B570 Specifications - Repl Fire Supp Sys.pdf

PDF 1 MB Posted

Attached to
Repair Aircraft Maintenance Fire Suppression System - Building 570 at Charleston AFB, SC
Solicitation number
FA4418-10-R-0007
Issued by

About this file

SPECIFICATIONS - Solicitation for FA4418-10-R-0007

View the file

Other files

File Type Posted
QUESTIONS ANSWERS.docx DOCX document
Pictures B570 Diesel Fuel.pdf PDF
B570 Fire Supp AsBuilt Extract FP2.pdf PDF
Interior Pictures B570.pdf PDF
QUESTIONS GENERATED.docx DOCX document
B570 Fire Supp AsBuilt Extract FP1.pdf PDF
Attendance List.pdf PDF
Addendum 1.pdf PDF
Amendment 2 .doc DOC document
Amendment 1.doc DOC document
SCALED Drawings.pdf PDF
AF Form 66.pdf PDF
100 PERCENT DWG.pdf PDF
B570 LBP-ACM COMPILED.pdf PDF
Green Procurement.pdf PDF
Wage Determination.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

RPR ACFT MNT FIRE SUPPRESSION SYS – B570

PROJECT NO. DKFX: 10-1008

June 23, 2009

O’BRIEN & GERE ENGINEERS, INC.

THIS SHEET LEFT INTENTIONALLY BLANK

TOC-1

13181/42280

9 March 2009 DKFX 10-1008 Table of Contents

RPR ACFT MNT Fire Suppression Sys – B570

PROJECT TABLE OF CONTENTS

DIVISION 1 – GENERAL REQUIREMENTS

01000 Statement of Work ......................................................................... 01000-01 Thru 01000-05

01011 Construction Site & Supplemental Storage Site ............................ 01011-01 Thru 01011-04

01320 Construction Project Critical Path Schedule .................................. 01320-01 Thru 01320-03

01330 Submittal Procedures ..................................................................... 01330-01 Thru 01330-04

01450N Construction Quality Control ........................................................ 01450N-01 Thru 01450N-13

01452 Special Inspection For Seismic-Resisting Systems ....................... 01452-01 Thru 01452-04

01501 Environmental ............................................................................... 01501-01 Thru 01501-17

01540 Green Procurement ........................................................................ 01540-01 Thru 01540-07

01572 Waste Management ....................................................................... 01572-01 Thru 01572-06

01575 Temporary Environmental Controls .............................................. 01575-01 Thru 01575-15

01781 Project Record Documents ............................................................ 01781-01 Thru 01781-07

DIVISIONS 2, 3, & 4 – NOT USED

DIVISION 5 – METALS

05090A Welding, Structural ........................................................................ 05090A-01 Thru 05090A-08

05120 Structural Steel .............................................................................. 05120-01 Thru 05120-07

05500 Metals: Miscellaneous and Fabrications ........................................ 05500-01 Thru 05500-06

DIVISION 6 – NOT USED

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

07413 Metal Wall Panels .......................................................................... 07413-01 Thru 07413-08

07920 Joint Sealants ................................................................................. 07920-01 Thru 07920-07

DIVISION 8 – DOORS AND WINDOWS – NOT USED

DIVISION 9 – FINISHES

09900 Paints and Coatings ....................................................................... 09900-01 Thru 09900-20

DIVISIONS 10, 11, AND 12 – NOT USED

DIVISION 13 – SPECIAL CONSTRUCTION

13080 Seismic Protection For Miscellaneous Equipment ........................ 13080-01 Thru 13080-06

13282N Lead In Construction ..................................................................... 13282N-01 Thru 13282N-14

13851A Fire Detection and Alarm System, Addressable ............................ 13851A-01 Thru 13851A-18

13930N Wet-Pipe Fire Suppression Sprinklers ........................................... 13930N-01 Thru 13930N-09

13956N Foam Fire Extinguishing For Aircraft Hangars ............................. 13956N-01 Thru 13956N-20

DIVISION 14 – NOT USED

TOC-2

9 March 2009 DKFX 10-1008 Table of Contents

RPR ACFT MNT Fire Suppression Sys – B570

DIVISON 15 – MECHANICAL

15070A Seismic Protection for Mechanical Equipment ............................. 15070A-01 Thru 15070A-04

15080 Thermal Insulation For Mechanical Systems ................................ 15080-01 Thru 15080-18

15182 Refrigerant Piping .......................................................................... 15182-01 Thru 15182-15

15700A Unitary Heating and Cooling Equipment ...................................... 15700A-01 Thru 15700A-11

15895 Air Supply, Distribution, Ventilation, and Exhaust System .......... 15895-01 Thru 15895-09

15990A Testing, Adjusting, and Balancing of HVAC Systems .................. 15990A-01 Thru 15990A-07

DIVISION 16 – ELECTRICAL

16050N Basic Electrical Materials and Methods ........................................ 16050N-01 Thru 16050N-05

16050S Common Work Results For Electrical ........................................... 16050S-01 Thru 16050S-12

16070A Seismic Protection For Electrical Equipment ................................ 16070A-01 Thru 16070A-04

01000-1

9 March 2009 DKFX 10-1008 Statement of Work

Rpr Acft Mnt Fire Suppression Sys - B570

SECTION 01000 CAFB

STATEMENT OF WORK

04/06

PART 1 GENERAL

1.1 SCOPE

1.1.1 The work to be performed by this contract consists of furnishing all plant, labor, materials, equipment supplies and supervision necessary to complete project DKFX: 10-1008 Rpr Acft Mnt Fire

Suppression Sys – B570 at the Charleston Air Force Base, South Carolina.

1.1.2 Scope of Work includes, but is not limited to the following major items of work which are listed for the Contractor’s convenience in order that he may determine the general scope of the work involved.

1.1.2.1 Replace existing B570 ceiling deluge fire protection system with a new wet pipe sprinkler system.

1.1.2.2 Provide high expansion foam systems within B570 and associated existing Foam Building.

1.1.2.3 Modify existing B570 fire alarm system.

1.1.2.4 Provide HVAC system in existing Foam Building.

1.1.2.5 Provide metal liner panel and rigid insulation on interior wall of existing Foam Building.

1.1.2.6 Provide integral test, drain, and pressure relief valves at each sprinkler riser to prevent excessive pressure in the riser. Pressure relief valve assemblies shall be AGF Manufacturing

Inc. Model 1011A “Test and Drain” or an approved equal.

1.1.3 It will be the responsibility of the Contractor to visit the project site prior to starting work to determine the actual amount of work, dimensions, and field conditions, which affect the work. Any variations between site conditions and project drawings shall be brought to the attention of the

Contracting Officer.

1.1.4 All work shall be in strict conformance with these specifications and attached drawings.

1.2 LOCATION

1.2.1 Charleston Air Force Base is located in North Charleston South Carolina (near Charleston, South

Carolina) and is accessible by Interstate 26 or by SC Highway 642 (also known as Dorchester Road).

1.3 HOURS OF WORK

01000-2

1.3.1 Working hours for the Contractor will normally be between the hours of 7:30 a.m. and 4:30 p.m., Monday through Friday, excluding federal holidays.

1.3.2 If the Contractor desires to work during periods other than above, additional government inspection forces may be required.

1.3.2.1 The Contractor must notify the Contracting Officer three working days in advance of his intention to work during the other periods to allow assignment of additional inspection forces when the Contracting Officer determines that they are reasonably available.

1.3.2.2 If such force is available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days; however, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of inspection at overtime rates will be charged to the Contractor and will be deducted from the final payment of the contract amount.

1.4 SCHEDULE OF OPERATIONS

1.4.1 The schedule of operations to be performed under this contact will be as directed by the

Contracting Officer to insure a minimum of inconvenience and interruption of normal daily operations in the area.

1.4.2 Contractor Access

1.4.2.1 The contractor will have access to the entire building.

1.4.2.2 The Free Zone (area which the contractor will be allowed to access) will be located in an area surrounding Building 570. The exact area will be designated on a map to be furnished by the

Government. Contractor's access will be limited to this area.

1.4.2.3 Proper coordination will be worked through Base Operations. Contractor will be utilizing designated gates to enter/exit the airfield and Free Zone. Contractor will comply with AFI31-101, AMC SUP 1. Contractor work may be delayed or terminated for short periods due to real-world security responses and military training exercises.

1.4.2.4 Contractor shall notify the Security Forces Control Center and Base Operations upon entering and exiting the affected area each day. Contractor will not have access to the Free Zone on government holidays.

1.4.3 Notify the Contracting Officer a minimum of 72 hours prior to interruption of any utility services.

1.5 TESTING

1.5.1 All required testing will be performed by an independent testing laboratory. This independent laboratory shall be hired by the contractor at no additional cost to the government.

01000-3

1.6 APPLICABLE DRAWINGS

1.6.1 The following shall form a part of these specifications:

DWG SHT SHEET TITLE

NO.

1 G001 Cover Sheet

2 G002 Location Plans & General Notes

3 A001 Overall Plan

4 A002 Enlarged Plan And Sections

5 M001 Mechanical Plan, Schedules, And Details

6 M002 Mechanical Details

7 FD01 Existing Sprinkler Demolition Plan

8 FD02 Existing AFFF Demolition Plan

9 FD03 Demolition Photos

10 FP01 Fire Protection Plan

11 FP02 Foam Equipment Room

12 FP03 Foam Equipment Room Details

13 FP04 Sections And Details

14 FA01 Fire Alarm Plan

15 FA02 Fire Alarm System One Line

16 AL01 Asbestos & Lead Testing

1.7 PROTECTION OF EXISTING EQUIPMENT, STRUCTURES, AND GROUNDS:

1.7.1 Any digging or excavating on Government property shall be accomplished with the authority of a

Work Clearance Request. The contractor must follow the provisions of the Work Clearance Request before any digging or excavating may be authorized. Requests for marking areas to dig must be made

72 hours prior to digging. If any communication cables, pipes, utility service wires or other

Government property is damaged by the contractor by unauthorized digging or excavating, the contractor shall be responsible for the repairs and any incidental and consequential damages, and the contractor shall provide, where applicable, an estimate and plan for making the repairs to the

Contracting Officer and Communication Squadron Focal Point at 566-35ll within four (4) hours. If the contractor fails to respond within this time frame, the Government may repair the damage and deduct all costs associated with the repair of the damage from the contract price. Repairs of

Government-owned communications cable shall be in accordance with AFTO 3lW3-l0-l3 standards.

A copy of these standards can be obtained from the Contracting Office. The contractor shall coordinate with the Contracting Officer on material and down-time prior to beginning any work. All work will undergo a final inspection by the Contracting Officer and a representative of the

Communications Squadron before acceptance. In accordance with Air Force Regulation ll2-l Chapter l3 (Claims in Favor of the Government), a copy of the invoice for repairs shall be submitted to the

Contracting Officer for administrative purposes.

1.7.2 The Contractor shall take such precautions as are necessary to prevent damage, discoloration, etc., to existing equipment, structures and grounds. All equipment, structures, and grounds damaged, discolored, etc., by the Contractor shall be repaired by the Contractor at no cost to the government.

The government will assume that all equipment that the Contractor works on is in an operating

01000-4 condition and in a good state of repair. It shall be the Contractors responsibility to notify the

Contracting Officer of any equipment that is not operating prior to commencing work.

1.8 QUALITY CONTROL

1.8.1 Each trade shall have at least one certified journeyman craftsman on site during all work involving that trade. Certification shall be from a recognized trade association or union (if applicable).

1.8.2 Proof of certification or enrollment may be requested by the Contracting Officer prior to starting work involving the respective trade.

1.9 AS-BUILT RECORDS

1.9.1 Maintain at the jobsite one set of full-size contract drawings marked to show any deviations which have been made from the contract drawings, including buried or concealed construction and utility features revealed, during the course of construction. Record the horizontal and vertical location of all buried utilities that differ from the contract drawings.

1.9.2 Make record drawings available for review by the Contracting Officer.

1.9.3 Submit the marked sets of prints to the Contracting Officer upon completion of the work.

1.9.4 A set of mechanical as-builts shall be submitted to the Contracting Officer prior to requesting an inspection of the mechanical systems.

1.10 PRECONSTRUCTION CONFERENCE

1.10.1 After award of the contract, but prior to commencement of any work at the site, meet with the

Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation and submission of the schedule of prices, shop drawings and other submittals, scheduling, programming and prosecution of work. Major subcontractors who will be engaged in the work shall also attend.

1.11 MATERIALS AND EQUIPMENT TO BE SALVAGED

1.11.1 Materials and equipment removed during construction and determined to be salvageable by the

Contracting Officer shall remain property of the Government and shall be turned over to the Contracting

Officer. Material shall be delivered by appointment to Base Supply, Building 611.

1.12 DEFINITIONS:

1.12.1 Wherever the term “Government” appears, the term shall be defined as “Contracting Officer.”

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

01000-5

-- End Of Section --

01011-1

9 March 2009 DKFX 10-1008 Construction Site/Supplemental Storage Site RPR ACFT MNT Fire Suppression Sys - B570 Management and Safety

SECTION 01011 CAFB

CONSTRUCTION SITE/SUPLEMENTAL STORAGE SITE

MANAGEMENT AND SAFETY

1.1 PRIMARY AND SUPPLEMENTAL SITES

The following standards relate to the appearance of the construction site during the construction cycle, to temporary administrative and storage areas, and to service facilities needed for execution and completion of the work. For most construction projects, the base civil engineer will provide the contractor with two sites; the construction site and a supplemental storage site. The supplemental storage site may not be in close proximity of the construction site but at a site designated by the Base Civil Engineer out of view from the general public.

1.2 SITE MAINTENANCE

1.2.1 A visually acceptable site at Charleston AFB is an important construction standard. A clean, well-kept site will help ensure compliance with the safety and environmental requirements of the contract.

Contractor’s trailers and storage buildings must follow the base paint standards. The contractor shall maintain the trailers or storage buildings in good condition or must remove them. The contractor is responsible for the security of his property and general housekeeping of the area(s). The construction site and supplemental storage site shall be kept in a clean and orderly state throughout the duration of the contract.

1.3 SUBMITTALS

1.3.1 Government approval is required for submittals with a "GA" designation; submittals having a

"FIO" designation are for information only. The following shall be submitted in accordance with Section 01330 SUBMITTAL PROCEDURES:

1.3.2.1 Construction Site Plan (GA)

1.3.2.2 Prior to starting the work, the contractor shall submit site plans to the Contracting Officer for approval showing the layout and details of all temporary facilities used for this contract. The base approval authority, normally the Base Civil Engineer, must approve the plan. The plan shall include the location of the construction fence, location of all site trailers, equipment and material storage areas, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas. Site photographs prior to the start of work may be included with the plan. At completion of work, the contractor shall remove the facilities and restore the site to its original condition.

1.3.3.1 Dirt and Dust Control Plan (GA)

1.3.3.2 The contractor shall submit a plan for controlling dirt, debris, and dust on base roadways, aircraft aprons, taxiways, and occupied areas. As a minimum, the plan shall identify the subcontractor and equipment for cleaning along the haul route and measures to reduce dirt, dust, and debris from roadways, aprons, taxiways, and occupied areas.

01011-2

1.4 CONTRACTOR’S TEMPORARY FACILITIES

1.4.1 Administrative Field Offices and Material Storage Trailers

1.4.1.1 Contractor’s administrative field office and storage trailers shall be in like-new condition. Locate the office and trailers behind the construction fence unless otherwise indicated on the drawings.

Storage of materials and debris under the trailers in prohibited.

1.4.2 Material Storage Sites

1.4.2.1 Supplemental Storage Site - This site is for storage of items not immediately required at the construction site. The location may not be indicated on the drawings. The contractor is responsible for the security of the stored property and general housekeeping.

1.4.2.2 Construction Site - Storage is limited to the materials that are needed within one week.

1.4.3 Construction Site/Supplemental Storage Site Enclosure

1.4.3.1 The Contractor shall install a 6 foot high chain link fence with fabric covering around the construction site and the supplemental storage site. The fencing should also be reflected in the contractor’s site plan required by 1.3 above.

1.4.3.2 Prior to installation, the Contracting Officer shall approve post, anchor and fencing plans.

1.4.3.3 Provide closed-mesh style polypropylene screen fabric with four ply hems and all accessories necessary to install on chain link fence, per the following requirements:

1.4.3.3.1 Fabric shall be closed-mesh polypropylene of 100% leno construction, stabilized polypropylene, heat set, with a 93% density, 5.8 oz. per yard, tensile strength of 300 x 110, black in color.

1.4.3.3.2 Hems shall be reinforced two-ply, double stitched with UV stabilized polypropylene thread with 2.75 inch black tape edge providing four-ply hem horizontal and vertical tape to have #2 brass grommets, 12” on center. UV stabilized polypropylene, heat set, with a 93% density, 5.8 oz. per yard.

1.4.3.3.3 Grommets shall be affixed to chain link fence with 11 gauge hog rings, or greater, and 50 pound test strength, black U.V. stabilized tie wraps to be used on top, center line, and side grommets of panels.

1.4.4 Dumpsters

1.4.4.1 Equip dumpsters with a secure cover. The cover shall be closed at all times, except when being loaded with trash and debris. Locate dumpsters behind the construction fence or out of the public view. Empty site dumpsters at least once a week, or as needed to keep the site free of debris and trash. If necessary, provide 208-liter (55-gallon) trash containers painted the darker base color to collect debris in the construction site area. Locate the trash containers behind the construction fence or out of the public view. Empty trash containers at least once a day. Large demolition normally requires a large dumpster without lids. These are acceptable but should not have debris higher than the sides before emptying.

01011-3

1.4.5 Temporary Sanitation Facilities

1.4.5.1 All temporary sewer and sanitation facilities shall be self-contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the contracting officer. The doors should be self-closing.

Locate the facility behind the construction fence or out of the public view.

1.5 GRASS CUTTING

1.5.1 Cut grass (or annual weeds) within the construction and storage sites to a 2-inch height at least once a week during the active growing season. Trim the grass around fences at time of grass cutting. Grass or weeds on stockpiled earth shall be maintained as described above.

1.6 CONSTRCTION SITE SAFETY

1.6.1 Contractor shall comply with all OSHA safety regulations during the performance of this contract.

1.6.2 Contractor shall provide barricades equipped with yellow flashing lights at all excavations in sufficient number to provide safety for vehicular and pedestrian traffic. Contractor shall maintain barricade lights in proper working order.

1.6.3 Contractor will be allowed to close only one travel lane of a base street or road at any time.

Contractor shall be responsible for maintaining two-way traffic within his work area and shall provide flagmen and barricades for traffic control.

1.6.4 Contractor shall obtain approval from the Base Radiation Safety Officer (RSO), 437 MG/SGPB, in order to bring any equipment (such as nuclear density gauge) with a radioactive source, or any other radioactive material onto Charleston Air Force Base. (Reference AFR 161-16, Paragraph 8m and base Regulation 161-3).

1.6.5 Contractor shall limit the number of vehicles at the facility to those required for completion of work. This shall be even more strictly enforced if the construction site is located near the flight line.

At no time shall any contractor personnel or vehicle cross the airfield “Red Line.” Doing so will result in action by the 437th Security Police Squadron. Use of deadly force is authorized in the defense of the Red Line area. The Red Line is clearly marked and labeled on the airfield pavement.

1.6.6 Contractor shall keep the jobsite in a clean and orderly manner (FOD free). It is the responsibility of the contractor to keep the grass cut, in and around the jobsite, to a level which is acceptable to the government.

1.6.7 For any project sited on the air field contractor shall fill out form and submit to for approval/permit. For a project located on Charleston AFB and if any equipment that the contractor uses exceeds in height the contractor shall fill out form and submit to for approval/permit. Notify the Base Community Planner when form is submitted and when permit is received.

01011-4

01320-1

9 March 2009 DKFX 10-1008 Construction Project Critical Path Schedule RPR ACFT MNT Fire Suppression Sys - B570

SECTION 01320 CAFB

CONSTRUCTION PROJECT CRITICAL PATH SCHEDULE

1.1 Description

The schedule shall consist of a network analysis schedule (diagram) and associated reports originating from a qualified scheduling consultant. Construction activities will be interrelated on a single schedule that represents the entire project duration from project award to completion. Updates will build upon each and shall be submitted at each biweekly QC/Scheduling meeting. The revised data will be used to measure work progress and shall aid in the evaluation of time extensions. The Critical Path Method (CPM) of network calculation shall be used to generate and update the schedule. Prime contractor management personnel, subcontractors, and suppliers shall actively participate in the generation and update of the schedule as required.

1.2 Definitions

1.2.1 Activity: A discrete part of the project that can be identified for planning, scheduling, monitoring, and controlling construction.

1.2.2 Construction activities include, but are not limited to, tasks related to; mobilization and demobilization, submittals, procurement of material, installation of temporary or permanent work, QC testing and inspections, start-up and testing of equipment, punch work completion, clean-up activities during construction, training to be provided, and administrative tasks necessary in the completion of the contract.

1.2.3 Critical activities are on the critical path and must start and finish on the planned dates to avoid delays.

1.2.4 Predecessor activities must be completed before another activity can start.

1.2.5 Procurement activities are tasks related to the procurement of material and equipment, including the submittal process. Separate procurement activities for each specification section shall be included on the schedule.

1.2.6 Quality Control activities are identifiable features of the contractor’s QC Program/Plan.

1.2.7 Government activities are activities controlled by the government that could impact the schedule.

These activities may include; submittal review, government conducted inspections, government permit approvals, utility markings, and delivery of government furnished equipment.

1.2.8 Activities shall be identified by the contractor and must be included on the critical path schedule.

1.2.8.1 Event: The starting or ending point of an activity.

1.2.8.2 Float: The measure of leeway in starting and completing an activity. Float is neither owned by the contractor nor the government.

01320-2

1.2.8.3 Fragment: A partial network that breaks down activities for greater detail.

1.2.8.4 Major Area: A significant construction element.

1.2.8.5 Milestone: A key or critical event or point in time for reference or measurement.

1.2.8.6 Network Diagram: A graphic diagram of the critical path schedule showing the relationship of activities.

1.2.8.7 Scheduler: The qualified sub-contractor responsible for preparing and updating the critical path schedule.

1.2.8.8 Duration: The length of time for one activity.

1.3 Submittals

1.3.1 Submit a preliminary “Critical Path Construction Schedule” defining the planned operations for the first 60 calendar days within 10 calendar days after Notice of Award. Level I detail is acceptable for this schedule.

1.3.2 An initial project schedule shall be submitted within 60 days of the Notice to Proceed. This schedule shall provide a reasonable sequence of activities throughout the entire project.

1.3.3 Submit bi-weekly updates of the critical path schedule at the QC meetings. These updates shall incorporate Level III detail for activities starting within 60 days (as a minimum). The level of detail is expected to increase significantly at each QC meeting until all activities are presented to Level III detail (within 180 days of Notice to Proceed). Prepare four copies for government personnel.

1.3.4 Submit resume showing qualifications of scheduler.

2.1 CRITICAL PATH SCHEDULE

2.1.1 The software system utilized shall be capable of developing the schedule based on the Critical Path

Method.

2.1.2 Diagram: Computer generated schedule showing the order and interdependence of activities, and the sequence in which the work is to be accomplished. Include restraints and work restrictions showing how the sequence of work is affected. Include milestones such as the completion of the SOQ’s, completion of pavements, completion of utilities and other milestones as mutually agreed upon during QC meetings.

2.1.3 Reports

2.1.3.1 Schedule Report: Shall include: activity numbers, activity description, activity duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float.

The report shall generally be in ‘logic’ form where preceding and succeeding activities are listed in ascending order. The format may be modified by the scheduler with the concurrence of both parties.

01320-3

2.1.3.2 Narrative: Describe progress made in each area of the project; note changes in activities, durations, logic, sequence of activities, and interdependencies; note milestone changes or accomplishment; note changes in the critical path; note current or anticipated delays; describe current and anticipated problem areas.

2.1.3.3 Modification Time Analysis: Evaluate proposed contract modifications to determine the time impact to the project. Contractor shall adjust work schedule so as to minimize delays to the project.

2.1.3.4 Constraints: The schedule shall show how each activity restricts or restrains other activities.

2.1.3.5 Level of Detail: Level III detail shall be used in defining activities.

2.1.3.6 Updates: The contractor shall establish procedures for monitoring and updating the CPM schedule and reports on a bi-weekly basis per the recommendations of the scheduler. Include logic revisions and any factors that have affected the schedule in the updated reports.

2.1.3.7 Anticipated Weather Delays: Formulate the schedule with allowances for normal adverse weather conditions as delineated in the contract documents. Include actual workdays lost in the updated schedules with detailed logic presented in the narrative report.

2.1.4 Scheduler

2.1.4.1 Qualifications: The scheduler shall have developed and maintained a computerized critical path schedule on at least two major construction projects. The scheduler shall have completed training in CPM from an accredited college/university or from an authorized trainer such as Primavera.

2.1.4.2 Responsibilities: Scheduler shall act as an independent and objective third party working for the benefit of the project. The scheduling consultant shall develop CPM schedules and reports as described and may modify activities or logic to ensure that the schedule reflects the actual construction restraints, constrictions, and interdependence of activities. Responsibilities include a detailed analysis of actual or anticipated lost or gained time at the biweekly scheduling.

2.1.4.3 Qualified Scheduling Consultant:

Scheduling Systems, Inc.

1031 Chuck Dawley Blvd., Suite 7B Mt. Pleasant, SC 29464

01330-1

9 March 2009 DKFX 10-1008 Submittal Procedures

SECTION 01330 CAFB

SUBMITTAL PROCEDURES

1.1 AF FORM 66

See AF Form 66 Schedule of Material Submittals for the required submittals for this project.

1.2 SUBMITTAL CLASSIFICATION

1.2.1 GOVERNMENT APPROVED (GA): Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.2.2 FOR INFORMATION ONLY (FIO): All submittals not requiring government approval will be for information only. They are not considered to be "shop drawings" within the terms of the contract clause referred to above.

1.3 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the CQC requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.4 DISAPPROVED SUBMITTALS

The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the Contracting Officer.

1.5 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

01330-2

Not Used

3.1 GENERAL

The Contractor shall make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) representative and each item shall be stamped, signed, and dated by the CQC representative indicating action taken.

Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

3.2 SCHEDULING

Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 15 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will-be allowed for time lost in late submittals.

3.3 TRANSMITTAL FORM (AF Form 3000)

Transmit form "AF Form 3000" shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse-side of the form.

These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.

3.4 SUBMITTAL PROCEDURE

3.4.1 Ten days after notice to proceed or as established by the Contracting Officer, and before starting installation of any materials or equipment, the Contractor shall submit to the Contracting Officer for approval, the appropriate number of complete sets of all material and equipment submittals as listed herein.

01330-3

3.4.2 The submittals shall include manufacturer’s styles or catalog numbers, cuts and other descriptive data including shop drawings to completely describe equipment proposed for use.

3.4.3 Submittals describing material and equipment for any building system (i.e., structural, mechanical, or electrical) shall be submitted at one time, complete. No considerations will be given by the Contracting Officer to partial or incomplete system submittals.

3.4.4 No equipment, materials, etc. will be installed until submittal approval has been obtained.

3.4.5 Submittals shall be made as follows:

3.4.5.1 Procedures: Identify project, contractor, subcontractor, major supplier, pertinent drawing sheet and detail number, as appropriate. Identify any deviations from Contract documents.

3.4.5.2 Deviations: For submittals, which include proposed deviations requested by the contractor, the contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

3.4.5.3 Substitutions: Submit a request for substitution to the Contracting Officer for any product or manufacturer not named, to be considered as equal. Document each request with complete data substantiating compliance of proposed substitution with contract documents. Substitutions will not be considered when they are indicated or implied on shop drawings or product data submittals, without separate written request or when acceptance will require revision to the contract documents.

A request constitutes a representation that the Contractor:

3.4.5.3.1 Has investigated the proposed product and has determined that it meets or exceeds the quality level of the specified product.

3.4.5.3.2 Will provide the same warranty as the specified product.

3.4.5.3.3 Will coordinate installation and make changes to other work which may be required for the work to be complete with no additional cost to the Government.

3.4.5.3.4 Waives claims for additional costs or time extension which may subsequently become apparent.

3.5 CONTROL OF SUBMITTALS

The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the approved contractor submittal date.

3.6 GOVERNMENT APPROVED SUBMITTALS

Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. Two (2) copies of the submittal will be retained by the Contracting Officer. All remaining copies of the submittal will be returned to the Contractor.

01330-4

3.7 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

3.8 DAILY WORK SHEETS

Contractor shall provide “daily work sheets” and submit to the Contracting Officer by noon each day for the previous day’s activities. Work sheets shall include list of all personnel on the job by trade, work accomplished each day, equipment on site, and materials received that day.

01450N-1

9 March 2009 DKFX 10-1008 Construction Quality Control

SECTION 01450N

CONSTRUCTION QUALITY CONTROL

(45 00 00 20) 07/06

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2003) Safety -- Safety and Health Requirements

1.2 SUBMITTALS

Government approval is required for submittals with a "GA" designation; submittals having a "FIO" designation are for information only. The following shall be submitted in accordance with Section

01330 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Quality Control (QC) Plan - GA

Submit a Construction QC Plan prior to start of construction.

SD-02 Design Data

Basis of Design and Design Intent - GA

1.3 INFORMATION FOR THE CONTRACTING OFFICER

Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the Contracting Officer. The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality Control (CQC) Report, (CQC) Report (Continuation Sheet), Preparatory Phase Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and Log.

1.3.1 Deliver the following to the Contracting Officer during Construction:

1.3.1.1 CQC Report: Submit the report electronically by 10:00 AM the next working day after each day that work is performed and for every seven consecutive calendar days of no-work.

01450N-2

1.3.1.2 Contractor Production Report: Submit the report electronically by 10:00 AM the next working day after each day that work is performed and for every seven consecutive calendar days of no-work.

1.3.1.3 Preparatory Phase Checklist: Submit the report electronically in the same manner as the CQC

Report for each Preparatory Phase held.

1.3.1.4 Initial Phase Checklist: Submit the report electronically in the same manner as the CQC Report for each Initial Phase held.

1.3.1.5 Field Test Reports: Within two working days after the test is performed, submit the report as an electronic attachment to the CQC Report.

1.3.1.6 Monthly Summary Report of Reports and Tests: Submit the report as an electronic attachment to the CQC Report at the end of each month. Hand-carry all originals attached to the last QC Report of the month.

1.3.1.7 Testing Plan and Log: Submit the report as an electronic attachment to the CQC Report, at the end of each month. A copy of the final Testing Plan and Log shall be provided to the OMSI preparer for inclusion into the OMSI documentation. Hand-carry the originals attached to the last CQC Report of each month and one copy attached to each CQC Report copy. A copy of the final Testing Plan and Log shall be provided to the OMSI preparer for inclusion into the OMSI documentation.

1.3.1.8 Rework Items List: Submit lists containing new entries daily, in the same manner as the CQC

Report. Hand-carry the originals attached to the last CQC Report of each month and one copy attached to each CQC Report copy.

1.3.1.9 CQC Meeting Minutes: Within two working days after the meeting is held, submit the report as an electronic attachment to the CQC Report. Hand-carry the original within two working days after the meeting is held, attached to the original CQC Report and one copy attached to each CQC Report copy.

1.3.1.10 QC Certifications: As required by the paragraph entitled "QC Certifications."

1.4 QC PROGRAM REQUIREMENTS

Establish and maintain a QC program as described in this section. This QC program is a key element in meeting the objectives of NAVFAC Commissioning. The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, completion inspections, and QC certifications and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this Contract. The QC program shall cover on-site and off-site work and shall be keyed to the work sequence. No construction work or testing may be performed unless the QC Manager is on the work site. The QC Manager shall report to an officer of the firm and shall not be subordinate to the Project Superintendent or the Project Manager. The QC Manager, Project Superintendent and Project Manager must work together effectively. Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job.

01450N-3

1.4.1 ACCEPTANCE OF THE CONSTRUCTION QUALITY CONTROL (QC) PLAN

Acceptance of the QC Plan is required prior to the start of construction. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time in order to verify the submitted qualifications. All QC organization personnel shall be subject to acceptance by the Contracting Officer. The Contracting Officer may require the removal of any individual for non-compliance with quality requirements specified in the Contract.

1.4.2 PRELIMINARY CONSTRUCTION WORK AUTHORIZED PRIOR TO ACCEPTANCE

The only construction work that is authorized to proceed prior to the acceptance of the QC Plan is mobilization of storage and office trailers, temporary utilities, and surveying.

1.4.3 NOTIFICATION OF CHANGES

Notify the Contracting Officer, in writing, of any proposed changes in the QC Plan or changes to the QC organization personnel, a minimum of 10 work days prior to a proposed change. Proposed changes shall be subject to acceptance by the Contracting Officer.

1.5 QC ORGANIZATION

1.5.1 QC MANAGER

1.5.1.1 DUTIES

Provide a QC Manager at the work site to implement and manage the QC program. The only duties and responsibilities of the QC Manager are to manage and implement the QC program on this Contract. The QC Manager shall not be designated as the safety competent person as defined by EM 385-1-1. The QC Manager is required to attend the partnering meetings, QC Plan Meetings, Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the three phases of control except for those phases of control designated to be performed by QC Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this Contract. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by the QC Specialists, testing laboratory personnel and any other inspection and testing personnel required by this Contract. The QC Manager is the manager of all QC activities.

1.5.1.2 QUALIFICATIONS

An individual with a minimum of 10 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of this Contract.

The individual shall have at least two years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1, and have experience in the areas of hazard identification, safety compliance, and sustainability.

01450N-4

1.5.2 CONSTRUCTION QUALITY MANAGEMENT TRAINING

In addition to the above experience and education requirements, the QC Manager shall have completed the course entitled "Construction Quality Management (CQM) for Contractors." If the QC Manager does not have a current certification, they shall obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.

1.6 QUALITY CONTROL (QC) PLAN

1.6.1 CONSTRUCTION QUALITY CONTROL (QC) PLAN

1.6.1.1 Requirements

Provide, for acceptance by the Contracting Officer, a Construction QC Plan submitted in a three-ring binder that includes a table of contents, with major sections identified with tabs, with pages numbered sequentially, and that documents the proposed methods and responsibilities for accomplishing commissioning activities during the construction of the project:

1.6.1.1.1 QC ORGANIZATION: A chart showing the QC organizational structure.

1.6.1.1.2 NAMES AND QUALIFICATIONS: Names and qualifications, in resume format, for each person in the QC organization. Include the CQM for Contractors course certifications for the QC Manager as required by the paragraphs entitled "Construction Quality Management Training" and " Duties and Qualifications".

1.6.1.1.3 DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL: Duties, responsibilities, and authorities of each person in the QC organization.

1.6.1.1.4 OUTSIDE ORGANIZATIONS: A listing of outside organizations, such as architectural and consulting engineering firms, that will be employed by the Contractor and a description of the services these firms will provide.

1.6.1.1.5 APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC

Manager and stating that he are responsible for implementing and managing the QC program as described in this Contract. Include in this letter the responsibility of the QC Manager to implement and manage the three phases of control, and his authority to stop work which is not in compliance with the Contract. Copies of the letters shall be included in the QC Plan.

1.6.1.1.6 SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving, and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the Submittal Register as specified in section 01330 SUBMITTAL PROCEDURES.

1.6.1.1.7 TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraphs entitled "Accreditation Requirements", as applicable.

01450N-5

1.6.1.1.8 TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test. Use Government forms to log and track tests.

1.6.1.1.9 PROCEDURES TO COMPLETE REWORK ITEMS: Procedures to identify, record, track, and complete rework items. Use Government forms to record and track rework items.

1.6.1.1.10 DOCUMENTATION PROCEDURES: Use Government form.

1.6.1.1.11 LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task that is separate and distinct from other tasks and has control requirements and work crews unique to that task. A DFOW is identified by different trades or disciplines and is an item or activity on the construction schedule. The list of DFOWs shall include, but not be limited to, all critical path activities on the NAS. Include all activities for which this specification requires QC Specialists or specialty inspection personnel. Each design development stage and submittal package shall have separate DFOWs in the Network Analysis Schedule.

1.6.1.1.12 PROCEDURES FOR PERFORMING THE THREE PHASES OF CONTROL: Identify procedures you will use to ensure the three phases of control are used to manage the quality on this project. For each DFOW, a Preparatory and Initial phase checklist will be filled out during the Preparatory and Initial phase meetings. The Preparatory and Initial Phases and meetings shall be conducted with a view towards obtaining quality construction by planning ahead and identifying potential problems for each DFOW.

1.6.1.1.13 PERSONNEL MATRIX: Not Applicable.

1.6.1.1.14 PROCEDURES FOR COMPLETION INSPECTION: Procedures for identifying and documenting the completion inspection process. Include in these procedures the responsible party for punch out inspection, pre-final inspection, and final acceptance inspection.

1.6.1.1.15 TRAINING PROCEDURES AND TRAINING LOG: Not Applicable.

1.6.1.1.16 ORGANIZATION AND PERSONNEL CERTIFICATIONS LOG: Procedures for coordinating, tracking and documenting all certifications on…

This is the start of the file's text. The full file is on GovTribe.