This document is a set of Questions and Responses from a site visit for a federal contract opportunity to repair the HVAC system in Building 91259 at Hurlburt Field.
The key details are:
- The existing duct-mounted smoke detectors must be removed and reinstalled if the ductwork is changed, and they must be tested before and after reinstallation.
- One person can serve as the superintendent, quality control manager, and site safety and health officer if they have the required qualifications.
- No HVAC or electrical system commissioning is required, but the systems must be tested, balanced, and have their controls verified.
- Wave guides may be needed for wall penetrations into the SKIFF area, which could impact the placement of the planned mini-split HVAC units.
- The base operates and maintains the existing control systems, with a local vendor as the installer.
- Duct-mate flanged construction is acceptable for sheet metal tie-ins on the new air handling units.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR HVAC 34TH & 319TH SOS, B91259
SITE VISIT QUESTIONS and RESPONSES
Q1: In each AHU room, the duct-mounted smoke detectors are installed in the coordinating HVAC duct. There are no notes on the drawings concerning duct-mounted smoke detectors. They will have to be removed and replaced when new duct work is installed. If they cannot be installed in the exact same location, will the fire alarm system need to be recertified and retested as part of this project’s scope?
A1: The existing duct smoke detectors are to remain. If the ductwork changes at the smoke detector, the existing duct smoke detectors shall be removed and reinstalled in the new ductwork.
Detectors shall be tested prior to removal and retested after they have been reinstalled.
Q2: Can one person serve as superintendent, quality control manager, and site safety and health officer if they have the experience and training required for each position?
A2: Yes, Super can be QC Manager and Site Safety/Health Officer if he/she has qualifications.
Q3: Is commissioning of HVAC or electrical systems a requirement of this project?
A3: No commissioning is required, however, the systems are to be test and balanced, and operation of the control systems verified.
Q4: At the site visit for Building it was discussed that the mini splits were going to serve the SKIFF area. Will wave guides be required for wall penetrations into the skiff area and if they are required then this will interrupt the communications from the condenser to the wall mount unit. Please confirm if wave guides are required and if they are require will the mins splits be relocated to serve another area in the building.
A4: Answer pending.
Q5: Is there a controls contractor that currently operates and maintains the existing control systems for building?
A5: The base operates and maintains the existing control system. Systems Specialists Inc. out of Pensacola is the local vendor and control system installer.
Q6: Please confirm that duct-mate flanged construction is acceptable for sheet metal ties ins on the new AHU’s for return air, supply air and outside air?
A6: Yes, duct-mate flanged construction is acceptable provided they are installed per manufacture’s recommendations.