1-_Combined_Specification.pdf
PDF 5 MB Posted
- Attached to
- C17 Runway Reconstruction
- Solicitation number
- FA4418-15-R-0013
About this file
1- Combined Specification Set
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0001.pdf | ||
| Q A_Answers_for_NAAF.docx | DOCX document | |
| Pre-proposal_Record_of_Attendance.pdf | ||
| Pre-proposal_Meeting_Minutes.pdf | ||
| 2_-_Combined_Drawing_Set.pdf | ||
| 0-FA4418-15-R-0013_Solicitation.pdf | ||
| 5-_Material_Submittal.pdf | ||
| 3-_WAGE_DETERMINATION.pdf | ||
| 6-_COSPP.pdf | ||
| 4-_Green_Procurement.pdf | ||
| 7-_Design_Narrative.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair C17 Landing Zone SBML 11-1056 North Auxiliary Airfield Final Design Submittal
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 13 SPECIAL PROJECT PROCEDURES
01 35 23 OPERATIONAL SAFETY ON AIRFIELDS DURING CONSTRUCTION
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 50 10 ENVIRONMENTAL (JB CHS)
01 54 00 GREEN PROCUREMENT (JB CHS)
01 57 20 WASTE MANAGEMENT (JB CHS)
01 57 50 TEMPORARY ENVIRONMENTAL CONTROLS (JB CHS) (INCLUSIVE OF
STORM WATER POLLUTION PREVENTION PLAN)
01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 78 02.00 20 PROJECT RECORD DOCUMENTS (JB CHS)
DIVISION 02 - EXISTING CONDITIONS
02 01 00.00 GEOTECHNICAL DATA
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 26 - ELECTRICAL
26 56 20.00 10 AIRFIELD AND HELIPORT LIGHTING AND VISUAL NAVIGATION AIDS
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.17 COLD MILLING OF BITUMINOUS PAVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 01 26.71 GROOVING FOR AIRFIELD PAVEMENTS
32 11 23 GRADED-CRUSHED AGGREGATE BASE COURSE
32 12 10 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 HOT-MIX ASPHALT AIRFIELD PAVING
32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY
PAVEMENTS
32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS
32 17 24.00 10 PAVEMENT MARKINGS
32 92 19 SEEDING
32 92 23 SODDING
PROJECT TABLE OF CONTENTS Page 1
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NO. TITLE
G001 TITLE SHEET
G100 BASIS OF DESIGN
G200 CONSTRUCTION SAFETY PHASING PLAN (CSPP)
G201 CSPP - PARTIAL AIRSPACE IMAGINARY SURFACES
G202 CSPP - NOTES
C001 CIVIL ABBREVIATIONS AND GENERAL NOTES
C101 EXISTING SITE AND DEMOLITION PLAN - AREA 1
C102 EXISTING SITE AND DEMOLITION PLAN - AREA 2
C103 EXISTING SITE AND DEMOLITION PLAN - AREA 3
C201 SITE PLAN - AREA 1
C202 SITE PLAN - AREA 2
C203 SITE PLAN - AREA 3
C210 LANDING ZONE GROOVING PLAN - OVERALL
C220 MARKING PLAN - LZ
C221 MARKING PLAN - RWY 6/24
C225 MARKING DETAILS - RWY 6/24
C301 GRADING AND STORM DRAINAGE PLAN - AREA 1
DOCUMENT 00 01 15 Page 1
DRAWING NO. TITLE
C302 GRADING AND STORM DRAINAGE PLAN - AREA 2
C303 GRADING AND STORM DRAINAGE PLAN - AREA 3
C310 LANDING ZONE CENTERLINE PROFILE
C311 LANDING ZONE CENTERLINE PROFILE
C320 CROSS SECTIONS
C321 CROSS SECTIONS
C322 CROSS SECTIONS
C323 CROSS SECTIONS
C620 PAVING SECTIONS
C621 PAVING DETAILS
C622 PAVING DETAILS
C623 PAVING DETAILS
C630 GRADING AND STORM DRAINAGE DETAILS
C640 UTILITY DETAILS
C700 EROSION CONTROL PLAN - OVERALL AIRFIELD
C701 INITIAL EROSION CONTROL PLAN - AREA 1
C702 INITIAL EROSION CONTROL PLAN - AREA 2
C703 INITIAL EROSION CONTROL PLAN - AREA 3
C711 INTERMEDIATE EROSION CONTROL PLAN - AREA 1
C712 INTERMEDIATE EROSION CONTROL PLAN - AREA 2
C713 INTERMEDIATE EROSION CONTROL PLAN - AREA 3
C721 FINAL EROSION CONTROL PLAN - AREA 1
C722 FINAL EROSION CONTROL PLAN - AREA 2
C723 FINAL EROSION CONTROL PLAN - AREA 3
C740 EROSION CONTROL DETAILS
DOCUMENT 00 01 15 Page 2
DRAWING NO. TITLE
E000 ELECTRICAL LEGEND AND ABBREVIATIONS
E001 ELECTRICAL NOTES
E101 ELECTRICAL DEMOLITION PLAN - AREA 1
E102 ELECTRICAL DEMOLITION PLAN - AREA 2
E103 ELECTRICAL DEMOLITION PLAN - AREA 3
E104 ELECTRICAL DEMOLITION PLAN - AREA 4
E201 ELECTRICAL LAYOUT PLAN - AREA 1
E202 ELECTRICAL LAYOUT PLAN - AREA 2
E203 ELECTRICAL LAYOUT PLAN - AREA 3
E204 ELECTRICAL LAYOUT PLAN - AREA 4
E301 ELECTRICAL CIRCUITING PLAN - AREA 1
E302 ELECTRICAL CIRCUITING PLAN - AREA 2
E303 ELECTRICAL CIRCUITING PLAN - AREA 3
E304 ELECTRICAL CIRCUITING PLAN - AREA 4
E401 FIXTURE DETAILS IN ASPHALT
E402 FIXTURE DETAILS IN CONCRETE
E403 GENERAL ELECTRICAL DETAILS
E404 GENERAL ELECTRICAL DETAILS
E405 ELECTRICAL DUCT SECTION DETAILS
E406 GENERAL ELECTRICAL DETAILS
E407 HANDHOLE DETAILS
E408 VISUAL LANDING ZONE MARKER PANEL DETAILS
E409 SIGN DETAILS
E410 SIGN DETAILS
E411 VAULT DETAILS
DOCUMENT 00 01 15 Page 3
DRAWING NO. TITLE
E501 OVERALL RUNWAY 5-23 LIGHTING CONFIGURATION
E502 RUNWAY 5-23 AMP-1 LIGHTING CONFIGURATION
E503 RUNWAY 5-23 AMP-3 OVERT LIGHTING CONFIGURATION
E504 RUNWAY 5-23 AMP-3 COVERT LIGHTING CONFIGURATION
1.3 SUPPLEMENTARY DRAWINGS
These supplementary drawings may not be a part of the contract but are included with the drawings for information.
1.3.1 Boring Logs
The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.
-- End of Document --
DOCUMENT 00 01 15 Page 4
SECTION 01 11 00
SUMMARY OF WORK
08/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, "Government Furnished Property," of this section.
Submit the following items to the Contracting Officer:
Utility Outage Requests Utility Connection Requests
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes the complete reconstruction of the approximately 3,500 foot long Landing Zone located at North Auxiliary Air Field. The reconstructed landing zone will be comprised of a new 90 foot wide Portland cement concrete section and asphalt shoulder pavement. New airfield lighting and signage, pavement markings, sodding and grassing and incidental related work will also be included in the project..
1.2.2 Location
The work shall be located at the North Auxiliary Airfield in North, South Carolina, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 CONTRACT DRAWINGS
Upon award of this project, the Contracting Officer will provide a link to a website where the Contractor can obtain electronic copies of the contract drawings and specifications.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or
SECTION 01 11 00 Page 1 adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.5 ON-SITE PERMITS
1.5.1 Utility Outage Requests and Utility Connection Requests
Notify the Contracting Officer at least 72 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked.
The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. But indicated in locations to be transversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Work shall be scheduled to hold outages to a minimum.
Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled outside the regular working hours or on weekends.
Contracting Officer may permit utility outages at his discretion.
Requests for utility outages and connections shall be made in writing to the Contracting Officer at least 15 calendar days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.5.2 Burning
Burning of trash or rubbish is not permitted.
1.6 LOCATION OF UNDERGROUND UTILITIES
Contractor is responsible for obtaining dig permits (AF 103) prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 11 00 Page 2
-- End of Section --
SECTION 01 11 00 Page 3
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The airfield will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
b. Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed by the Contracting Officer. All Contractor and subcontractor personnel shall fill out SFS Form 74 and submit it to the Contracting Officer 72 hours prior to badge issuance or base access. Ensure the form is completely/honestly filled out with original signatures affixed to form. A copy of a valid form of
SECTION 01 14 00 Page 1 identification is required as well. Individuals who are not legal residents, will be required to also complete Ins. Form I-9 and provide a copy of resident alien card. These forms will be used by the Contracting Officer to conduct background checks prior to badge issuance/base access.
Those who are denied access to the installation due to negative background information, will be removed from the installation by the Project Supervisor/Contracting Officer and will not be allowed further entry until issue(s) are cleared and/or removed. For further clarification on process requirements, contact the Contracting Officer and Security Forces at (843) 963-6158.
1.3.1.3 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.3.1.4 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Use of Radioactive Equipment
Contractor shall obtain approval, at least 30 calendar days prior to the planned date for commencement of activities, from the Joint Base Charleston
- Air Base Radiation Safety Officer (RSO), 628 AMDS/SGPB (963-6289), in order to bring any equipment with a radioactive source (such as a nuclear density gauge) or any other radioactive material onto Joint Base Charleston
- Air Base (reference AFI 40-201, Paragraph 3.4.5.2, dated 13 April 2007 for specific requirements).
Contractor shall provide the following, a miminum of thirty (30) days prior to bringing equipment onto the Base:
1. Contract Number;
2. Swipe Sampling Data;
3. Copy of permit to own and operate equipment;
4. Certificate of training for the operator;
5. Valid South Carolina State Drivers License;
6. Written approval from the Base Radiation Safety Officer; and
7. Current NRC Form 241, NRC Reciprocity Form.
1.3.3 Working Hours
Regular working hours must consist of a period between 0600 and 1900, Monday through Saturday, excluding Government holidays. Contractor shall check in and out with the Fire Department at the beginning and end of each work shift.
1.3.4 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract
SECTION 01 14 00 Page 2 number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 3
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/11
PART 1 GENERAL
1.1 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,
e. Others as required by State of South Carolina law.
1.2 SUPERVISION
Provide at least one (1) qualified Project Manager and one (1) on-site Project Superintendent. Both shall be fluent in English. The Project Manager must have a minimum 10 years experience as a Project Manager or Superintendent on projects like this contract or similar in size and complexity. The Project Superintendent must have a minimum of 10 years experience as a Superintendent on projects similar in size and complexity.
The Project Manager in this context shall mean the individual with the responsibility for the overall management of the project and the Project Superintendent shall mean the individual with the responsibility for quality and production. Both the Project Manager and Project Superintendent are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.
Approval of Project Manager and on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed Project Manager and on-site Project Superintendent describing their experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed Project Manager and on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.3 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the
SECTION 01 30 00 Page 1 site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.
1.4 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Contractor and Subcontractors will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.4.1 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer.
The Partners will determine the frequency of the follow-on sessions.
1.5 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.
The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use
SECTION 01 30 00 Page 2 of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not be allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 3
SECTION 01 32 17.00 20
NETWORK ANALYSIS SCHEDULES (NAS)
08/10
PART 1 GENERAL
1.1 DESCRIPTION
The Contractor is responsible for scheduling procurement, Contractor quality control and construction, acceptance testing and training. Refer to Specification Section 01 33 00 SUBMITTAL PROCEDURES to determine if any items require Government approval prior to construction; If any are required, that submittal review time shall be included in the schedule.
The schedule is a tool to manage the project, both for Contractor and Government activities. It will also be used to report progress and evaluate time extensions. If cost-loaded, it will provide the basis for progress payments.
The Contractor shall use the Critical Path Method (CPM) and the Precedence Diagram Method (PDM) to satisfy time and cost applications. For consistency, when scheduling software terminology is used in this specification, the terms in Primavera's scheduling programs are used.
1.2 SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES, except as modified in this contract.
SD-01 Preconstruction Submittals
Qualifications; G
Baseline Network Analysis Schedule (NAS); G
SD-07 Certificates
Monthly Network Analysis Schedule Update; G
SD-11 Closeout Submittals
As-Built Schedule; G
1.3 SCHEDULE ACCEPTANCE PRIOR TO START OF WORK
The Contracting Officer and Contractor shall participate in a preliminary meeting(s) to discuss the proposed schedule and requirements of this section prior to the Contractor preparing the Project Baseline Schedule.
Government review comments on the Contractor's schedule(s) shall not relieve the Contractor from compliance with requirements of the Contract Documents.
Only bonds shall be paid prior to acceptance of the Baseline Network Analysis Schedule (NAS).
SECTION 01 32 17.00 20 Page 1
The acceptance of a Baseline NAS is a condition precedent to:
1. The Contractor starting work on the demolition or construction stage(s) of the contract.
2. Processing Contractor's pay request(s) for construction activities/items of work.
3. Review of any schedule updates.
Submittal of the Baseline Network Analysis Schedule, and subsequent schedule updates, shall be understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work shall be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.4 SOFTWARE
Project schedules must be prepared and maintained using Primavera P3, Primavera SureTrak, or Primavera P6. Save files in Concentric P3 or P6 file format, compatible with the Governments version of the scheduling program. Importing data into P3/SureTrak/P6 using data conversion techniques or third party software will be cause for rejection of the submitted schedule.
1.5 QUALIFICATIONS
The designated Scheduler for the project shall have prepared and maintained at least 3 previous schedules of similar size and complexity of this contract using Primavera P3, Primavera SureTrak, or Primavera P6. A resume outlining the qualifications of the Scheduler shall be submitted for acceptance to the Contracting Officer. Payment will not be processed until an acceptable Scheduler is provided.
1.6 NETWORK SYSTEM FORMAT
The system shall include time scaled logic diagrams and specified reports.
1.6.1 Diagrams
Provide Time-scaled Logic Diagram printed in color on ANSI D size sheets.
The diagram shall clearly show activities on the critical path. Include the following information for each activity:
a. Activity ID
b. Activity Description
c. Original Duration in Work Days
d. Remaining duration
e. Percent Complete
f. Early Start Date
g. Early Finish Date
SECTION 01 32 17.00 20 Page 2
h. Total Float
1.6.2 Schedule Activity Properties and Level of Detail
The NAS shall identify all Government, Construction Quality Management (CQM), Construction activities planned for the project and all other activities that could impact project completion if delayed. Separate activities shall be created for each Phase, Area and Location the activity is occurring. Activity categories included in the schedule are specified below.
With the exception of the Contract Award and Contract Completion Date (CCD) milestone activities, no activity shall be open-ended; each activity shall have predecessor and successor ties. Once an activity exists on the schedule it may not be deleted or renamed to change the scope of the activity and shall not be removed from the schedule logic without approval from the Contracting Officer. The ID number for a deleted activity shall not be re-used for another activity. No more than 20 percent of the activities shall be critical or near critical. Critical is defined as having zero days of Total Float. "Near Critical" is defined as having Total Float of 1 to 14 days. Contractor activities shall be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.
1.6.2.1 Activity Categories
a. Procurement Activities: Examples of procurement activities include, but are not limited to; Material/equipment submittal preparation, submittal and approval of material/equipment; material/equipment fabrication and delivery, and material/equipment on-site. As a minimum, separate procurement activities will be provided for critical items, long lead items, items requiring government approval and material/equipment procurement for which payment will be requested in advance of installation. The Contractor shall show each delivery with relationship tie to the Construction Activity specifically for the delivery.
b. Government Activities: Government and other agency activities that could impact progress shall be clearly identified. Government activities include, but are not limited to; Government approved submittal reviews, Government conducted inspections/tests, environmental permit approvals by State regulators, utility outages, Design Start, Construction Start, (including Design/Construction Start for each Fast-Track Phase, and delivery of Government Furnished Material/Equipment.
c. Quality Management (QM) Activities: CQM Activities shall identify the Preparatory Phase and Initial Phase for each Definable Feature of Work identified in the Contractor's Quality Control Plan. These activities shall be added to each Three-Week Look Ahead Schedule referenced in the paragraph entitled "THREE-WEEK LOOK AHEAD SCHEDULE" and will also be included in each monthly update. The Follow-up Phase will be represented by the Construction Activities in the Baseline Schedule and in the schedule updates.
d. Construction Activities: No on-site construction activity shall have a duration in excess of 20 working days. Separate construction activities shall be created for each Phase, Area, and Location the activity is occurring. Contractor activities will be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days, SECTION 01 32 17.00 20 Page 3 unless otherwise defined in this contract.
1.6.2.2 Contract Milestones and Constraints
a. Project Start Date Milestones: The Contractor shall include as the first activity on the schedule a start milestone titled "Contract Award", which shall have a Mandatory Start constraint equal to the Contract Award Date.
b. Projected Completion Milestone: The Contractor shall include an unconstrained finish milestone on the schedule titled "Projected Completion". Projected Completion is defined as the point in time the Government would consider the project complete and ready for its intended use. This milestone shall have the Contract Completion (CCD) milestone as its only successor.
c. Contract Completion Date (CCD) Milestone: The Contractor shall include as the last activity on the schedule a finish milestone titled "Contract Completion (CCD)", which shall have a Mandatory Finish constraint equal to the current Contract Completion Date. Calculation of schedule updates shall be such that if the finish of the "Projected Completion" milestone falls after the contract completion date, then negative float will be calculated on the longest path and if the finish of the "Projected Completion" milestone falls before the contract completion date, the float calculation shall reflect positive float on the longest path. The only predecessor to the Contract Completion Date Milestone shall be the Projected Completion milestone.
1.6.2.3 Activity Code
At a minimum, the Contractor shall establish activity codes identified in this specification and 3 additional activity codes identified by the Contracting Officer. Once established, activity codes and values cannot be changed without approval by the Contracting Officer.
a. Phase: All activities shall be assigned a 4-digit code value based on the contract phase it occurs in.
b. Area Code: All activities shall be assigned an area code value identifying the Area in which the activity occurs. Activities shall not belong to more than one area. Area is defined as a distinct space, function or activity category; such as, separate structure(s), sitework, project summary, construction quality management, material/equipment procurement, etc.
c. Work Item: All activities in the project schedule shall be assigned a 4-digit Work Item code value. Examples of Work Item code values include but are not limited to water lines, drain lines, building pad and foundation, slab on grade, walls and columns, suspended slab, roof structure, roofing, exterior finish systems, interior rough-in, and finishes, etc.
d. Location 1: Assign a 4-digit Location 1 code value to activities associated with multistory structures. Code values are used to identify the floor level where an activity is occurring.
e. Location 2: Assign a 4-digit Location 2 code value to all activities to identify the location within an Area, Work Item or Building Level that an activity is occurring.
SECTION 01 32 17.00 20 Page 4
f. Responsibility Code: All activities in the project schedule shall be identified with the party responsible for completing the task.
Activities shall not belong to more than one responsible party.
1.6.2.4 Anticipated Weather Delays
The Contractor shall use the following schedule of anticipated monthly non-work days due to adverse weather as the basis for establishing a "Weather Calendar" showing the number of anticipated non-workdays for each month due to adverse weather, Saturdays, Sundays and all Federal Holidays as non-work days.
Adverse weather is defined as the occurrence of one or more of the conditions below which prevents exterior construction activity or access to the site within twenty-four (24) hours including a weekend day or holiday provided that the Contractor has scheduled construction activities that day. Scheduled construction activities are defined as those activities that are detailed and planned in the Contractor's weekly construction progress meetings. No consideration for an adverse weather day will be granted for which no construction activities are scheduled.
a. precipitation (rain, snow, or ice) in excess of one-tenth inch (0.10") liquid measure;
MONTHLY ANTICIPATED ADVERSE WEATHER DELAYS
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
7 6 6 5 5 7 8 7 5 5 4 6
Assign the Weather Calendar to any activity that could be impacted by adverse weather. The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time extension for the difference of days between the anticipated and actual adverse weather delay if the number of actual adverse weather delay days exceeds the number of days anticipated for the month in which the delay occurs and the adverse weather delayed activities critical to contract completion. A lost workday due to weather conditions is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity.
1.6.3 Schedule Software Settings and Restrictions
a. Activity Constraints: Date/time constraint(s), other than those required by the contract, will not be allowed unless accepted by the Contracting Officer. Identify any constraints proposed and provide an explanation for the purpose of the constraint in the Narrative Report.
b. Default Progress Data Disallowed: Actual Start and Actual Finish dates on the CPM schedule shall match the dates on the Contractor Quality Control and Production Reports.
c. Software Settings: Schedule calculations and Out-of-Sequence progress (if applicable) shall be handled through Retained Logic, not Progress Override. All activity durations and float values will be shown in days. Activity progress will be shown using Remaining Duration. Default activity type will be set to "Task". The project "Must Finish By" date
SECTION 01 32 17.00 20 Page 5 shall be left blank.
1.6.4 Required Tabular Reports
The following reports shall be included with the schedule submittal:
a. Log Report: Listing of all changes made between the previous schedule and current updated schedule.
b. Narrative Report: Identify and justify; 1) Progress made in each area of the project; 2) Critical Path; 3) Date/time constraint(s), other than those required by the contract 3) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, critical path, and cost loading; 4) Any decrease in previously reported activity Earned Amount; 5) Pending items and status thereof, including permits, changes orders, and time extensions; 6) Status of Contract Completion Date and interim milestones; 7) Current and anticipated delays (describe cause of delay and corrective actions(s)); and 8) Description of current and future schedule problem areas. Each entry in the narrative report will cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.
c. Earned Value Report: Listing all activities having a budget amount cost loaded. Compilation of total earnings on the project from notice to proceed to current progress payment request. Group and sort activities as directed by the Contracting Officer. Show current budget, previous physical percent complete, to-date physical percent complete, previous earned value, to-date earned value and cost to complete on the report for each activity:
d. Schedule Variance Control (SVC) Diagram: With each schedule submission, provide a SVC diagram showing 1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates and 2) Earned Value to-date. Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer.
1.7 SUBMISSION AND ACCEPTANCE
1.7.1 Monthly Network Analysis Updates
Contractor and Government representatives shall meet at monthly intervals to review and agree on the information presented in the updated project schedule. The submission of an acceptable, updated schedule to the Government is a condition precedent to the processing of the Contractor's pay request. If a Schedule of Prices is the basis for progress payments, it shall be consistent with the logic and activity breakdowns on the progress schedule. If progress payments are based on a cost-loaded schedule, the Contractor and Government shall agree on percentage of payment for each activity progressed during the update period.
Provide the following with each Schedule submittal:
a. Time Scaled Logic Diagram.
b. Reports listed in paragraph entitled "Required Tabular Reports."
c. Data disks containing the project schedule. Include the back-up native .prx/current
SECTION 01 32 17.00 20 Page 6 mandated schedule program files.
1.7.2 As-Built Schedule
As a condition precedent to the release of retention and making final payment, submit an "As-Built Schedule," as the last schedule update showing all activities at 100 percent completion. This schedule shall reflect the exact manner in which the project was actually constructed.
1.8 CONTRACT MODIFICATION
Submit a Time Impact Analysis with each cost and time proposal for a proposed change. Time Impact Analysis (TIA) shall illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.
a. Each TIA shall be in both narrative and schedule form demonstrating the delay impact. The TIA shall identify the predecessors to the new activities and demonstrate the impacts to successor activities. The Contractor shall run the schedule calculations and submit the impacted schedule with the proposal or claim.
b. The TIA schedule submitted with the proposal shall show all activity progress as of the date of the proposal. If the impact to the schedule occurs prior to the proposal submission, the TIA schedule shall be updated to show all activity progress as of the time of the impact. If the proposed change does not impact the CCD, no TIA shall be required.
c. Submit Data disks containing the TIA schedule. Include the back-up native .prx/current mandated schedule program files.
d. Unless the Contracting Officer requests otherwise, only conformed contract modifications shall be added into the Project NAS.
1.9 PROJECT FLOAT
Project Float is the length of time between the Contractor's Projected Finish Milestone and the Contract Completion Date Milestone. Project Float available in the schedule, at any time shall not be for the exclusive use of either the Government or the Contractor.
1.10 THREE-WEEK LOOK AHEAD SCHEDULE
The Contractor shall prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Project Network Analysis Schedule. The work plans shall be keyed to NAS activity numbers and updated each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Project NAS on an electronic spreadsheet program and printed on 8 ½ by 11 sheets as directed by the Contracting Officer. Activities shall not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Three hard copies and one electronic file of the 3-Week Look Ahead Schedule shall be delivered to the Contracting Officer no later than 8 a.m. each Monday
SECTION 01 32 17.00 20 Page 7 and reviewed during the weekly CQC Coordination Meeting.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 32 17.00 20 Page 8
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Certificates of insurance
Surety bonds
List of proposed Subcontractors
List of proposed products
Construction progress schedule
Network Analysis Schedule (NAS)
Submittal register
SECTION 01 33 00 Page 1
Schedule of prices
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
Design submittals, design substantiation submittals and extensions of design submittals.
SD-06 Test Reports
SECTION 01 33 00 Page 2
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
SECTION 01 33 00 Page 3
Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor QC approval.
Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.4 PROJECT MANAGEMENT PROGRAM
At the Government's option, the Government may provide an internet based project management program for management of submittals, requests for information, correspondence, quality control testing results and other construction management processes. The Government will bear the cost for procurement of the internet based project management program. If provided by the Government, the contractor shall utilize and manage the Government provided program at no additional cost to the Government.
1.5 PREPARATION
1.5.1 Transmittal Form
Transmit each submittal, except sample installations and sample panels to office of approving authority. Transmit submittals with transmittal form prescribed by Contracting Officer and standard for project. On the transmittal form identify Contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled, "Identifying Submittals," of this section. Process transmittal forms to record actions regarding samples.
1.5.2 Identifying Submittals
When submittals are provided by a Subcontractor, the Prime Contractor is to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
SECTION 01 33 00 Page 4
a. Project title and location.
b. Construction contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone…
This is the start of the file's text. The full file is on GovTribe.