDURES AT

LEAST WEEKLY.

2. THE ENGINEER OR CRM SHOULD MONITOR CONCRETE WORKING TASKS, SUCH AS SAW CUTTING, CORING, GRINDING

AND GROOVING DAILY TO ENSURE PROPER METHODS ARE EMPLOYED.

3. TEMPORARY CONCRETE WASHOUT FACILITIES SHOULD BE MAINTAINED TO PROVIDE ADEQUATE HOLDING CAPACITY

WITH A MINIMUM FREEBOARD OF 4-INCHES FOR ABOVE GRADE FACILITIES AND 12-INCHES FOR BELOW GRADE

FACILITIES. MAINTAINING TEMPORARY CONCRETE WASHOUT FACILITIES SHOULD INCLUDE REMOVING AND

DISPOSING OF HARDENED CONCRETE AND RETURNING THE FACILITIES TO A FUNCTIONAL CONDITION.

4. EXISTING FACILITIES SHOULD BE CLEANED, OR NEW FACILITIES SHOULD BE CONSTRUCTED AND READY FOR USE

ONCE THE WASHOUT IS 75% FULL.

5. TEMPORARY CONCRETE WASHOUT FACILITIES SHOULD BE INSPECTED FOR DAMAGE (I.E., TEARS IN PVC LINER, MISSING SANDBAGS, ETC.). DAMAGED FACILITIES SHOULD BE REPAIRED IMMEDIATELY.

WASHOUT MAINTENANCE NOTES:

CONCRETE WASHOUT AREA

SCALE: NOT TO SCALE

AutoCAD SHX Text

A/E SEAL

AutoCAD SHX Text 10'

AutoCAD SHX Text 15'

AutoCAD SHX Text %%uABOVE GRADE (PLAN VIEW)

AutoCAD SHX Text %%uSECTION B-B

AutoCAD SHX Text

STAKE (TYP.)

AutoCAD SHX Text TWO-STACKED 2 x 12 ROUGH WOOD FRAME

AutoCAD SHX Text

10 MIL PLASTIC LINING

AutoCAD SHX Text

10 MIL PLASTIC LINING

AutoCAD SHX Text

WOOD FRAME SECURELY FASTENED WITH TWO STAKES

AutoCAD SHX Text B

AutoCAD SHX Text B

NOTE: OR SIMILAR BASED ON THE SCDHEC BMP GUIDEBOOK

SCALE: NOT TO SCALE

SILT FENCE INSTALLATION

SCALE: NOT TO SCALE

FLAT BOTTOM TRENCH DETAIL

M

A

X

I

M

U

M

A

C

I

FILTER FABRIC

BACKFILL TRENCH WITH

COMPACTED EARTH

COMPACTED EARTH

COMPACTED EARTH

FILTER FABRIC

6"

6"

24" (MINIMUM)

24" (MINIMUM)

6"

R

U

N

O

F

F

RUNOFF

RUNOFF

18-IN. TO 24-IN.

BURY FABRIC

USE EITHER FLAT-BOTTOM OR

V-BOTTOM TRENCH SEE DETAILS

FILTER

FABRIC

BURY FILTER FABRIC AT LEAST 12"

1.25 LB./LINEAR FT.

STEEL POSTS

HEAVY DUTY

PLASTIC TIE FOR

STEEL POSTS

(RESTRICT TO

TOP 8-INCHES

OF FABRIC)

18" - 24"

SILT FENCE - GENERAL NOTES

1. DO NOT PLACE SILT FENCE ACROSS CHANNELS OR IN OTHER AREAS SUBJECT

TO CONCENTRATED FLOWS. SILT FENCE SHOULD NOT BE USED AS A VELOCITY

CONTROL BMP. CONCENTRATED FLOWS ARE ANY FLOWS GREATER THAN 0.5

CFS.

2. MAXIMUM SHEET OR OVERLAND FLOW PATH LENGTH TO THE SILT FENCE SHALL

BE 100-FEET.

3. MAXIMUM SLOPE STEEPNESS (NORMAL [PERPENDICULAR] TO THE FENCE LINE)

SHALL BE 2:1.

4. SILT FENCE JOINTS, WHEN NECESSARY, SHALL BE COMPLETED BY ONE OF THE

FOLLOWING OPTIONS: WRAP EACH FABRIC TOGETHER AT A SUPPORT POST

WITH BOTH ENDS FASTENED TO THE POST, WITH A 1-FOOT MINIMUM OVERLAP;

- OVERLAP SILT FENCE BY INSTALLING 3-FEET PASSED THE SUPPORT POST TO

WHICH THE NEW SILT FENCE ROLL IS ATTACHED. ATTACH OLD ROLL TO NEW

ROLL WITH HEAVY-DUTY PLASTIC TIES; OR,

- OVERLAP ENTIRE WIDTH OF EACH SILT FENCE ROLL FROM ONE SUPPORT POST

TO THE NEXT SUPPORT POST.

5. ATTACH FILTER FABRIC TO THE STEEL POSTS USING HEAVY-DUTY PLASTIC TIES

THAT ARE EVENLY SPACED WITHIN THE TOP 8-INCHES OF THE FABRIC.

4. INSTALL THE SILT FENCE PERPENDICULAR TO THE DIRECTION OF THE

STORMWATER FLOW AND PLACE THE SILT FENCE THE PROPER DISTANCE FROM

THE TOE OF STEEP SLOPES TO PROVIDE SEDIMENT STORAGE AND ACCESS FOR

MAINTENANCE AND CLEANOUT.

5. INSTALL SILT FENCE CHECKS (TIE-BACKS) EVERY 50-100 FEET, DEPENDENT ON

SLOPE, ALONG SILT FENCE THAT IS INSTALLED WITH SLOPE AND WHERE

CONCENTRATED FLOWS ARE EXPECTED OR ARE DOCUMENTED ALONG THE

PROPOSED/INSTALLED SILT FENCE.

HEAVY DUTY PLASTIC TIES

FILTER FABRIC

HEAVY DUTY PLASTIC TIES

PLAN SYMBOL

SILT FENCE - POST REQUIREMENTS

1. SILT FENCE POSTS MUST BE 48-INCH LONG STEEL POSTS THAT MEET, AT A

MINIMUM, THE FOLLOWING PHYSICAL CHARACTERISTICS.

- COMPOSED OF A HIGH STRENGTH STEEL WITH A MINIMUM YIELD STRENGTH OF

50,000 PSI.

- INCLUDE A STANDARD "T" SECTION WITH A NOMINAL FACE WIDTH OF

1.38-INCHES AND A NOMINAL "T" LENGTH OF 1.48-INCHES.

- WEIGH 1.25 POUNDS PER FOOT (± 8%)

2. POSTS SHALL BE EQUIPPED WITH PROJECTIONS TO AID IN FASTENING OF FILTER

FABRIC.

3. STEEL POSTS MAY NEED TO HAVE A METAL SOIL STABILIZATION PLATE WELDED

NEAR THE BOTTOM WHEN INSTALLED ALONG STEEP SLOPES OR INSTALLED IN

LOOSE SOILS. THE PLATE SHOULD HAVE A MINIMUM CROSS SECTION OF

17-SQUARE INCHES AND BE COMPOSED OF 15 GAUGE STEEL, AT A MINIMUM. THE

METAL SOIL STABILIZATION PLATE SHOULD BE COMPLETELY BURIED.

4. INSTALL POSTS TO A MINIMUM OF 24-INCHES. A MINIMUM HEIGHT OF 1- TO 2-

INCHES ABOVE THE FABRIC SHALL BE MAINTAINED, AND A MAXIMUM HEIGHT OF

3 FEET SHALL BE MAINTAINED ABOVE THE GROUND.

5. POST SPACING SHALL BE AT A MAXIMUM OF 6-FEET ON CENTER.

SILT FENCE - FABRIC REQUIREMENTS

1. SILT FENCE MUST BE COMPOSED OF WOVEN GEOTEXTILE FILTER FABRIC THAT

CONSISTS OF THE FOLLOWING REQUIREMENTS:

- COMPOSED OF FIBERS CONSISTING OF LONG CHAIN SYNTHETIC POLYMERS OF

AT LEAST 85% BY WEIGHT OF POLYOLEFINS, POLYESTERS, OR POLYAMIDES

THAT ARE FORMED INTO A NETWORK SUCH THAT THE FILAMENTS OR YARNS

RETAIN DIMENSIONAL STABILITY RELATIVE TO EACH OTHER;

- FREE OF ANY TREATMENT OR COATING WHICH MIGHT ADVERSELY ALTER ITS

PHYSICAL PROPERTIES AFTER INSTALLATION;

- FREE OF ANY DEFECTS OR FLAWS THAT SIGNIFICANTLY AFFECT ITS PHYSICAL

AND/OR FILTERING PROPERTIES; AND,

- HAVE A MINIMUM WIDTH OF 36-INCHES.

2. USE ONLY FABRIC APPEARING ON SC DOT'S QUALIFIED PRODUCTS LISTING

(QPL), APPROVAL SHEET #34, MEETING THE REQUIREMENTS OF THE MOST

CURRENT EDITION OF THE SC DOT STANDARD SPECIFICATIONS FOR HIGHWAY

CONSTRUCTION.

3. 12-INCHES OF THE FABRIC SHOULD BE PLACED WITHIN EXCAVATED TRENCH

AND TOED IN WHEN THE TRENCH IS BACKFILLED.

4. FILTER FABRIC SHALL BE PURCHASED IN CONTINUOUS ROLLS AND CUT TO

THE LENGTH OF THE BARRIER TO AVOID JOINTS.

5. FILTER FABRIC SHALL BE INSTALLED AT A MINIMUM OF 24-INCHES ABOVE THE

GROUND.

1. THE KEY TO FUNCTIONAL SILT FENCE IS WEEKLY INSPECTIONS, ROUTINE

MAINTENANCE, AND REGULAR SEDIMENT REMOVAL.

2. REGULAR INSPECTIONS OF SILT FENCE SHALL BE CONDUCTED ONCE EVERY

CALENDAR WEEK AND, AS RECOMMENDED, WITHIN 24-HOURS AFTER EACH

RAINFALL EVEN THAT PRODUCES 1/2-INCH OR MORE OF PRECIPITATION.

3. ATTENTION TO SEDIMENT ACCUMULATIONS ALONG THE SILT FENCE IS

EXTREMELY IMPORTANT. ACCUMULATED SEDIMENT SHOULD BE CONTINUALLY

MONITORED AND REMOVED WHEN NECESSARY.

4. REMOVE ACCUMULATED SEDIMENT WHEN IT REACHES 1/3 THE HEIGHT OF THE

SILT FENCE.

5. REMOVED SEDIMENT SHALL BE PLACED IN STOCKPILE STORAGE AREAS OR

SPREAD THINLY ACROSS DISTURBED AREA. STABILIZE THE REMOVED SEDIMENT

AFTER IT IS RELOCATED.

6. CHECK FOR AREAS WHERE STORMWATER RUNOFF HAS ERODED A CHANNEL

BENEATH THE SILT FENCE, OR WHERE THE FENCE HAS SAGGED OR COLLAPSED

DUE TO RUNOFF OVERTOPPING THE SILT FENCE. INSTALL CHECKS/TIE-BACKS

AND/OR REINSTALL SILT FENCE, AS NECESSARY.

7. CHECK FOR TEARS WITHIN THE SILT FENCE, AREAS WHERE SILT FENCE HAS

BEGUN TO DECOMPOSE, AND FOR ANY OTHER CIRCUMSTANCE THAT MAY

RENDER THE SILT FENCE INEFFECTIVE. REMOVED DAMAGED SILT FENCE AND

REINSTALL NEW SILT FENCE IMMEDIATELY.

8. SILT FENCE SHOULD BE REMOVED WITHIN 30 DAYS AFTER FINAL STABILIZATION

IS ACHIEVED AND ONCE IT IS REMOVED, THE RESULTING DISTURBED AREA SHALL

BE PERMANENTLY

STABILIZED.

SILT FENCE - INSPECTION & MAINTENANCE

SCALE: NOT TO SCALE

V-SHAPED TRENCH DETAIL

D S

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

R E

P A

T

I V

E

V

E H

I C

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

E M

E M

J R

C

R W

P

R W

P

C I V

T

A I L

S

C-502

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION: LIST OF QUALIFIED PROVIDERS

OF SILT FENCING / LOW FLOW DROP INLET PROTECTION GEOTEXTILE FABRICS

COASTAL SITE SUPPLY, INC.

P O BOX 60988

NORTH CHARLESTON, SC 29419

877-744-9747

FAX: 843-744-9750

ATTN: BILLY DENSON

PROTECH ENVIRONMENTAL SUPPLY

1500 CONTINENTAL BLVD., SUITE C/F

CHARLOTTE, NC 28273

(704)676-9788

FAX: (704)676-9791

ATTN: MITCH PERKINS

WILLACOOCHEE INDUSTRIAL FABRICS

P. O. BOX 599

HIGHWAY 82 WEST

WILLACOOCHEE, GA 31650

(912) 534-5757

FAX: (912) 534-5533

PROPEX, INC.

P O BOX 22788

6025 LEE HIGHWAY, SUITE 425

CHATTANOOGA, TN 37422

(800)621-1273

FAX: (423)899-7619

WWW.GEOTEXTILE.COM

ACF ENVIRONMENTAL

2831 CARDWELL ROAD

RICHMOND, VA 23234

(800)448-3636

FAX: (804)743-7779

WWW.ACFENVIRONMENTAL.COM

DDD EROSION CONTROL, INC.

P O BOX 694

1383 INDUSTRIAL DRIVE

ASHBURN, GA 31714

(229) 567-0751

FAX: (229) 567-0752

EMAIL: DDDEROSION@WINDSTREAM.NET

WWW.3DEROSION.COM

ATTN: DON DAVIS

BELTON INDUSTRIES, INC.

PO BOX 127 (2) STYLE 941

BELTON, SC 29627 (3) STYLE 945

(864) 338-5711

ATTN: MR. DAVID GALLOWAY

THRACE-LINQ

2550 WEST FIFTH NORTH ST.

SUMMERVILLE, SC 29483-9699

(803) 875-8280

(800) 445-4675

CONSTRUCTION FABRICS & SUPPLY

1603 JAMES P. ROGERS DRIVE

VALDOSTA, GEORGIA 31601

(229) 244-0004

ATTN: ANGIE ANDERSON OR

JEFF COPPAGE

HANES GEOCOMPONENTS

10800 S. COMMERCE BLVD. #9

SUITE L, CHARLOTTE, NC 28273

(704)588-7626

FAX: (704)588-7972

ATTN: KEITH GREGORY

WWW.HANESGEO.COM

SCALE: NOT TO SCALE

TEMPORARY GRAVEL CONSTRUCTION ENTRANCE/EXIT

CONSTRUCTION ENTRANCE - GENERAL NOTES

CONSTRUCTION ENTRANCE - INSPECTION & MAINTENANCE

1. STABILIZED CONSTRUCTION ENTRANCES SHOULD BE USED

AT ALL POINTS WHERE TRAFFIC WILL EGRESS/INGRESS A

CONSTRUCTION SITE ONTO A PUBLIC ROAD OR ANY

IMPERVIOUS SURFACES, SUCH AS PARKING LOTS.

2. INSTALL A NON-WOVEN GEOTEXTILE FABRIC PRIOR TO

PLACING ANY STONE.

3. INSTALL A CULVERT PIPE ACROSS THE ENTRANCE WHEN

NEEDED TO PROVIDE POSITIVE DRAINAGE.

4. THE ENTRANCE SHALL CONSIST OF 2-INCH TO 3-INCH D50

STONE PLACED AT A MINIMUM DEPTH OF 6-INCHES.

5. MINIMUM DIMENSIONS OF THE ENTRANCE SHALL BE

15-FEET WIDE BY 20-FEET LONG, AND MAY BE MODIFIED AS

NECESSARY TO ACCOMMODATE SITE CONSTRAINTS.

6. THE EDGES OF THE ENTRANCE SHALL BE TAPERED OUT

TOWARDS THE ROAD TO PREVENT TRACKING AT THE EDGE

OF THE ENTRANCE.

7. DIVERT ALL SURFACE RUNOFF AND DRAINAGE FROM THE

STONE PAD TO A SEDIMENT TRAP OR BASIN OR OTHER

SEDIMENT TRAPPING STRUCTURE.

8. LIMESTONE MAY NOT BE USED FOR THE STONE PAD.

1. THE KEY TO FUNCTIONAL CONSTRUCTION ENTRANCES IS WEEKLY

INSPECTIONS, ROUTINE MAINTENANCE, AND REGULAR SEDIMENT

REMOVAL.

2. REGULAR INSPECTIONS OF CONSTRUCTION ENTRANCES SHALL BE

CONDUCTED ONCE EVERY CALENDAR WEEK AND, AS RECOMMENDED,

WITHIN 24-HOURS AFTER EACH RAINFALL EVEN THAT PRODUCES

1/2-INCH OR MORE OF PRECIPITATION.

3. DURING REGULAR INSPECTIONS, CHECK FOR MUD AND SEDIMENT

BUILDUP AND PAD INTEGRITY. INSPECTION FREQUENCIES MAY NEED TO

BE MORE FREQUENT DURING LONG PERIODS OF WET WEATHER.

4. RESHAPE THE STONE PAD AS NECESSARY FOR DRAINAGE AND RUNOFF

CONTROL.

5. WASH OR REPLACE STONES AS NEEDED AND AS DIRECTED BY SITE

INSPECTOR. THE STONE IN THE ENTRANCE SHOULD BE WASHED OR

REPLACED WHENEVER THE ENTRANCE FAILS TO REDUCE THE AMOUNT

OF MUD BEING CARRIED OFF-SITE BY VEHICLES. FREQUENT WASHING

WILL EXTEND THE USEFUL LIFE OF STONE PAD.

6. IMMEDIATELY REMOVE MUD AND SEDIMENT TRACKED OR WASHED

ONTO ADJACENT IMPERVIOUS SURFACES BY BRUSHING OR SWEEPING.

FLUSHING SHOULD ONLY BE USED WHEN THE WATER CAN BE

DISCHARGED TO A SEDIMENT TRAP OR BASIN.

7. DURING MAINTENANCE ACTIVITIES, ANY BROKEN PAVEMENT SHOULD BE

REPAIRED IMMEDIATELY.

8. CONSTRUCTION ENTRANCES SHOULD BE REMOVED AFTER THE SITE

HAS REACHED FINAL STABILIZATION. PERMANENT VEGETATION SHOULD

REPLACE AREAS FROM WHICH CONSTRUCTION ENTRANCES HAVE BEEN

REMOVED, UNLESS AREA WILL BE CONVERTED TO AN IMPERVIOUS

SURFACE TO SERVE POST-CONSTRUCTION.

6" MIN.

N

N

UNDERLYING NON-WOVEN GEOTEXTILE FABRIC

ROCK PAD THICKNESS

ROCK PAD WIDTH

ROCK PAD LENGTH

ROCK PAD STONE SIZE

6 INCHES

24 FEET

D50 = 2-3 INCHES

20 FEET

AVERAGE STONE DIAMETER OF

2"-3" WITH A 6" MINIMUM DEPTH

SIZE

SPECIFICATION

AutoCAD SHX Text

SF

AutoCAD SHX Text

SF

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT Y

BIL

D K

R E

P A

T

I V

E

V

E H

I C

R

R I E

R

P

O S

T

DKGV 13-2150

07-21-2017

D R

A W

I N

G

R

E V

I S

I O

N S

R E

V

D E

S C

R I P

T I O

N P

R E

P

B

Y D

A T

E A

P P

R D

E M

E M

J R

C

R W

P

R W

P

C I V

T

A I L

S

C-503

CONCRETE CURB

NOT TO SCALE

PAVEMENT REPLACEMENT DETAIL

SCALE: NOT TO SCALE

DITCH LINE

UTILITY (IF APPLICABLE)

FULL-DEPTH

SAW CUT

SELECTIVE BACKFILL

TAMPED IN 6" LAYERS

TO 95% COMPACTION

PER ASTM D-1557

FINISH GRADE

COMPACTED EARTH

CONCRETE WALK

TOOLED EDGES

SLOPE

2% MAXIMUM

5' WIDTH

V A

R I E

S

5'

CONTRACTION JOINTS

50' MAX. SPACING BETWEEN EXPANSION JOINTS

1/4" EXP. JT.

ASPHALT

SCALE: NOT TO SCALE

XXXXX X X X

CONCRETE SIDEWALK DETAIL

TYPICAL SIDEWALK SECTION

1. ALL SIDEWALKS SHALL BE 4" THICK.

2. CONTRACTION JOINTS SHALL BE 1" DEEP AND EDGED WITH 1/8" RADIUS.

3. EXPANSION MATERIAL 1/2" THICK SHALL BE REQUIRED WHERE SIDEWALK ABUTS

CONCRETE STRUCTURE.

4. CONTRACTION JOINTS SHALL BE SPACED AT 5'-0"

5. SIDEWALKS TO LIGHT BROOM FINISH

6. ALL JOINTS AND EDGES TO BE TOOLED.

7. SIDEWALKS TO BRUSHED AND TOOLED.

1"

PRIME COAT

SCALE: NOT TO SCALE

MINIMUM PAVEMENT SECTION

12" COMPACTED

SUBGRADE 95%

ASTM D-1557

8" STONE BASE

(SCDOT SPEC 305)

3.0" ASPHALTIC CONC.

SURFACE COURSE, APPLY IN 2

(1

") LIFTS (SCDOT SPEC 402)

SCALE: NOT TO SCALE

6x6-W2.0xW2.0 WWF

3/8" DIA. PAN HEAD

MACHINE SCREW W/HEX

NUT & WASHERS

FIBER OR PVC WASHER

SIGN

2'-0"

GALVANIZED 3 LB/FT "U"

CHANNELED POST, PAINTED

JBC DARK BRONZE STD.

SCDOT MINIMUM

REQUIREMENTS FOR

BREAK-AWAY INSTALLATION

M

I N

I M

U

Q

U I R

E D

T

T O

M

O

F

S

I G

N

SIGN PLACEMENT AND ATTACHMENT

SCALE: NOT TO SCALE

PLACE 1

" SURFACE COURSE

OVERLAY AT MILLED

TRANSITION AREA

SEE PAVEMENT

SECTION DETAIL

EXISTING

PAVEMENT

8"

PIPE ZONE

2" MIN.

12" MIN.

6"

MATERIAL

GRANULAR

COMPACTED

CLASS 2 OR 3 BACKFILL TO BE PLACED

IN LAYERS 8" MAX COMPACTED DEPTH

COMPACTED TO A DENSITY REQUIRED

BY SPECIFICATIONS.

CROSS SECTION

SCALE: NOT TO SCALE

STORM PIPE BEDDING

32"

AutoCAD SHX Text

A/E SEAL

AutoCAD SHX Text 16"

AutoCAD SHX Text 6"

AutoCAD SHX Text

CONCRETE CURB

AutoCAD SHX Text

CONCRETE PAVEMENT

AutoCAD SHX Text

6" APPROX.

2'

D R

C H

K

B

Y

A P P R O V E D

B Y

D A

T E

D A

T E

D A

T E

D A

T E

F O

R

J O

I N

T

B

A S

E

C

H A

R L

E S

T O

N

J O

I N

T

B

A S

E

C

H A

R L E

S T

O N

AI

R

MO

BI

LIT

Y

CO

MM

AN

D

DE

PA

RT

ME

NT

O

F

DE

FE

NS

E W

E A

P O

A

T I O

N

S

O U

R

O L I N

A

DRAWING SIZE: ANSI D (22"x34")

PROJECT NO.

RECORD DRAWING DATE

SHEET

IF SHEET IS LESS THAN 22"x34" (ANSI D) IT IS A REDUCED PRINT, SCALE ACCORDINGLY.

OF

320-C Midland Parkway, Summerville, SC, 29485

ENGINEERING | ARCHITECTURE

CEMS Project No: 15154C Project Manager: C. Hinson

300 N. 3rd St., Suite 110, Wilmington, NC, 28401

843.875.3637

252.649.0334

G

E W

BAIR AS

IN628TH

IRA D

MANCOM

MO

IT Y

BIL

IRA D

MANCOM

MO

IT…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.