Attachment 6 - Site Visit Questions and Answers (Amended-28 May 24).pdf
PDF 108 KB Posted
- Solicitation number
- FA441724Q0140
About this file
This document contains the Questions and Answers from a site visit for the Riptide DFAC Kitchen Equipment Recapitalization RFQ No. FA441724Q0140 for Hurlburt Field AFB, FL. The key details are:
The existing kitchen equipment runs on natural gas, with all doors swinging to the right. The agency prefers installation to occur after 1900 hours, but may be able to accommodate a full-day closure or adjusted meal periods if necessary. The agency can request changes to the electrical configurations, but the contractor will be responsible for hiring a licensed electrician to reconnect any hardwired equipment. The RFQ calls for a solid door on item #16, but the contractor can also provide a quote for one with a glass door. Overall, this document provides clarification and additional details related to the kitchen equipment and installation requirements for this federal contract opportunity.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Ques�ons and Answers
Rip�de DFAC Kitchen Equipment Recapitaliza�on
RFQ No. FA441724Q0140
• Which way do the doors swing on the exis�ng units that have doors?
o All doors swing to the right. The double Vulcan ovens open in the middle and doors swing to each side.
• Of the units that use gas, are all units run off natural gas?
o Yes, all units run off of natural gas.
• Are there any units that run off propane?
o No units run off propane.
• Is third shi� installa�on required?
o Ideally, installa�on would be a�er 1900. If this is not possible, with enough advanced coordina�on, we may be able to close for a day or adjust meal periods.
• During the site visit, the end user men�oned they would like item #1 and #2 would like them beside themselves. Will CE change the plugs so that we can accommodate this?
o We could ask CE to do this but it’s not necessary for us to get the equipment and con�nue to have it staged as is.
• Items #13 and #15 are currently hard wired. Will CE disconnect and provide a receptacle for the new equipment if applicable?
o Item #15 is not hard wired and there is already a work order in progress for CE to do all work required to the building to accommodate item #13.
• Will CE reconnect (Hardwire) the new equipment or is this in our scope?
o No. Reconnec�ng the hardware will require the contractor to hire a licensed electrician.
• Item #16 (Listed as x2). Verify spec is for solid door.
o The spec is for a solid door, but the contractor said they’d provide a quote for one that include a glass door as well.
File details come from the government source that posted it. Updated .