QUESTION_AND_ANSWER_CONCERNING_PROPOSAL_SUBMISSION.docx
DOCX document 12 KB Posted
- Attached to
- Repair 12. 47 KV Electrical Basewide Federal contract opportunity
- Solicitation number
- FA4417-17-R-0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA441717R00100002.pdf | ||
| FTEV_12-1069_DRAWINGS_4_Aug_2017.pdf | ||
| ADDENDUM_1.pdf | ||
| FTEV_12-1069_SPECIFICATIONS_-_4_Aug_2017.pdf | ||
| Questions_and_Answers.pdf | ||
| Amendment_1.pdf | ||
| Site_Visit_BRIEF_17R0010.pdf | ||
| 17-R-0010_PreProposal_Sign_In_Sheet_19_July.pdf | ||
| Sol_Atch_5_-_Financial_Worksheet,_17R0010.pdf | ||
| Sol_Atch_2-_FTEV_12-1069_DRAWINGS_Final.pdf | ||
| FA4417-17-R-0010.pdf | ||
| Sol_Atch_3-_Wage_Det,_17R0010.pdf | ||
| Sol_Atch_1-_FTEV_12-1069,_Specifications_Final.pdf | ||
| Sol_Atch_6,_,_Add_Contract_Reqs,_17R0010.pdf | ||
| Sol_Atch_4_-_PPQ,_17R0010.pdf | ||
| Synopsis.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL EMPHASIS
QUESTION AND ANSWER CONCERNING PROPOSAL SUBMISSION
Repair 12.47 KV Electrical Basewide Solicitation Number: FA4417-17-R-0010
PLEASE READ CAREFULLY AND COMPLY
To all interested parties, please be reminded and read carefully the proposal content and submission requirements for your proposal. During questions and answers one firm asked for base access to turn in a hard copy paper proposal. Please note, the Government will not accept paper copies of proposals. The only hard copy document that is required to be delivered is a paper copy of the Bid Guarantee (bid bond) which must arrive before the proposal due date and time. The remainder of your proposal must be submitted ELECTRONICALLY before the proposal due date and time. There are three acceptable methods for submitting electronically and they are detailed in Sections L and M of the solicitation. Please re-read the entire RFP carefully, as well as Sections L and M, to avoid any confusion on proposal submission.
INCOMPLETE PROPOSALS AND PROPOSALS THAT ARE NOT SUBMITTED AS INSTRUCTED WILL BE CONSIDERED NON-RESPONSIVE, WILL NOT BE EVALUATED, AND WILL BE REJECTED.